Resolved
RESOLVED That the Audit Results Report for the year ended 31 March 2018 be received and noted.
Audit Committee noted this item on Wednesday 25 July 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED That the Audit Results Report for the year ended 31 March 2018 be received and noted.
Crawley Borough Council Audit results report Year ended 31 March 2018
16 July 2018 Private and Confidential 16 July 2018
Dear Audit Committee Members
We are pleased to attach our audit results report for the forthcoming meeting of the Audit Committee. This report summarises our preliminary audit conclusion in relation to the audit of Crawley Borough Council (the Council) for 2017/18.
We have substantially completed our audit of the Council for the year ended 31 March 2018. Subject to concluding the outstanding matters listed in our report, we confirm that we expect to issue an unqualified audit opinion on the financial statements in the form at Section 4, before the statutory deadline of 31 July 2018. We also have no matters to report on your arrangements to secure economy, efficiency and effectiveness in your use of resources.
This report is intended solely for the use of the Audit Committee, other members of the Council, and senior management. It should not be used for any other purpose or given to any other party without obtaining our written consent.
We would like to thank your staff for their help during the engagement.
We welcome the opportunity to discuss the contents of this report with you at the Audit Committee meeting on 25 July 2018.
Yours faithfully
Paul KIng Associate Partner For and on behalf of Ernst & Young LLP Encl
2 [Option 1]
Contents 01 Executive Summary 02 Understanding Financial 03 Areas of Audit Focus 04 Audit Report 05 Audit Differences 06 Value for Money Statements
07 Other reporting 08 Assessment Control of 09 Data Analytics 10 Independence 11 Appendices issues Environment In April 2015 Public Sector Audit Appointments Ltd (PSAA) issued “Statement of responsibilities of auditors and audited bodies”. It is available from the via the PSAA website (www.PSAA.co.uk). The Statement of responsibilities serves as the formal terms of engagement between appointed auditors and audited bodies. It summarises where the different responsibilities of auditors and audited bodies begin and end, and what is to be expected of the audited body in certain areas. The “Terms of Appointment (updated February 2017)” issued by the PSAA sets out additional requirements that auditors must comply with, over and above those set out in the National Audit Office Code of Audit Practice (the Code) and in legislation, and covers matters of practice and procedure which are of a recurring nature. This report is made solely to the Audit Committee and management of Crawley Borough Council in accordance with the statement of responsibilities. Our work has been undertaken so that we might state to the Audit Committee, and management of Crawley Borough Council those matters we are required to state to them in this report and for no other purpose. To the fullest extent permitted by law we do not accept or assume responsibility to anyone other than the Audit Committee and management of Crawley Borough Council for this report or for the opinions we have formed. It should not be provided to any third-party without our prior written consent.
3 01 Executive Summary
4 Executive Summary Scope update
In our audit planning report tabled at the 6 March 2018 Audit Committee meeting, we provided you with an overview of our audit scope and approach for the audit of the financial statements. We carried out our audit in accordance with this plan.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Audit Results Report for the year ended 31 March 2018Report | 5 MB | DownloadRead as text |
Follow Audit Committee at Crawley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 7 Jul 2026 | Audit Planning Report: Year Ended 31 March 2026RESOLVED That the Audit Planning Report for the year ended 31 March 2026 be noted. | Noted | Open |
| 7 Jul 2026 | Internal Audit Annual Conclusion: 2025/26RESOLVED That the Annual Internal Audit Conclusion for 2025/26 be noted. | Noted | Open |
| 7 Jul 2026 | Update on Counter-FraudRESOLVED That the Update on Counter-Fraud (as amended) be noted. | Noted | Open |
| 7 Jul 2026 | Annual Report of the Audit Committee Chair: 2025/26RESOLVED That the Committee confirm it is assured that the Council's governance arrangements, financial management an... | Decided | Open |
| 7 Jul 2026 | Risk Management UpdateRESOLVED The Committee confirmed its satisfaction with the Council's risk management arrangements. That the following... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.