Gas Contract Renewal

Approved Executive 1 paper

AI summaryCoventry Cabinet approves a gas supply framework worth up to £6.3 million with Total Energies via ESPO, running to 31 March 2031, with early entry to allow flexible wholesale purchasing.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedGas Framework up to £6.3m approved
MoneyUp to £6.3 millionIncludes a 20% buffer above forecast spend
What happens nextContract by 31 January 2026Gas delivery starts 1 April 2027
Who it affectsCouncil, schools, community centres60+ Council and 80+ third party gas supplies

What was decided

Cabinet approved a Gas Framework of up to £6.3 million for gas supply to 31 March 2031, with delegation to the Director of People and Facilities Management to finalise legal terms and to the Head of Energy Services to manage wholesale purchasing. Report P6, P7, P8

The contract will run through the ESPO framework with Total Energies as the supplier, the recommendation rather than standalone procurement or the Strategic Energy Partner route. Report P60, 2.1, 2.2, 2.3

The framework includes flexibility to reduce gas volumes by up to 100% over the term without financial penalty, to allow continued decarbonisation of the Council's estate. Report P49, 1.1, 1.6

Why

The current contract runs to 31 March 2027, and early engagement allows the chosen supplier a longer period to buy gas ahead, smoothing the impact of market volatility. Report P2, P3, P34

Officers judged ESPO to deliver value for money through scale, wholesale market access, a dedicated trading team and good billing accuracy, while continuing with Total Energies avoids the cost of switching around 164 gas meters. Report P47, P60, P61, P83, P84, P85, P86, P87, P88

Although the Council is moving away from gas under its Climate Change Strategy, gas remains unavoidable during the transition, particularly for heating and the crematorium, so a new contract is needed. Report P1, 1.1, 1.6

What happens next

Finalise terms with ESPO and aim to sign the contract by 31 January 2026 so that forward purchasing of wholesale gas can begin. Report 5.1, P66, P34

Service Level Agreements will be put in place with schools and other independent users, who remain the Council's responsibility to the supplier. Report P42, 6.2, P74, P75, P76, P79

Energy budgets will be reviewed annually; if total contract value looks set to exceed £6.3m, further approval will be sought. Report 6.1, P68, P69

The money

  • £6.3million Maximum approved Gas Framework value including 20% buffer Report P6, P33, P34
  • £1,364,860 Forecast total gas spend in 2027-28 Report P33
  • £1,268,989 Forecast total gas spend in 2028-29 Report P33
  • £1,307,059 Forecast total gas spend in 2029-30 Report P33
  • £1,346,271 Forecast total gas spend in 2030-31 Report P33
  • £1,839,102 Forecast Council-only gas cost over the contract term Report P33
  • £3,448,076 Forecast schools and independents gas cost over the contract term Report P33
  • £5,287,178 Forecast total gas spend over the contract term Report P33

Options considered

  • Chosen: Call-off public sector framework via ESPO with Total Energies, the recommended option. Delivers value through scale, wholesale access, dedicated trading expertise and avoids the cost and disruption of switching all gas meters Report 2.1, P47, P60, P61, P83, P84, P85, P86, P87, P88
  • Rejected: Standalone procurement of a gas supplier or broker. Adds significant risk and resourcing, would still rely on pre-defined approval limits and exposes the Council to deemed rate tariffs if offers are suspended Report 2.2, P51, P52, P53
  • Rejected: Bespoke call-off from the Strategic Energy Partner contract with E.ON UK. The SEP gateway process concluded there is no added value to procuring gas via this route Report 2.3, P55

Implications

  • Legal: The Council relies on the General Power of Competence (Localism Act 2011), plus Local Government Act 2003 and Local Authorities (Goods and Services) Act 1970, and the ESPO framework was set up under the Public Contracts Regulations 2015. Report 6.2, P72, P77, P78, P81, P82, P84
  • Equalities: The project has no direct impact on equality duties, though it is expected to support continued service delivery by containing gas costs. Report 7.3, P97
  • Climate: Gas is the Council's third largest source of CO2 emissions, but the contract allows demand to be cut as buildings are decarbonised and the Council judges that cutting gas use is more effective than switching to green gas. Report 1.6, P40, P41, 7.4, P99
  • Risk: Flexible procurement and ESPO's trading team are the main risk controls; the Council is also exposed to roughly 80 third party supplies, mitigated through monitoring and Service Level Agreements. Report 7.2, P42, P93, P94
  • Staffing: Contract will be managed by the Council's Energy Management Services team within People and Facilities Management, with no significant extra resource needed. Report P94, 7.2, P95
  • Other: Missed deadlines carry clear cost risks: not joining by 31 January 2026 reduces forward purchasing, while not having a contract by 31 March 2027 would push users onto deemed rates that could more than double the forecast spend. Report P34, 5.1

Who and where

  • Coventry City Council services using gas for heating, water heating and the cremation process Report 1.1
  • Schools and community organisations that buy gas through the Council's contract, covering more than 80 third party supplies Report P1, P42, 7.5
  • Coventry residents and businesses, through continued progress against the Council's Climate Change Strategy 2024-2030 Report P1, 1.1, 7.1, P91

Timeline

  • 27 November 2025: Contributors began reviewing the draft report Report P104
  • by 31 January 2026: Target date to sign the contract so that forward purchasing of wholesale gas can begin Report 5.1, P66, P34
  • 1 April 2027: Start of the new gas delivery period Report P66
  • 31 March 2031: End of the proposed gas supply contract term Report P6

Plain English for the jargon

  • ESPO: Eastern Shires Purchasing Organisation, a public sector buying body that runs compliant energy frameworks and trades on the wholesale market on behalf of users.
  • Flexible procurement: Buying gas in blocks over time rather than at one fixed price, used to reduce exposure to price spikes.
  • Strategic Energy Partner (SEP): E.ON, appointed by Coventry in 2023 for a 15 year partnership to help decarbonise the city's energy systems.
  • Independent supplies: Third party sites such as schools and community centres whose gas is purchased through the Council's contract.
  • Deemed rates:
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item55

Resolved

RESOLVED that Cabinet: 1) Approves the proposal to enter into a Gas Framework up to £6.3million for the supply of gas up to 31 March 2031. 2) Delegates authority to the Director of People and Facilities Management, following consultation with the Director of Finance and Resources and the Director of Law and Governance, to finalise the legal due diligence and terms and conditions of the Gas Framework and any ... view the full minutes text for item 55.
Word for word from the decision Coventry published for this meeting. Source: edemocracy.coventry.gov.uk

Follow this further

Built from Coventry's papers

What the report saysPro

Report to Cabinet

Executive summary

Coventry’s Climate Change Strategy (2024-2030) sets out the Council’s decarbonisation ambitions, which includes increasing clean energy supply and increasing the energy efficiency of our estate, alongside helping to facilitate partners to do the same. A significant amount of work has gone into decarbonising the Council’s estate over the last decade. Over 40 buildings have been upgraded which includes increasing renewable energy generation through installation of solar pv, decarbonisation of heat through installation of heat pumps and connecting a number of the Council’s buildings to the district heat network, alongside improving insulation, glazing etc. The Council has also appointed E.ON as its Strategic Energy Partner (SEP) over the next 15 years, to help increase the scale and pace of decarbonisation across the city. One of the first activities the SEP completed was production of the Coventry Energy Plan, which looks at how the city could decarbonise energy infrastructure over the next 15 years. This includes moving away from gas and creating more locally produced electricity. At present, we are in a transition phase and the purchase of gas is an unavoidable activity that has in recent years had increasing financial implications for the Council. Since 2021 the annual gas spend for both corporate and independent sites has varied between £1.6m and £3.3m per year due to significant global events that have impacted the gas markets. The corporate contract currently covers over 60 Council gas supplies but also supports more than 80 related 3rd party gas supplies including schools and community centres.

The Council’s current gas contract is not set to expire until 31 March 2027. But by engaging early, the chosen supplier will have a longer period over which to buy gas ahead of the contract start date. This approach is widely used and is known as “flexible procurement”. It involves purchasing blocks of gas over time when the cost is lower which reduces the risk of being subject to shock price increases.

The Council has been using the flexible procurement approach to gas since 2009. This approach has been successful in mitigating the impact on the Council from the unprecedented volatility in the gas market.

This report sets out the Council’s gas requirements as well as the anticipated financial implications on Council budgets. It is important to note that the proposed gas contract allows flexibility to reduce gas demand during the contract period, which is anticipated as energy efficiency improvements are made to more buildings across the city.

Recommendations

Cabinet is recommended to:

1) Approve the proposal to enter into a Gas Framework up to £6.3million for the supply of gas up to 31 March 2031.

2) Delegate authority to the Director of People and Facilities Management, following consultation with the Director of Finance and Resources and the Director of Law and Governance to finalise the legal due diligence and terms and conditions of the Gas Framework and any other legal agreements required to facilitate delivery of the gas supply and its ancillary services.

3) Delegate authority to the Head of Energy Services, following consultation with the Director of People and Facilities Management, to oversee the ongoing management of the wholesale purchasing strategy during the term of the contract.

List of Appendices included:

None

Background papers

None

Other useful documents

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Gas Contract RenewalReport 391 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 25 attended
PA
Councillor Pervez AkhtarDeputy Cabinet Member, in attendance
KC
Councillor Kamran CaanCommittee Member, present
GA
Councillor George Arthur DugginsChair, apologies
AS
Councillor Abdul Salam KhanDeputy Chair, present
JO
Councillor Jim O'BoyleCommittee Member, present
GR
Councillor Gary RidleyNon Voting Opposition Member, in attendance
PS
Councillor Patricia SeamanCommittee Member, present
PH
Councillor Patricia HethertonCommittee Member, present
GL
Councillor Gavin LloydBy Invitation, in attendance
RB
Councillor Richard BrownCommittee Member, present
NA
Councillor Naeem AkhtarCommittee Member, present
RP
Councillor Ram Parkash Lakha OBEBy Invitation, in attendance

All 25 on the meeting page

More from Coventry Cabinet

All decisions
MeetingDecisionOutcome
7 Jul 2026 Revenue and Capital Outturn 2025/26RESOLVED that Council be recommended to approve the contribution to reserves of £3.2m for the purposes described in S... Approved Open
7 Jul 2026 Acceptance of the Music Hub Revenue Grant for the Strategic Area of Coventry, Warwickshire and SolihullRESOLVED that, the Cabinet: 1. Approve acceptance of the revenue grant for the academic year 2026/27 from ACE of £1,7... Approved Open
17 Mar 2026 Private Sector Housing Enforcement Policy 2026-31RESOLVED that the Cabinet recommend that the policy be reviewed by full Council for approval. Approved Open
17 Mar 2026 Coventry: City of Movement Strategy 2026-2031RESOLVED that, the Cabinet: 1. Note and accept the additional recommendation from the Scrutiny Co-ordination Committe... Approved Open