Palmer Lane Regeneration 2023 Update

Approved Executive 2 papers

Cabinet approved this item on Tuesday 11 July 2023. Below is the council's own wording, with the papers it was decided on.

Item10

Resolved

RESOLVED that Cabinet: (1) Approves the additional funding of £318k for the delivery of the Palmer Lane project taking the total budget for the delivery of the scheme to £2.4m. The additional funding will be added to the 5-year capital programme. (2) Notes the grant acceptance of £534k received from Historic Coventry Trust in March 2023 under delegated authority contained in paragraph 2.3.2 (c) of Part 3F (Financial Procedure Rules) of the Council Constitution. (3) Notes the delegated authority provided to the Director of Transportation and Highways following consultation ( by ... view the full minutes text for item 10.
Word for word from the decision Coventry published for this meeting. Source: edemocracy.coventry.gov.uk

Follow this further

Built from Coventry's papers

What the report saysPro

Report to Cabinet

Executive summary

Since 2019 the Council has transformed the city centre through a £44m programme of investment in the public realm. The impact of this work has been significant, attracting developers to invest in the city and creating a legacy for residents and those living and working in the city.

Palmer Lane is a proposed regeneration scheme that includes deculverting the River Sherbourne and hard and soft landscaping around the area to create a new city centre place for dwell time and supporting the establishment of a new business in the Illingworth building.

The scheme was first approved by Cabinet as part of the Public Realm Phase 5 report in March 2018, as a complement to the Public Realm 5 (PR5) works taking place in the city centre and to develop designs for the proposal. During 2021 there was an additional need identified for a further £950k to fund the overall regeneration of Palmer Lane as well as approve the external funding contributions towards the project. This was given approval in a Cabinet Member report in July 2021.

The Palmer Lane project has continued to detailed design level throughout the year of 2021 and 2022 to a point where final designs are in place and legal land agreements are concluded.

Following early contractor engagement with a framework construction company the project will need further funding in order to deliver the overall Palmer Lane scheme. This increase in cost is a consequence of high inflation over the last 12 months and increases in labour and material costs that we have seen during 2022/2023. This report therefore also seeks approval for an additional ask of £318k to be funded from corporate reserves. This report also seeks to report to Cabinet a grant acceptance from Historic Coventry Trust (HCT) of £534k which took place in March 2023, this was an increase of £155k from the previous approved HCT contribution of £379k. Due to the urgency required to accept the grant funding, this was accepted under delegated powers in accordance with the provisions of the Council Constitution.

Recommendations

The Cabinet is recommended to:

(1) Approve the additional funding of £318k for the delivery of the Palmer Lane project taking the total budget for the delivery of the scheme to £2.4m. The additional funding will be added to the 5-year capital programme.

(2) Note the grant acceptance of £534k received from Historic Coventry Trust in March 2023 under delegated authority contained in paragraph 2.3.2 (c) of Part 3F (Financial Procedure Rules) of the Council Constitution.

(3) Note the delegated authority provided to the Director of Transportation and Highways following consultation (by way of the Cabinet Member report dated 15th July 2021) to conclude negotiations and enter into legal agreements with the various landowners for parcels of land to be acquired or leased by the Council and/or for licences to be entered into to enable works to be carried out and for agreements to be entered into and/or for leases to be granted by the Council to third parties over land in the Council’s ownership in order for the scheme to be viable and to Authorise any variations related to such legal agreements.

(4) Note the continued exercise of the delegated authority provided (by way of the Cabinet Member report dated 15th July 2021) to commence the procurement in order to appoint a works contractor through an approved procurement framework.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
05) Appendix 1Appendix 773 KB Download
PDF
Palmer Lane Regeneration 2023 UpdateReport 513 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

19 of 37 attended
MD
Megan DrageOfficer, expected
OA
Oluremi AremuOfficer, expected
AW
Adrian WestOfficer, expected
EA
Elaine AttheyOfficer, expected
JW
Julie WheelerOfficer, expected
PH
Phil HelmOfficer, expected
PA
Councillor Pervez AkhtarDeputy Cabinet Member, expected
KC
Councillor Kamran CaanCommittee Member, present
GA
Councillor George Arthur DugginsChair, present
AS
Councillor Abdul Salam KhanDeputy Chair, apologies
JO
Councillor Jim O'BoyleCommittee Member, present
DS
Councillor David Stuart WelshCommittee Member, present

All 37 on the meeting page

On this subject at Coventry

Search all
  1. Palmer Lane Regeneration 2023 UpdateThis decision
  2. Palmer Lane RegenerationApproved

More from Coventry Cabinet

All decisions
MeetingDecisionOutcome
7 Jul 2026 Revenue and Capital Outturn 2025/26RESOLVED that Council be recommended to approve the contribution to reserves of £3.2m for the purposes described in S... Approved Open
7 Jul 2026 Acceptance of the Music Hub Revenue Grant for the Strategic Area of Coventry, Warwickshire and SolihullRESOLVED that, the Cabinet: 1. Approve acceptance of the revenue grant for the academic year 2026/27 from ACE of £1,7... Approved Open
17 Mar 2026 Private Sector Housing Enforcement Policy 2026-31RESOLVED that the Cabinet recommend that the policy be reviewed by full Council for approval. Approved Open
17 Mar 2026 Coventry: City of Movement Strategy 2026-2031RESOLVED that, the Cabinet: 1. Note and accept the additional recommendation from the Scrutiny Co-ordination Committe... Approved Open
17 Mar 2026 Transport Capital Programme 2026/27RESOLVED that, the Cabinet: 1. Approve delivery of the 2026/27 programmes of Local Network Improvement schemes and Hi... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies