RESOLVED that the Cabinet: 1. Authorises a procurement process to set up a set of multi-supplier term contracts for 4 years for the provision of property maintenance, repairs and improvements. 2. Delegates authority to the Deputy Chief Executive (Place), following consultation with the Cabinet Member for City Services, to agree the award of contract(s) following a restricted tender process. 3. Authorises the City Council to enter into Contract(s) with the successful suppliers for the 4 years.
Word for word from the decision Coventry published for this meeting.Source: edemocracy.coventry.gov.uk
Name of Cabinet Member: Cabinet Member for City Services - Councillor J Innes
Director Approving Submission of the report: Deputy Chief Executive (Place)
Ward(s) affected: All
Title: Procurement for Term Contracts Project Management and Property Services
Is this a key decision? Yes - The proposals within the report have financial implications in excess of £1m per annum and will affect the whole of the City.
Executive Summary: Coventry City Council’s Compliance and Surveying Team provide a property management service for Council buildings and schools as well as a number of external clients. The works mainly include repairs and maintenance with some property improvements and are undertaken on either a planned or reactive basis depending on the work required. The provision of these works has been via Term Contracts for a number of years.
As the existing term contracts are coming to an end, in order to deliver these works it is proposed to undertake a restricted tender process to set up a multi-lot, multi-supplier (between 2 and 4 suppliers per lot) term contract for a period of 4 years. A term contract is an agreement whereby there is no guarantee of work. However, should there be a requirement for such work the term contractor will be approached. The first placed supplier on each lot will be offered the work. The others will be approached if the first place is unable to undertake the work.
As the spend on these contracts would be in excess of £1million per annum, Cabinet is asked to approve the re-letting of these contracts. Recommendations:
Cabinet is requested to:
1) Authorise a procurement process to set up a set of multi-supplier term contracts for 4 years for the provision of property maintenance, repairs and improvements;
2) Delegate authority to the Deputy Chief Executive (Place), following consultation with the Cabinet Member for City Services, to agree the award of contract(s) following a restricted tender process;
3) Authorise the City Council to enter into Contract(s) with the successful suppliers for the 4 years.
List of Appendices included:
None
Other useful background papers:
Procurement Outline Document (POD) Proc 2 (Gate 2 – Approval to Procure) – Term Contracts Project Management and Property Services. Available by contacting Procurement and Commissioning team on 02476 833757
Has it been or will it be considered by Scrutiny?
No
Has it been or will it be considered by any other Council Committee, Advisory Panel or other body?
No
Will this report go to Council?
No
2 Report title: Term Contracts Property Asset Management
1. Context (or background)
1.1Coventry City Council’s Compliance and Surveying Team delivers a property maintenance repairs and improvement programme covering Council buildings, schools and other external buildings with a spend of circa £3.170M per annum. This is carried out either via our own Repairs and Maintenance workforce or through the use of term contracts.
1.2Capacity limits the ability of our own workforce to carry out all the works required. Their function is primarily reactive repairs. The school customer base require much of the work to be carried out in school holidays which term contractors are able to undertake. This work also attracts fee income.
1.3To enable the delivery of the programme the following works and services are provided by external contractors. The predicted annual spend is shown in brackets: Wet Areas (£200k pa) General Build (£1m pa) Hard Landscaping (£250k pa) Roofing (£1m pa) Flooring (£175k pa) Fencing (£175k pa) Decorations (£250k pa) Ceilings and Partitions (£100k pa) Structural Surveys (£20kpa)
1.4With the exception of Structural Surveys the Council currently has a number of term contracts which commenced in 2013 and expire in August 2017.
1.5The Council has had a similar arrangement to that proposed within this report for the last 4 years and this has been deemed by the client to be successful.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Revenue and Capital Outturn 2025/26RESOLVED that Council be recommended to approve the contribution to reserves of £3.2m for the purposes described in S...
Transport Capital Programme 2026/27RESOLVED that, the Cabinet: 1. Approve delivery of the 2026/27 programmes of Local Network Improvement schemes and Hi...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.