RESOLVED that the Communities and Neighbourhoods Scrutiny Board (4): 1. Welcomed and noted the presentation and thanked officers for a very informative presentation. 2. Requested that a location map and the proposed traffic management plan be circulated to members to enable them to better understand how the facility would be accommodated on the site and the plans for traffic management in the area to reduce impact on the surrounding areas.
Word for word from the decision Coventry published for this meeting.Source: edemocracy.coventry.gov.uk
04 February 2021 Scrutiny Board 4 – Project Updates
Planning
• Member approval received at January planning committee • Conditions include; - Traffic management plan to address resident and member concerns - Bio-diversity offset plan in agreement with CCC ecologist - Improvement works to Public Footpath to upgrade and allow pedestrian and cycle access to site for employees MRF Project Board – Project Updates
Project Evolution
• Addition Partners – Stratford and Warwick District Council • Facility Capacity – increased from 120,000 to 175,000 tonnes per annum • Equipment and building size – to accommodate larger facility • Plastics – emerging government legislation • Advanced technology – use of robotics and optics • Photo-voltaic panels – green power source • Insurance – nervous market MRF Project Board – Project Updates
Procurement Update
• Civils contractor – final submission end of Feb • Process (equipment) contractor – Preferred Bidder selection • Operations – Sherbourne Recycling • Final business case and costs - March MRF Project Board – Project Updates
Process Contractor • Technologically advanced solution • Most advanced of its kind in the UK, possibly the world • Highly automated and innovative state of the art facility • Combination of robotics and optics • Processing 47.5 tonnes an hour
The industry has been talking for a few years about the MRF of the future, but this time we can really say that we will make it happen. This will be a game changer and a loud statement within the market Comments Jonathan Ménard, Executive VP of Sales and Strategic Positioning at Machinex. MRF Project Board – Project Updates
Process Contractor
• Experienced contractor • Value engineering underway prior to final tender submission • Supporting improvements at Whitley Depot to accommodate access route MRF Project Board – Project Updates
Next Steps
• Final tender submission and financial modelling – end of Feb / early March • Contact Award – 01 April 2021 • Works commence on site – May 2021 • Operational site – Spring / early Summer 2023
• Shareholder Panel – first meeting late Feb / early March MRF Project Board – Project Updates
Recommendation The Communities and Neighbourhood Board are recommended to consider and note the contents of the presentation.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Communities and Neighbourhoods Scrutiny Board (4) at Coventry and we tell you when its next papers are published, before the meeting rather than after it.
Severe Weather Emergency Protocol UpdateRESOLVED The Communities and Neighbourhoods Scrutiny Board (4) noted the content of the briefing note made the follow...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.