Resolved
RESOLVED that the inclusion of four additional locations, as detailed in Appendix A, in the 2020/21 Local Safety Scheme programme be approved.
City Services approved this item on Monday 15 June 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the inclusion of four additional locations, as detailed in Appendix A, in the 2020/21 Local Safety Scheme programme be approved.
Every year a citywide review of personal recorded injury collisions is undertaken. This information is used to identify and prioritise potential Local Safety Scheme locations. Local safety schemes are installed at locations where there are 6 or more recorded personal injury collisions in a 3 year period, to try to reduce injuries.
On 10th March 2020 Cabinet approved the 2020/21 Local Safety Scheme Programme as part of the 2020/21 Transportation and Highway Maintenance Capital Programme. In addition to the locations identified in the original programme it is proposed to include 4 more locations in the programme. This is to allow for possible delays resulting from engineering difficulties or issues raised at consultation, which may result in it not being possible to introduce all the initial schemes during 2020/2021.
This report is submitted to gain approval for the 4 additional locations to be included in the 2020/21 programme.
The cost of Local Safety Schemes is funded from the Highways Maintenance and Investment Capital Programme budget through the Local Transport Plan
Cabinet Member for City Services is recommended to:
1. Approve the inclusion of four additional locations, as detailed in Appendix A, in the 2020/21 Local Safety Scheme programme
List of Appendices included: Appendix A – Proposed Safety Scheme Locations 2020/21 Background Papers
None
Other useful documents:
Cabinet Report dated 20th March 2020 2020/21 Transportation and Highway Maintenance Capital programme report
Has it been or will it be considered by Scrutiny?
No
Has it been or will it be considered by any other Council Committee, Advisory Panel or other body?
No
Will this report go to Council?
No
2 Report title: Local Safety Scheme Programme 2020/21 – Additional Locations
1. Context (or background)
1.1Each year a citywide review of personal recorded injury collisions is undertaken. This information is used to identify and prioritise potential Local Safety Scheme locations. Local safety schemes are installed at locations where there are 6 or more recorded personal injury collisions in a 3 year period to try to reduce injuries.
1.2On 10th March 2020 Cabinet approved the 2020/21 Local Safety Scheme Programme as part of the 2020/21 Transportation and Highway Maintenance Capital Programme.
1.3Since the approval of the initial programme four additional sites have been identified, as detailed in Appendix A, to be included in this year’s programme. All proposed Local Safety Scheme locations and schemes are subject to further investigation and possible delays resulting from engineering difficulties or issues raised at consultation. This can result in it not being possible to introduce all the originally proposed schemes during 2020/2021, therefore the approval of additional schemes will enable the available budget to be fully utilised.
2. Options considered and recommended proposal
2.1The annual citywide review identified many locations with 6 or more recorded personal injury collisions, these were prioritised as potential Local Safety Scheme locations, including possible ASE schemes. Due to finite resources, not all potential locations identified were included in the 2020/21 programme.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Local Safety Scheme Programme 2020/21: Additional LocationsReport | 243 KB | DownloadRead as text |
Follow City Services at Coventry and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 29 Jul 2026 | Proposed Variation to Hackney Carriage Fares and Authorisation to AdvertiseRESOLVED that the Cabinet Member for City Services: Considers the proposed fare increase submitted by Unite the Union... | Approved | Open |
| 29 Jul 2026 | Petitions Determined by Letter and Petitions Deferred Pending Further InvestigationsRESOLVED that the Cabinet Member for City Services endorses the actions being taken by officers as set out in Section... | Decided | Open |
| 1 Jul 2026 | Petition e34/25-26 - New Zebra Crossing on Nod Rise next to bridge over the brookRESOLVED that the Cabinet Member for City Services: 1. Note the petitioners’ concerns regarding the request for a con... | Noted | Open |
| 1 Jul 2026 | Petition e27-25/26 - New footpath between Pickford Green and Eastern GreenRESOLVED that the Cabinet Member for City Services: Note the petitioners’ concerns Approve the phased approach set ou... | Noted | Open |
| 1 Jul 2026 | Petition 12-24/25 - Remove the Parking Permit Scheme from Zone WGRESOLVED that the Cabinet Member for City Services : Note the petitioners’ request. Defer the decision to a future Ca... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.