RESOLVED That the Cabinet approves: a) the funding intentions and associated outcomes for the future programme as outlined in section 5 of report HCS/24 . b) the process for allocating funding as outlined in section 5 of report HCS/24 . c) the process for approving grant allocations and appeals process in 2021/22 and 2022/23 as outlined in section 5 of report HCS/24 . Reasons for the Recommendations The proposed transfer will reduce the budget gap in the General Fund as laid out in the Budget Strategy. The recommendations support the Council to achieve a balanced budget position for 2021/22 onwards whilst retaining sufficient revenue funds to deliver a high quality outcome focused commissioning and small grants programme that can better respond to our community’s needs. They also take into account the needs of the organisations that we currently fund and allow us to support them through a transition period, as appropriate to their individual circumstance.
Word for word from the decision Crawley published for this meeting.Source: democracy.crawley.gov.uk
That the Commission consider the report and decide what comments, if any, it wishes to submit to the Cabinet.
2.2To the Cabinet agree:
1) the funding intentions and associated outcomes for the future programme as outlined in section 5.
2) the process for allocating funding as outlined in section 5.
3) the process for approving grant allocations and appeals process in 2021/22 and 2022/23 as outlined in section 5.
Reasons for the recommendations
3.1The recommendations support the Council to achieve a balanced budget position for 2021/22 onwards whilst retaining sufficient revenue funds to deliver a high quality outcome focused commissioning and small grants programme that can better respond to our community’s needs.
3.2They also take into account the needs of the organisations that we currently fund and allow us to support them through a transition period, as appropriate to their individual circumstance.
Background
4.1The Council currently provides a community grants programme with a comparatively generous annual budget pot of £632,000. The programme funds twenty two Voluntary and Community sector organisations to deliver a broad variety of services, activities and one off events. Grants range from £2,500 to £140,000.
4.2As part of the budget setting process for 2021/22, the Council has stated its intention to reduce the overall community grants pot by £211,000 (one third) and retain a pot totalling £421,000. This contributes to the Council achieving a balanced budget position as part of its Budget Strategy 2021/22 - 2025/26 FIN/508.
4.3It has also been recognised that the Council’s funding of the Voluntary and Community Sector required review. The approach has remained largely unchanged over the past decade or so. With Crawley facing unprecedented economic challenges in the wake of the Covid-19 pandemic, there will be social challenges facing the town that require new approaches and capacity. This will require the Council to develop a much more targeted approach in its funding of the sector to meet existing and emerging need.
4.4The provision of a one-off ‘Lower Tier Services’ government grant allocation within the recent Provisional local government finance settlement as outlined elsewhere on this agenda in the Budget and Council tax report FIN 514 section 5.5.2 has afforded the Council the opportunity to make 2021/22 a transitionary approach in allocating funding for the Voluntary and Community Sector. In doing so the Council aims to move fully to a new commissioning stance from 2022/23.
4.5A transitional year allows the Council to work with all organisations and support them through the change. Different organisations will have differing levels of resilience to change, for instance the organisations funded currently have a combined unrestricted reserves pot of around £3.8 million, albeit the provision made within each organisation varies greatly. This approach also allows the Council to fulfil any contractual obligations, specifically to provide an allocation of £140,000 to Citizens Advice in 2021/22.
4.6The process of engagement with all funded groups has begun. Officers have met with every funded organisation to facilitate a high level conversation around potential changes to the community grants programme and the impact of various funding reduction scenarios.
5. Proposals
It is proposed that the Council apply the following principles to achieve a successful transition from the current programme model and funding to the new arrangement;
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Financial Outturn 2025-2026 (Quarter 4)RESOLVED That the Cabinet: a) notes the outturn for the financial year 2025/26 as summarised in report FIN/745 . b) a...
Treasury Management Outturn 2025 – 2026RESOLVED That the Cabinet: a) notes the Treasury Management Outturn 2025/2026 report FIN/746 . b) approves the actual...
2026-2027 Budget Monitoring - Quarter 1RESOLVED That the Cabinet notes the projected outturn for the financial year 2026/27 as summarised in report FIN/747 ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.