RESOLVED that Cabinet: 1) Approves the acceptance of the Additional WMCA Funding of up to £12.24m to be added to the £98.8m previously secured which will be utilised to facilitate the delivery of City Centre South. 2) ... view the full minutes text for item 71.
Word for word from the decision Coventry published for this meeting.Source: edemocracy.coventry.gov.uk
City Centre South (CCS) will deliver transformational improvements to Coventry city centre through the creation of a new residential led community providing new homes, jobs, commercial and leisure opportunities and high-quality public spaces.
The Council’s development partner, Shearer Property Regen Ltd (SPRL), led by Hill Developments are continuing to move the scheme forward and have made considerable progress since being appointed as the funding partner under the terms of the Development Agreement between the Council, SPRL and Shearer Property Group (SPG). This report seeks formal approval to the next stage of the project following the previous Council Decisions in December 2022 which approved the provision of Council funding to the scheme.
Since the recommendations contained within the December 2022 report were approved, a significant amount of work has been undertaken to progress the scheme, including the Compulsory Purchase Order (CPO) being confirmed by the Secretary of State, the delivery of high-quality new premises for the Shopmobility scheme and a significant amount of ground investigations and surveys being undertaken. However, changes in fire safety regulations proposed earlier this year in the wake of the Grenfell disaster have required changes to the design of, and timescales for, the scheme resulting in viability challenges which need to be resolved before the scheme can commence further.
These changes announced by Michael Gove, Secretary of State for Levelling Up, Communities & Housing, in July 2023 will require all residential buildings over 18m in height to incorporate dual stair cores and additional fire-fighting lifts to improve means of escape and building safety in the event of fire. This change was not anticipated at the time the previous report was considered.
This change in regulation has had a significant, adverse effect on scheme viability due to increasing build costs and reduced sales/lettable area, thus depressing overall scheme viability. In order to address this issue and to prevent the scheme from stalling the Council has been able to successfully negotiate an additional grant assistance from the West Midlands Combined Authority (WMCA) of up to £12.24m (“Additional WMCA Funding”) in addition to the £98.8 million pounds already provided.
This report, therefore, requests authority to accept the Additional WMCA Funding and to request delegated authority to amend the Development Agreement with SPRL and Grant Agreements with WMCA in order to be able to apply this funding towards the delivery of the scheme.
Recommendations
Cabinet is asked to recommend that Council:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Revenue and Capital Outturn 2025/26RESOLVED that Council be recommended to approve the contribution to reserves of £3.2m for the purposes described in S...
Transport Capital Programme 2026/27RESOLVED that, the Cabinet: 1. Approve delivery of the 2026/27 programmes of Local Network Improvement schemes and Hi...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.