Resolved
RESOLVED that, subject to the consideration of the additional confidential information contained within the corresponding Private report, Coventry Shareholder Committee approve the UKBIC Business Plan.
Coventry Shareholder Committee approved this item on Wednesday 26 March 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that, subject to the consideration of the additional confidential information contained within the corresponding Private report, Coventry Shareholder Committee approve the UKBIC Business Plan.
UKBIC is a state-of-the-art battery manufacturing research and development facility, funded by £114m from the UK Government (through Innovate UK, part of UK Research & Innovation) and £18m from the West Midlands Combined Authority (WMCA). The facility is operated by UKBIC Ltd which is owned by Coventry City Council (CCC). The Council is also accountable body for the grant funding used to establish the facility.
This report recommends approval of the UKBIC Business Plan for 25/26 which is included at as an appendix to the corresponding private report. Recommendations:
The Coventry Shareholder Committee is recommended to:
1. Approve the UKBIC Business Plan attached to Appendix 1 of the corresponding private report
List of Appendices included: None.
Background papers: None.
Other useful documents None.
Has it or will it be considered by Scrutiny? No.
Has it or will it be considered by any other Council Committee, Advisory Panel or other body? No.
Will this report go to Council? No. Report title:
1. Context (or background)
1.1The UK Battery Industrialisation Centre (UKBIC) Limited is a state of the art, 20,000m2 battery manufacturing research and development facility on Rowley Road which was formally opened in July 2021. UKBIC is an open access facility designed to allow UK manufacturers to trial and industrialise the next generation of batteries for electric vehicles and other applications, which is essential to the UK’s net zero ambitions.
1.2Between November 2017 and October 2019, the Council approved the acceptance of £114m grant funding from Innovate UK’s Faraday Battery Challenge towards the total cost of £132m to develop the UKBIC facility. The remaining £18m was provided in the form of a loan from WMCA, with repayments secured through an arrangement put in place with UKBIC Ltd ensuring that the Council is put in funds.
1.3The Faraday Battery Challenge was established by government in 2018 to invest in research and innovation projects, and facilities, to drive the growth of a strong battery business in the UK. Securing UKBIC in the Coventry area is critical to the future of the area’s world-class automotive and advanced manufacturing cluster.
1.4UKBIC Ltd (company no. 11227726) was established in order to operate the facility. CCC owns 100% of the shares in UKBIC Ltd and has two CCC directors who sit on the board, including the Chair. The remaining board seats are made of up of the UKBIC Managing Director and Finance Director, a representative from Government’s Advanced Propulsion Centre (APC) and independent battery / automotive industry experts. In addition, a Faraday Challenge Director attends the board as an observer.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
UKBIC Business Plan 2025/26Report | 151 KB | DownloadRead as text |
Follow Coventry Shareholder Committee at Coventry and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 15 Apr 2025 | Council Acting as Charitable Trustees for War Memorial Park regarding the site of the Former Wisteria LodgeRESOLVED that Coventry Shareholders Committee: 1) In its role as charitable trustee of the War Memorial Park and in t... | Agreed | Open |
| 26 Mar 2025 | Exclusion of Press and PublicRESOLVED that the press and public be excluded under Section 100(A)(4) of the Local Government Act 1972 for the consi... | Decided | Open |
| 26 Mar 2025 | Coventry Municipal Holdings Limited - Accounts for the Year Ending 31st March 2024RESOLVED that, the Coventry Shareholder Committee: 1. Considered and noted the comments received from the Scrutiny Co... | Noted | Open |
| 26 Mar 2025 | Coventry and Warwickshire Growth Hub Business Plan (Financial Year 2025/26)RESOLVED that, the Coventry Shareholder Committee approve the Coventry and Warwickshire Growth Hub Business Plan and ... | Approved | Open |
| 26 Mar 2025 | Business Planning Cycle for 2025/26 for the Coventry Municipal Holdings GroupRESOLVED that, subject to the consideration of the additional confidential information contained within the correspon... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.