Coventry City Council
Communities and Neighbourhoods Scrutiny Board (4), Wednesday 5 April 2017 at 2.00pm

Flood Risk Management and Drainage Update

Decided Scrutiny 1 paper

Communities and Neighbourhoods Scrutiny Board (4) decided this item on Wednesday 5 April 2017. Below is the council's own wording, with the papers it was decided on.

Item35

Resolved

RESOLVED that the Communities and Neighbourhoods Scrutiny Board (4):- (1) Notes the progress of the lead Local Flood Authority as Statutory Consultee on planning applications (2) Notes the outcome of the flooding event that occurred within Coventry on 6 February, 2016 (3) Notes the activities undertaken during the delivery of the annual Drainage Capital Programme
Word for word from the decision Coventry published for this meeting. Source: edemocracy.coventry.gov.uk

Follow this further

Built from Coventry's papers

What the report saysPro

Report to Communities and Neighbourhoods Scrutiny Board (4)

 Briefing note

To: Communities and Neighbourhoods Scrutiny Board

Date: 5th April 2017

Subject: Flood Risk Management and Drainage Update

1 Purpose of the Note 1.1 The Communities and Neighbourhoods Scrutiny Board (4) to note actions from the Board held on 9th March 2016. The actions are attached as an appendix to this report. See appendix 1.

1.2To update the Communities and Neighbourhoods Scrutiny Board (4) on the Lead Local Flood Authority (LLFA) Statutory Consultee role on planning applications

1.3To update the Communities and Neighbourhoods Scrutiny Board (4) on the flooding event that occurred within Coventry on 6th February 2016 at Broad Lane, Upper Eastern Green and Butt Lane, Allersley.

1.4To update the Communities and Neighbourhoods Scrutiny Board (4) on the activities undertaken during delivery of the annual Drainage Capital Programme.

2 Recommendations 2.1 The Communities and Neighbourhoods Scrutiny Board (4) are recommended to: 1) Note the progress of the Lead Local Flood Authority (LLFA) as Statutory Consultee on planning applications. 2) Note the outcome of the flooding event that occurred within Coventry on 6th February 2016 3) Note the activities undertaken during the delivery of the annual Drainage Capital Programme. 4) Identify any further recommendations for the Cabinet Member.

3 Lead Local Flood Authority Statutory Consultee on Planning Applications 3.1 In April 2015, Coventry City Council had its role as LLFA extended to include Statutory Consultee on planning applications.

3.2The Flood Risk Management & Drainage team review planning applications where there is a direct consultation with the planning service on a statutory and non-statutory basis to determine if there is a flood risk to the proposed development or to the local community. The team are also challenged with the review of the weekly list of planning applications submitted in addition to the direct consultations received from planning. Annual average planning applications reviewed by the team have amounted to circa 2300.

3.3Enforceable planning conditions are recommended for all new development and redevelopment sites to ensure this is sustainable for Coventry and future flood risk is

1 managed down. Where deliverable, improvements to existing flood risk are sought in line with the national planning policies of England.

3.4All planning applications are tracked against the 21 day response timescale to help focus resourcing. Collaboration on priorities with the planning service occurs and regular service improvement meetings are being held to ensure well focused service delivery.

4 Coventry City Flooding Event 6th February 2016 – Update 4.1 As previously reported to SB4, during Saturday 6th February 2016 there was prolonged, very heavy, rainfall throughout Coventry causing flooding at a number of locations. The majority of issues reported to the City Council were highway and garden flooding but there were reports of internal flooding at 8 properties.

4.2Broad Lane / Banner Lane / Goldthorn Close 4.3 As part of the new roundabout works associated with the new development site at the Bannerbrook, flood mitigation and drainage improvements were proposed in an effort to address the flooding issue.

4.4The flood mitigation scheme initially considered was river storage on-line, parallel with the Broad Lane, however, excessive Public Utility Service diversion costs and storage volume achievable have proved this part of the scheme to be unviable.

4.5The flood mitigation proposal is now a larger cross boundary scheme with Solihull Metropolitan Council for upstream storage areas on the Brookstray. This larger scheme will deliver increased benefits for the community at risk. In view of the coordination needed with both Coventry and Solihull, the Environment Agency will now lead on this project.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Flood Risk Management and Drainage UpdateReport 65 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 14 attended
NA
Councillor Naeem AkhtarChair, present
RB
Councillor Roger BaileyCommittee Member, present
SB
Suzanne BennettSecretary, in attendance
NC
Neil CowperOfficer, present as substitute
JI
Councillor Jayne InnesBy Invitation, present
BK
Councillor Balvinder KaurCommittee Member, expected
TK
Councillor Tariq KhanCommittee Member, in attendance
RP
Councillor Ram Parkash Lakha OBEBy Invitation, present
MM
Michelle McGintyOfficer, expected
KM
Councillor Keiran MulhallCommittee Member, present
BS
Councillor Bally SinghCommittee Member, present
RS
Councillor Rupinder SinghCommittee Member, present

All 14 on the meeting page

On this subject at Coventry

Search all
  1. Flood Risk Management and Drainage UpdateThis decision
  2. Flood Risk Management and Drainage UpdateNoted
  3. Flood Risk Management and Drainage UpdateNoted

More from Coventry Communities and Neighbourhoods Scrutiny Board (4)

All decisions
MeetingDecisionOutcome
2 Jul 2026 Severe Weather Emergency Protocol UpdateRESOLVED The Communities and Neighbourhoods Scrutiny Board (4) noted the content of the briefing note made the follow... Noted Open
2 Jul 2026 Work Programme 2026/2027RESOLVED that the Communities and Neighbourhoods Scrutiny Board (4) noted the work programme and agreed to add the fo... Noted Open
12 Mar 2026 CCTV in Taxis Task and Finish Group - AddendumRESOLVED The Communities and Neighbourhoods Scrutiny Board (4) made the following recommendations to the Cabinet Memb... Decided Open
12 Mar 2026 Food Waste CollectionsRESOLVED that the Communities and Neighbourhoods Scrutiny Board (4) recommend that the Cabinet Member for City Servic... Decided Open
12 Mar 2026 Work Programme 2025/2026RESOLVED that the Communities and Neighbourhoods Scrutiny Board (4) notes the Work Programme and request an item be a... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies