That the Committee were minded to approve those elements of the application within the administrative area of Coventry City Council subject to conditions, a Section 106 Agreement being entered into by the applicant in respect of those matters, including matters where further clarification is awaited, as highlighted in this report which relate directly to those matters under the City Council’s jurisdiction, and the Secretary of State not wishing to intervene regarding determination of the application. 2. That authority be delegated to the Strategic Lead for Planning to issue the planning permission together with the power to make any amendments to the conditions and any contributions set out within the report, which are considered necessary in relation to Application OMES/2021/2268
Word for word from the decision Coventry published for this meeting.Source: edemocracy.coventry.gov.uk
Planning Committee Report Planning Ref: OMES/2021/2268 Site: Coventry Airport, Rowley Road, CV3 4FR Ward: Binley and Willenhall Proposal: Outline planning application with all matters reserved apart from access (which is submitted in detail) for the development of a battery manufacturing facility with ancillary battery recycling capability including landscaping, car parking, access and associated works. The application is accompanied by an Environmental Statement. The proposed development may not accord with the provisions of the Development Plan in force in the area in which the land to which the application relates is situated. (Departure Application) This is a cross-boundary planning application, meaning that the site is also located within Warwick District and therefore an identical planning application has been made to Warwick District Council Case Officer: Daniel Taylor
INTRODUCTION
Coventry Airport is owned by Coventry City Council (CCC). Coventry Airport Ltd (CAL) have a long leasehold interest in, and operate, the airport. Both parties are the Applicant for this application and have entered a Joint Venture Arrangement to promote and develop the airport for a Gigafactory. The Gigafactory would occupy the entirety of the airport site with all airport related operations and the businesses operating from the site ceasing.
A “Gigafactory” is a facility to manufacture batteries for electric vehicles and a range of other applications at scale. Due to the global demand for battery production, this is only set to keep rising. Gigafactories are now the established method for battery production by manufacturers. There are currently no such facilities of anything approaching this scale in the UK, although Gigafactories have been delivered in the United States, Europe, and Asia. The applicant states that the continued absence of large-scale battery production to support the ongoing Electric Vehicle (EV) sector in the UK seriously risks undermining the future automotive and other battery enabled sectors with a consequential adverse impact upon jobs and supply chain.
The Government has identified Gigafactories as critical to the UK’s automotive sector, future economic growth, and Net Zero targets. The applicant states that the West Midlands has been chosen as a potential location for a UK Gigafactory due to its mature automotive sector; emerging specialism in battery technology; strength in manufacturing, research and development; skilled and available workforce; and location in the centre of the country. Coventry Airport has been identified as the preferred site for a West Midlands Gigafactory by the West Midlands Combined Authority, Coventry City Council, Warwick District Council, Warwickshire County Council, and Coventry and Warwickshire Local Enterprise Partnership (LEP), via their representation on the West Midlands Electrification Taskforce.
The application is an Outline application with all matters reserved for future determination save for the principal means of access to the site. Whilst the detail for the majority of the proposal is yet to be submitted, parameters are set as part of this Outline application which define the extent of the type, scale and distribution of the development proposed on the site, within which future Reserved Matters applications will be submitted. The parameters set for aspects such as the factory’s height, overall size, and distribution of massing around the site, have been influenced by a knowledge of the likely future market and processes involved in operating such a facility. The likely future operator is not yet known and discussions on this remain commercially confidential at this stage.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.