Resolved
It was agreed that this would be looked at by officers and reported to members of the Board by email.
Finance and Corporate Services Scrutiny Board (1) agreed this item on Wednesday 1 July 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
It was agreed that this would be looked at by officers and reported to members of the Board by email.
This report outlines the final revenue and capital outturn position for 2014/15 and reviews treasury management activity and 2014/15 Prudential Indicators reported under the Prudential Code for Capital Finance.
The overall financial position includes the following headline items: Revenue overspending of £2.2m which will be balanced to nil after a planned contribution from the General Fund Balance. £10.3m of costs due to early retirement and voluntary redundancy. This follows and is consistent with approval of the programme of staffing reductions agreed by Cabinet in August 2014. Headline variations including an over-spend of £6.4m within the People Directorate and an under-spend of £5.7m within the Asset Management Revenue Account. Capital Programme expenditure of £101m and capital spending of £22m rescheduled into 2015/16. Overall reserve balances increasing from £81m to £84.5m
Cabinet is requested to: 1. Approve the final revenue outturn position of a £2.2m overspend, balanced to nil by a £2.2m contribution from the General Fund Balance. 2. Recommend to Council that it approves £3m in-year funding of redundancy and retirement costs 3. Approve the final capital expenditure and resourcing position, incorporating expenditure of £101m against a final budget of £124m, borrowing to fund the programme of £0.3m and £22m expenditure rescheduled into 2015/16. 4. Approve the outturn Prudential Indicators position in section 2.4.4 and Appendix 3.
Audit and Procurement Committee is recommended to: 1. Consider the contents of the report and determine whether there are any issues which it wants to refer to the Cabinet Member for Strategic Finance and Resources.
Council is requested to: 1. Approve £3m in-year funding of redundancy and retirement costs.
List of Appendices included:
Appendix 1 Detailed breakdown of Directorate Revenue Variations Appendix 2 Capital Programme Changes and Analysis of Rescheduling Appendix 3 Prudential Indicators
Other useful background papers:
None
Has it been or will it be considered by Scrutiny?
Yes – Scrutiny Board 1, 1st July 2015
Has it been or will it be considered by any other Council Committee, Advisory Panel or other body?
Yes - Audit and Procurement Committee 22nd June
Will this report go to Council?
Yes – 23rd June 2015
2 Report title: Revenue and Capital Outturn 2014/15
1. Context (or background)
1.1This report sets out the Council’s revenue and capital outturn position in 2014/15 and performance against its Prudential Indicators for the year. The City Council set a revenue budget for the year of £259m and a Capital Programme of £142m.
1.2The reported figures show the Council's financial position in relation to management accounts used to monitor performance through the year. The Audit and Procurement Committee will consider separately the Council's Statement of Accounts that shows the financial position in a statutorily prescribed format including technical accounting adjustments that do not reflect how the Council's day to day finances are managed.
2. Options considered and recommended proposal
2.1Revenue Outturn
2.1.1 Table 1 below summarises the outturn position - an overspend of £2.2m prior to a planned contribution from the General Fund Balance which then brings the overall position to a nil variation.
Table 1 Summary Outturn Position
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Revenue and Capital Outturn Report 2014-2015Report | 475 KB | DownloadRead as text |
Follow Finance and Corporate Services Scrutiny Board (1) at Coventry and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 25 Mar 2026 | Update on Savings Delivery and Policy Investment Decisions in 2025-26RESOLVED that the Board note the content of the briefing note and presentation. | Noted | Open |
| 25 Mar 2026 | Home to School TransportRESOLVED that the Board noted the contents of the briefing note and presentation and thanked Officers for their work. | Noted | Open |
| 11 Feb 2026 | Workforce InsightsRESOLVED that the Board note the contents of the report on current workforce data. | Noted | Open |
| 11 Feb 2026 | Distribution of Government FundingRESOLVED that the Board note the presentation and briefing note. | Noted | Open |
| 14 Jan 2026 | Pre Budget Consultation Report 2026/27RESOLVED that the Board: a) Note the contents of the Pre Budget Consultation Report (Appendix 1) which was approved b... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.