AI summaryCoventry Cabinet Member approved a Listed Building Application to demolish the Grade II listed former Swimming Baths on Fairfax Street, with £50,000 from Homes England and £252,000 from council capital receipts towards a £514,000 cost shared with CRL.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedDemolition of former Coventry Swimming Baths
Money£514,000Total cost of application, shared with CRL
What happens nextSubmit before Christmas 2025Three year window to fund demolition
Who it affectsFormer Coventry Swimming BathsAnd CRL regeneration partnership on Fairfax Street
What was decided
Approved work to bring forward a Listed Building Application to demolish the former Coventry Swimming Baths in Fairfax Street. Report P5
Accepted £50,000 grant funding from Homes England as part of the Council's contribution to the application costs. Report P6
Approved using £252,000 from existing capital receipts to fund the rest of the Council's contribution, with the balance of the £514,000 total to be provided by CRL; also approved varying the existing Exclusivity Agreement with CRL. Report P7, P8
Why
The baths have been closed since 2020 and no realistic reuse option has been brought forward despite extensive marketing; mothballing costs the taxpayer approximately £400k per year. Report P1, 1.3, 1.4
Historic England has confirmed it will not object to a demolition application and considers the planned approach pragmatic. Report P2, 3.1
A previous financial appraisal of an exhibition, leisure and food hall option showed a funding gap of c.£13m. Report 1.3
What happens next
Submit the Listed Building Application to the Local Planning Authority before Christmas 2025. Report 4.1
If consent is granted, work over a three year period to secure the funding needed for the actual demolition. Report 4.1, P39
Bring a further report back to governance to agree future delivery arrangements, demolition funding, and implementation of any planning consent. Report P39
The money
£50,000 Grant funding from Homes England towards the Council's contribution to the Listed Building Application Report P6, 1.6
£252,000 Council funding from existing capital receipts for the remainder of its contribution Report P7
£514,000 Total cost of preparing and submitting the Listed Building Application, with the remaining cost provided by CRL Report P7
£400k per year Current annual mothballing, security and maintenance costs for the Swimming Baths and The Elephant Report P2, 1.4
c.£13m Funding gap identified in a previous financial appraisal of an exhibition, leisure and food hall reuse option Report 1.3
Options considered
Rejected: Continue to market the site to occupiers and investors. No financially realistic proposals have come forward despite extensive marketing since 2021 and the building is deteriorating Report 2.1, P34
Rejected: Take forward the demolition application without a partner. No compelling reason for the Council to fund all costs alone and a specialist partner adds significant value to a specialist application Report 2.2, P36, P37
Chosen: Take forward the demolition application in partnership with CRL, varying the Exclusivity Agreement. Builds on existing partnership work and engagement with Historic England; spreads cost between the Council and CRL Report 2.3, P39
Implications
Legal: Relies on the general power of competence in section 1 of the Localism Act 2011. A grant drawdown agreement with Homes England is required, and the existing Exclusivity Agreement with CRL will be amended. Report P45, P46, P47
Risk: Confidence that the Listed Building Application will be granted is based on Historic England stating it will not object and that the Council's approach of separating demolition from any future replacement scheme is pragmatic. Report P52, 3.1
Equalities: A full Equality Impact Assessment is not required because the proposal relates to a planning application to demolish a vacant, derelict building. Report 6.4, P57
Climate: No climate or environment implications at this stage; any future demolition would be managed under the Council's environmental management policies. Report 6.5, P59
Staffing: Main impact is on staff resources within the Property and Development service area. Report 6.3, P55
Who and where
Coventry City Council, as applicant for the Listed Building Application and owner of the mothballed building Report P1, 1.2
Coventry Regeneration Limited (CRL), Special Purpose Vehicle of Redford Developments Limited, as joint funder and exclusivity partner Report P1, 2.3
Homes England, providing the £50,000 grant Report P6, 1.6
Historic England, consultee on the application Report P2, 3.1
Local Planning Authority, decision maker on the Listed Building Application Report 4.1
Taxpayers in Coventry, currently bearing the £400k per year mothballing cost Report P2, 1.4
The Elephant building (adjacent Sports Centre), which remains in active marketing alongside this decision Report 1.3, 1.5
Timeline
2020: Coventry Swimming Baths closed to the public Report 1.1
February 2019: Cabinet declared the Swimming Baths surplus to requirements and consented to disposal Report 1.2
Since 2021: Active marketing of the Swimming Baths and The Elephant by Avison Young and in Council and WMCA investment prospectuses Report P34
June 2026: Current Exclusivity Agreement with CRL runs until this date Report P37
Before Christmas 2025: Listed Building Application to be submitted to the Local Planning Authority Report 4.1
Three year period after consent: Window in which to secure funding for the demolition works to commence Report 4.1, P39
Plain English for the jargon
CRL: Coventry Regeneration Limited, a Special Purpose Vehicle of Redford Developments Limited (previously called Rainier)
Listed Building Consent: Planning permission required to demolish or alter a listed building, in this case the Grade II listed former Swimming Baths
Exclusivity Agreement: Agreement giving CRL sole rights to bring forward proposals for the site, which would be varied as part of this decision
EIA: Equality Impact Assessment
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item10
Resolved
RESOLVED that the Cabinet Member for Jobs, Regeneration and Climate Change, subject to consideration of the corresponding private report, : 1) Approves proposals to take forward the necessary work to bring forward a Listed Building Application for the demolition of the former Coventry Swimming Baths in Fairfax Street 2) Approves the acceptance of £50,000 grant funding from Homes England to be utilised towards the Council’s contribution to the costs of the Listed Building Application 3) Approves the use of £252,000 from existing capital receipts to fund the remainder of the Council’s contribution towards the £514,000 cost of the preparation and submission of the Listed Building Application, with the remaining cost being provided by CRL. 4) Authorises that the existing Exclusivity Agreement between the Council and CRL be varied to align with the principles set out in the Heads of Terms contained at Appendix 1 of the corresponding private report. 5) Delegates authority to ... view the full minutes text for item 10.
Word for word from the decision Coventry published for this meeting.Source: edemocracy.coventry.gov.uk
Report to Jobs, Regeneration and Climate Change, 8 pages
Executive summary
The former Coventry Swimming Baths on Fairfax Street have been closed since 2020. During that time, the Council has been working with its regeneration partner Coventry Regeneration Limited (“CRL”), who are a Special Purpose Vehicle of Redford Developments Limited (previously called “Rainier”), to undertake extensive and comprehensive work to seek viable and sustainable uses for the buildings. Despite extensive efforts, no realistic reuse option has been able to be brought forward.
The cost of mothballing the former Swimming Baths is currently costing the taxpayer approx. £400k per year. Given that there is no realistic chance of reuse of the buildings, as well as the cost to the public purse, the Council wishes to take forward the necessary steps set out below in order to realise the demolition of the buildings: Prepare and submit an application to secure a Listed Building Consent (the Swimming Baths are Grade II listed) for the demolition of the buildings. The Council will jointly fund the cost of this work with CRL. As part of the work to date, there has been extensive engagement with Historic England and they confirmed that they will not object to an application for the demolition of the Swimming Baths.
Once a consent is secured, this will put the Council in the best place to seek to secure the funding required for the actual demolition of the buildings. This will also pave the way working alongside CRL to undertake further work to ultimately realise a high quality regeneration scheme on the site of the former Swimming Baths for the benefit of Coventry and its communities.
Recommendations
The Cabinet Member for Jobs, Regeneration and Climate Change is recommended to:
1) Approve proposals to take forward the necessary work to bring forward a Listed Building Application for the demolition of the former Coventry Swimming Baths in Fairfax Street
2) Approve the acceptance of £50,000 grant funding from Homes England to be utilised towards the Council’s contribution to the costs of the Listed Building Application
3) Approve the use of £252,000 from existing capital receipts to fund the remainder of the Council’s contribution towards the £514,000 cost of the preparation and submission of the Listed Building Application, with the remaining cost being provided by CRL.
4) Authorise that the existing Exclusivity Agreement between the Council and CRL be varied to align with the principles set out in the heads of terms contained at appendix 1 of the private element of this report.
5) Delegate authority to the Director of Property Services and Development, following consultation with the Director of Law and Governance, the Director of Finance and Resources and the Cabinet Member for Jobs, Regeneration and Climate Change, to:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Leasehold Disposal of Broadgate HouseRESOLVED that the Cabinet Member for Jobs, Regeneration and Climate Change:- 1. Declares Broadgate House surplus to t...
Exclusion of the Press and PublicRESOLVED that approval be given to exclude the press and public under Section 100(A) 4 of the Local Government Act 19...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.