RESOLVED that the City Council: 1) Approves capital expenditure of a maximum of up to £10.28m to be financed from borrowing, to fund the LED upgrade of up to 29,500 streetlights with up to 1 in 5 having smart sensor ports. 2) Delegates authority to the Director of Innovation, Director of City Services & Commercial and the Director of Law and Governance and the Director of Finance and Resources, following consultation with the Cabinet Member for City Services, to enter into and finalise the financial and legal terms necessary to implement the LED upgrade via the appropriate mechanism contained within the PFI Streetlighting Agreement.
Word for word from the decision Coventry published for this meeting.Source: edemocracy.coventry.gov.uk
This report seeks approval from Cabinet and Council to approve investment of £10.28m to progress with the upgrade of the majority of the city’s streetlights (29,500) to LEDs.
In 2023/24 the Authority spent £3.4m on energy for streetlights; based on 38p kwh. We have an opportunity to reduce revenue costs by investing in energy efficient LED street lighting technology, which use approximately 50% less energy than our current lights. LEDs also have a much lower maintenance requirement. Overall, this will result in savings of over £900k based on current consumption which will more than cover the borrowing cost as well as delivering all the other benefits. The lower energy consumption will result in a reduction of our carbon emissions by 1200 tonnes per annum.
LEDs will provide resilience to changes in energy prices which can be impacted by world affairs. LED lighting will provide the City Council with the opportunity to dim the lights to as low as 30% whilst still providing the same quality of our current lighting at 50% dim. This will enable a review of the part night switch off policy and to potentially generate additional savings. The LED upgrade also offers the opportunity to help make Coventry a ‘Smart City’ by incorporating smart sensor ports in 1 in 5 of the new lanterns. This will offer opportunity to easily collect environmental data (air quality, noise, or traffic flows for example) across the whole city.
Recommendations
Cabinet is recommended to request that Council:
1) Approves capital expenditure of up to £10.28m to be financed from borrowing, to fund the LED upgrade of up to 29,500 streetlights with up to 1 in 5 having smart sensor ports.
2) Delegates authority to the Director of Innovation and the Director of Law and Governance and the Director of Finance and Resources, following consultation with the Cabinet Member for City Services, to enter into and finalise the financial and legal terms necessary to implement the LED upgrade via the appropriate mechanism contained within the PFI Streetlighting Agreement.
Council is requested to:
1) Approve capital expenditure of a maximum of up to £10.28m to be financed from borrowing, to fund the LED upgrade of up to 29,500 streetlights with up to 1 in 5 having smart sensor ports.
2) Delegate authority to the Director of Innovation, Director of City Services & Commercial and the Director of Law and Governance and the Director of Finance and Resources, following consultation with the Cabinet Member for City Services, to enter into and finalise the financial and legal terms necessary to implement the LED upgrade via the appropriate mechanism contained within the PFI Streetlighting Agreement.
List of Appendices included:
Appendix 1 – Equality Impact Assessment Form
Background papers
None
Other useful documents
None
Has it or will it be considered by Scrutiny?
No – however the matter will be considered by the Communities and Neighbourhoods Scrutiny Board (4) on 30th January 2025 Has it or will it be considered by any other Council Committee, Advisory Panel or other body?
Leadership Board: 09 July 2024 Member Briefing: 25 July 2024 Political Cabinet: 07 October 2024 Labour Group: 21 October 2024
Will this report go to Council?
Yes - 14th January 2025 Report title: PFI Street Lighting LED Upgrade
1. Context (or background)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Election of the Leader of the CouncilRESOLVED that Councillor George Duggins be duly elected as Leader of the Council. Note 1): In accordance with Council...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.