RESOLVED that the Cabinet: 1. Approve the 2015/16 capital programme of schemes for maintenance and integrated transport as detailed in table 3 of the report submitted. 2. Approve the schemes designated 'A' for construction in 2015/16 as indicated in table 3 of the report submitted, and delegate authority to the Cabinet Member for Public Services, to approve the schemes not designated ‘A’ in table 3 and additionally any schemes proposed in relation to monies received through Challenge Fund bids.
Word for word from the decision Coventry published for this meeting.Source: edemocracy.coventry.gov.uk
1. Approve the 2015/16 capital programme of schemes for maintenance and integrated transport as detailed in table 3 below.
2. Approve the schemes designated 'A' for construction in 2015/16 as indicated in table 3, and delegate authority to the Cabinet Member for Public Services, to approve the schemes not designated ‘A’ in table 3 and additionally any schemes proposed in relation to monies received through Challenge Fund bids.
List of Appendices included:
Appendix 1 – Description of all Maintenance and Integrated Transport schemes. Appendix 2 – Breakdown of the Structural Maintenance Programme. Appendix 3 – Breakdown of the Road Maintenance Programme. Appendix 4 – Proposed Safety Schemes Programme Appendix 5 – Proposed Traffic Management Programme Appendix 6 – Proposed Intelligent Mobility programme.
Has it, or will it be considered by any other council committee, advisory panel or other body? No
The City Council's five year capital programme was approved by Full Council on 24th February 2015.
Will this report go to Council? No Report title: 2015/16 Transportation and Maintenance Capital Programme
1. Context (or background)
1.1This report sets out a detailed capital programme of all Highway Maintenance and Integrated Transport schemes which are due to be carried out during 2015/16. The report sets out individual allocations and the various sources of funding in table 3, and sets out the specific details of each project in appendices 1 to 6.
2. Options considered and recommended proposal
2.1In 2014, the Department for Transport (DfT) consulted on revising its approach to the Highway Maintenance Block allocation formula.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Revenue and Capital Outturn 2025/26RESOLVED that Council be recommended to approve the contribution to reserves of £3.2m for the purposes described in S...
Transport Capital Programme 2026/27RESOLVED that, the Cabinet: 1. Approve delivery of the 2026/27 programmes of Local Network Improvement schemes and Hi...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.