RESOLVED that Cabinet: 1. Approve delivery of the 2025/26 programmes of local network improvements and highways maintenance schemes, as set out in Appendices 1 - 3 of the report 2. Delegate authority to the Director of City Services and Commercial, following consultation with the Cabinet Member for City Services and the Director of Finance and Resources, to: · accept any funding that is secured via this fund up to a maximum sum of £2.5 million pounds · add any schemes which receive sufficient funding to the five-year capital programme and approve their delivery 3. Note the latest update on arrangements for future transport funding to be received as part of the West Midlands Integrated Settlement
Word for word from the decision Coventry published for this meeting.Source: edemocracy.coventry.gov.uk
The Coventry Transport Strategy was approved by Council in December 2022. It is a 15- year Strategy which sets out plans to fundamentally change the city’s transport system, including by investing in significant improvements to public transport, walking and cycling and by accelerating the transition to zero emission vehicles.
This report includes details of a number of capital programmes which will be delivered over the coming year. This includes a £3.1m programme of local network improvements, an £11.9m programme of highways maintenance and up to £2m (subject to funding approval) of further improvements to walking and cycling. These programmes form part of the Council’s wider commitment to deliver the changes set out in the Coventry Transport Strategy.
Funding sources for these programmes include the City Region Sustainable Transport Settlement (CRSTS) and tranche 5 of the Active Travel Fund (ATF5). In the future, both CRSTS and ATF funding will be absorbed into the West Midlands’ wider Integrated Settlement, along with several of further sources of transport funding. Recommendations:
Cabinet is recommended to:
1. Approve delivery of the 2025/26 programmes of local network improvements and highways maintenance schemes, as set out in Appendices 1 - 3 of the report
2. Review the latest update on Active Travel Fund tranche 5 and delegate authority to the Director of City Services and Commercial, following consultation with the Cabinet Member for City Services and the Director of Finance and Resources, to:
accept any funding that is secured via this fund up to a maximum sum of £2.5 million pounds add any schemes which receive sufficient funding to the five-year capital programme and approve their delivery
3. Review the latest update on arrangements for future transport funding to be received as part of the West Midlands Integrated Settlement
List of Appendices included:
Appendix 1 – Local Network Improvement Programme 2025-26 Scheme List Appendix 2 – Highways Maintenance Description of Maintenance Schemes Appendix 3 – Highways Maintenance Scheme Locations
Background papers
None
Other useful documents:
The Coventry Transport Strategy and accompanying Implementation Plan are published on the Council’s website at https://www.coventry.gov.uk/transport-strategy-2
Has it or will it be considered by Scrutiny?
No
Has it or will it be considered by any other Council Committee, Advisory Panel or other body?
The Transport Capital Programme will also be considered by the Council’s Leadership Board. At the time of writing, the date for this meeting is to be confirmed.
Will this report go to Council?
No Report title: 2025/26 Transport Capital Programme
1. Context (or background)
1.1The Coventry Transport Strategy was approved by Council in December 2022. It is a 15-year Strategy which sets out plans to fundamentally change the city’s transport system, including by investing in significant improvements to public transport, walking and cycling and by accelerating the transition to zero emission vehicles.
1.2The Strategy is accompanied by a detailed Implementation Plan setting out the ‘pipeline’ of specific improvements that the Council intends to deliver over the lifetime of the Strategy, with a particular emphasis on years 1-5. This Plan was approved at the same time as the Strategy but has subsequently been updated, with some minor changes being approved by Cabinet in October 2024.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Revenue and Capital Outturn 2025/26RESOLVED that Council be recommended to approve the contribution to reserves of £3.2m for the purposes described in S...
Transport Capital Programme 2026/27RESOLVED that, the Cabinet: 1. Approve delivery of the 2026/27 programmes of Local Network Improvement schemes and Hi...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.