RESOLVED that Cabinet:- 1) Approves the Council’s first quarter revenue monitoring position. 2) Approves the revised forecast capital outturn position for the year of £187.6m incorporating: £16m rescheduling from 2024/25 outturn, £1.9m net increase in spending relating to approved/technical changes and £1.9m of net programme rescheduling of expenditure to future years.
Word for word from the decision Coventry published for this meeting.Source: edemocracy.coventry.gov.uk
The purpose of this report is to advise Cabinet of the forecast outturn position for revenue and capital expenditure and the Council’s treasury management activity as at the end of June 2025. The net revenue forecast position after management action is for spend in 2025/26 of £1.6m over budget. Whilst not a wholly comparable position, at the same point in 2024/25, there was also a projected overspend of £7.1m.
The Council continues to face budget pressures within Adults’ Social Care, with overspends also being reported in Property Services and Development, Regeneration and Economic Development and City Services. These financial pressures are being caused by a combination of continued service demand, complexity & market conditions in social care, legacy inflation impacts, and income shortfalls due largely to the economic climate.
The Council’s capital spending is projected to be £187.6m and includes major schemes progressing across the city. The size of the programme and the nature of the projects within it continue to be fundamental to the Council’s role within the city. Although prevailing inflation rates look to be stabilising, legacy inflationary pressures continue to affect capital projects. We will continue to monitor this position and ensure projects are delivered within available resources. Recommendations:
The Cabinet is requested to:
1) Approve the Council’s first quarter revenue monitoring position.
2) Approve the revised forecast capital outturn position for the year of £187.6m incorporating: £16m rescheduling from 2024/25 outturn, £1.9m net increase in spending relating to approved/technical changes and £1.9m of net programme rescheduling of expenditure to future years.
Audit and Procurement Committee is requested to:
1) Consider the proposals in the report and forward any recommendations to the Cabinet.
List of Appendices included:
Appendix 1 - Revenue Position: Detailed Service breakdown of forecast outturn position Appendix 2 - Capital Programme: Analysis of Budget/Technical Changes Appendix 3 - Capital Programme: Analysis of Programme Acceleration/(Rescheduling) Appendix 4 - Prudential Indicators
Background papers
None
Other useful documents
None
Has it been or will it be considered by Scrutiny?
No
Has it been or will it be considered by any other Council Committee, Advisory Panel or other body?
Yes - Audit and Procurement Committee, 22nd September 2025
Will this report go to Council?
No Report title: 2025/26 First Quarter Financial Monitoring Report (to June 2025)
1. Context (or background)
1.1Cabinet approved the City Council's revenue budget of £296.7m on the 25th February 2025 and a Capital Programme of £171.6m. This is the first quarterly monitoring report for 2025/26. The purpose is to advise Cabinet of the forecast outturn position for revenue and capital expenditure, recommending any action required, and to also report on the Council’s treasury management activity.
1.2The current 2025/26 revenue forecast is for net expenditure to be £1.6m over budget (after management action). The reported forecast at the same point in 2024/25 was an overspend of £7.1m which reflected pressures relating primarily to social care activity and price. 2025/26 capital spend is projected to be £187.6m.
1.3Whilst it is not unusual to experience a forecast overspend at this point, it is essential that the Council maintains strict financial discipline to operate within approved budgets.
2. Options considered and recommended proposal.
2.1This is a budget monitoring report and as such there are no options.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Revenue and Capital Outturn 2025/26RESOLVED that Council be recommended to approve the contribution to reserves of £3.2m for the purposes described in S...
Transport Capital Programme 2026/27RESOLVED that, the Cabinet: 1. Approve delivery of the 2026/27 programmes of Local Network Improvement schemes and Hi...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.