Resolved
RESOLVED That the Commission noted the report and requested that the views expressed during the debate, were fed back to the Cabinet through the Commission’s Comment sheet.
Overview and Scrutiny Commission noted this item on Monday 4 July 2022. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED That the Commission noted the report and requested that the views expressed during the debate, were fed back to the Cabinet through the Commission’s Comment sheet.
2.1To the Overview and Scrutiny Commission:
That the Commission consider the report and decide what comments, if any, it wishes to submit to the Cabinet.
2.2To the Cabinet:
The Cabinet is recommended to:
a) Note the outturn for the financial year 2021/22 as summarised in this report.
b) Note that this has been an exceptional year where it has been very difficult to do accurate financial projections.
c) Add £97,000 to the capital programme, funded from Government Grant for Changing Places Toilets as outlined in section 9.10 of this report.
The Cabinet is recommended to ask Full Council to:
d) Agree to the transfers of reserves as outlined in section 10 of this report.
3.1To report to Members on the projected outturn for the year compared to the approved budget. 4. Background
4.1As part of the Budget Strategy, the Council has in place robust budget monitoring systems to ensure that unapproved overspends are avoided. The Council also manages and analyses underspending to identify potential savings that could help meet current and future years’ priorities.
4.2Budget monitoring is undertaken on a monthly basis with budget holders. There are quarterly budget monitoring reports to Cabinet with the Corporate Management Team receiving monthly update reports on key areas and any other areas of concern. The Overview and Scrutiny Commission also have the opportunity to scrutinise expenditure. The financial year 2021/2022 was exceptionally difficult to project accurately due to the impact of the pandemic on the Council’s finances together with Government support.
4.3This report outlines the projected outturn for 2021/2022 as at the end of March 2022.
4.4As discussed in the budget report and Budget Strategy, due to the pandemic it is very difficult to accurately forecast the Council’s financial position for the year.
5. Budget Monitoring Variations
5.1General Fund The table below summarises the projected variances in the relevant Portfolio at Quarter 4. This shows an underspend of £656,000 against the original budget.
[F indicates that the variation is favourable, U that it is unfavourable]
Actual Variance Variance at projected at Quarter 4 Quarter 3 £’000 £'000
Cabinet 267 U 337 Public Protection & Community Engagement (85) F (71) Environmental Services & Sustainability 21 U 305 Housing 162 U 161 Wellbeing 795 U 1,225 Planning & Economic Development 38 U (47) Resources (84) F (2)
Sub Total 1,114 U 1,908
Investment Interest (512) F (622) Approved Coronavirus Budgets (941) F (1,113) Sales, Fees and Charges Grant Q1 (316) F (316) New Homes Bonus (1) F 0
Net Variance (656) (143) Further details of these projected variances are provided in Appendix 1(i & ii) attached to this report.
Significant Quarter 4 variances over £50,000
5.1.1 Cabinet
There are no significant variations to report this quarter.
5.1.2 Public Protection & Community Engagement
There are no significant variations to report this quarter.
5.1.3 Environmental Services & Sustainability Services
Upgraded security due to recent capital works has reduced the level of vandalism occurring within Crawley Borough Council car parks, combined with lower maintenance costs and an uptake in pay and display usage during quarter four, the actual overspend has been reduced to £62,000 from £146,000 reported at quarter 3.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Financial Outturn 2021-2022 (Quarter 4)Report | 1.6 MB | DownloadRead as text |
Follow Overview and Scrutiny Commission at Crawley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 7 Sep 2026 | Financial Outturn 2025-2026 (Quarter 4)RESOLVED That the Commission noted the report and requested that the views expressed during the debate, were fed back... | Noted | Open |
| 7 Sep 2026 | Treasury Management Outturn 2025 – 2026RESOLVED That the Commission noted the report and requested that the views expressed during the debate were fed back ... | Noted | Open |
| 7 Sep 2026 | 2026-2027 Budget Monitoring - Quarter 1RESOLVED That the Commission noted the report and requested that the views expressed during the debate, were fed back... | Noted | Open |
| 7 Sep 2026 | Crawley Homes Complaints Performance and Service Improvement Plan 2026RESOLVED That the Commission noted the report and requested that the views expressed during the debate, were fed back... | Noted | Open |
| 7 Sep 2026 | Crawley Homes Asset StrategyRESOLVED That the Commission noted the report and requested that the views expressed during the debate, were fed back... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.