Crawley Borough Council
Cabinet, Wednesday 29 November 2023 at 7.00pm

Crawley Station Gateway - Phase 1

Approved Executive 3 papers

Cabinet approved this item on Wednesday 29 November 2023. Below is the council's own wording, with the papers it was decided on.

Item9

Resolved

RESOLVED That the Cabinet: a) approves the refreshed concept design for the Station Gateway Phase 1 project found at Appendix A of report PES/443 ; comprising a public realm and bus station improvement scheme focusing on Friary Way, Haslett Avenue West and The Martlets. b) approves the refreshed concept design to go out to public and stakeholder consultation, prior to the submission of a planning application and procurement of a construction contractor. c) delegates authority to approve the final designs for Station Gateway Phase 1 to the Head of Major Projects and Commercial Services, in consultation with the Head of Economy & Planning and Cabinet Member for Planning and Economic Development, following the period of stakeholder consultation and undertaking minor modifications as required. d) delegates to the Head of Major Projects and Commercial Services the submission of a planning application to the Local Planning Authority on behalf of Crawley Borough Council e) delegates authority to the Head of Major Projects and Commercial Services to undertake a procurement tendering exercise to appoint a construction contractor in accordance with the Council’s Procurement Code. f) delegates authority to the Leader of the Council, in consultation with the relevant Cabinet Member and Head of Major Projects and Commercial Services, to approve the award of the construction contact following an appropriate procurement process. g) delegates the negotiation, approval and completion of all relevant documentation, including legal paperwork, to the Head of Economy and Planning, Head of Governance, People and Performance and the Head of Corporate Finance (Generic Delegations 2 & 3 will be used to enact this recommendation). h) that the Full Council be asked to approve the amalgamation of the two funding streams (£5.4m from the Crawley Growth programme and £2m from the Towns Fund) already allocated within the Council’s capital programme to enable delivery of the project as set out in section 7.2 of report PES/443 . Reasons for the Recommendations To enable the successful delivery of the Station Gateway Phase 1 scheme which will deliver significant public realm and bus station improvements whilst future-proofing future town centre regeneration schemes.
Word for word from the decision Crawley published for this meeting. Source: democracy.crawley.gov.uk

Follow this further

Built from Crawley's papers

What the report saysPro

Report to Cabinet

Recommendations

2.1To the Overview & Scrutiny Commission:

That the Overview & Scrutiny Commission consider the report and decide what comments, if any, it wishes to submit to Cabinet.

2.2To the Cabinet:

The Cabinet is recommended to:

a) Approve the refreshed concept design for the Station Gateway Phase 1 project found at Appendix A; comprising a public realm and bus station improvement scheme focusing on Friary Way, Haslett Avenue West and The Martlets.

b) Approve the refreshed concept design to go out to public and stakeholder consultation, prior to the submission of a planning application and procurement of a construction contractor.

c) Delegate authority to approve the final designs for Station Gateway Phase 1 to the Head of Major Projects and Commercial Services, in consultation with the Head of Economy & Planning and Cabinet Member for Planning and Economic Development, following the period of stakeholder consultation and undertaking minor modifications as required.

d) Delegate to the Head of Major Projects and Commercial Services the submission of a planning application to the Local Planning Authority on behalf of Crawley Borough Council

e) Delegate authority to the Head of Major Projects and Commercial Services to undertake a procurement tendering exercise to appoint a construction contractor in accordance with the Council’s Procurement Code.

f) Delegate authority to the Leader of the Council, in consultation with the relevant Cabinet Member and Head of Major Projects and Commercial Services, to approve the award of the construction contact following an appropriate procurement process.

g) Delegate the negotiation, approval and completion of all relevant documentation, including legal paperwork, to the Head of Economy and Planning, Head of Governance, People and Performance and the Head of Corporate Finance (Generic Delegations 2 & 3 will be used to enact this recommendation).

h) Request Full Council to approve the amalgamation of the two funding streams (£5.4m from the Crawley Growth programme and £2m from the Towns Fund) already allocated within the Council’s capital programme to enable delivery of the project as set out in section 7.2 of report PES/443.

Reasons for the recommendations

3.1To enable the successful delivery of the Station Gateway Phase 1 scheme which will deliver significant public realm and bus station improvements whilst future-proofing future town centre regeneration schemes.

Background

4.1The Crawley Growth Programme is a major regeneration programme of infrastructure improvements and physical regeneration designed to support significant increases in new homes, business investment and employment growth. The Programme is being delivered by Crawley Borough Council in partnership with West Sussex County Council (WSCC), underpinned by £49.093m of public funding and supported by a range of public and private sector organisations including Metrobus, Manor Royal Business Improvement District, the Arora Group, Network Rail and Govia Thameslink Railway (GTR).

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Terms of ReferenceAppendix A 242 KB Download
PDF
Concept DesignAppendix B 1.4 MB Download
PDF
Crawley Station Gateway: Phase 1Report 77 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 18 attended
MJ
Councillor Michael JonesChair, present
II
Councillor Ian IrvineCommittee Member, present
YK
Councillor Yasmin KhanCommittee Member, present
CM
Councillor Chris MullinsCommittee Member, present
SM
Councillor Sue MullinsCommittee Member, present
AN
Councillor Atif NawazCommittee Member, present
BN
Councillor Bob NoyceCommittee Member, apologies
TR
Councillor Tahira RanaCommittee Member, present
CM
Carolin MartlewOfficer, in attendance
SC
Siraj ChoudhuryOfficer, in attendance
ID
Ian DukeOfficer, in attendance
CP
Chris PedlowOfficer, in attendance

All 18 on the meeting page

On this subject at Crawley

Search all
  1. Crawley Station Gateway - Phase 1This decision
  2. Planning Application CR/2020/0274/FUL - Ambulance Station, Ifield Avenue, West Green, CrawleyAgreed
  3. Recommendation 5 – Crawley Station Gateway - Phase 1Approved
  4. Crawley Station Gateway - Phase 1Noted
  5. Planning Application CR/2021/0621/OUT - Car Park, Station Way, Northgate, CrawleyRefused
  6. Planning Application CR/2019/0660/FUL - Overline House, Station Way, Northgate, CrawleyAgreed

More from Crawley Cabinet

All decisions
MeetingDecisionOutcome
9 Sep 2026 Financial Outturn 2025-2026 (Quarter 4)RESOLVED That the Cabinet: a) notes the outturn for the financial year 2025/26 as summarised in report FIN/745 . b) a... Approved Open
9 Sep 2026 Treasury Management Outturn 2025 – 2026RESOLVED That the Cabinet: a) notes the Treasury Management Outturn 2025/2026 report FIN/746 . b) approves the actual... Approved Open
9 Sep 2026 2026-2027 Budget Monitoring - Quarter 1RESOLVED That the Cabinet notes the projected outturn for the financial year 2026/27 as summarised in report FIN/747 ... Approved Open
9 Sep 2026 Crawley Homes Complaints Performance and Service Improvement Plan 2026RESOLVED That the Cabinet: a) approves the Crawley Homes Annual Complaints Performance and Service Improvement Plan R... Approved Open
9 Sep 2026 Crawley Homes Asset StrategyRESOLVED That the Cabinet: a) approves the Crawley Homes Asset Management Strategy ( appendix A of report CH/222 ) fo... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies