RESOLVED That the Cabinet: a) notes the outturn for the financial year 2023/2024 as summarised in this report FIN/658 b) approves the addition of a Senior Project Manager within the Built Environment Team to be funded from existing and future capital projects. (para 9.9 of report FIN/658 ) c) approves the virement in the Capital Programme of £67k from Allotments to Goffs Park (para 9.8 of report FIN/658 ) d) notes the carry forward requests detailed in Section 6 of report FIN/658 The Full Council be recommended to: a) agree to the transfers of reserves and level of balances as outlined in Section 10 of report FIN/658 . b) approve the addition to the Capital Programme of £1.1m funded from the Better Care Fund. (para 9.3 of report FIN/658 ). c) approve the addition to the Capital Programme of £60k for Three Bridges Station funded from S106 monies received. (para 9.6 of report FIN/658 ). Reasons for the Recommendations To report to Councillors on the outturn, subject to audit, for the year compared to the approved budget.
Word for word from the decision Crawley published for this meeting.Source: democracy.crawley.gov.uk
That the Commission consider the report and decide what comments, if any, it wishes to submit to the Cabinet.
2.2To the Cabinet:
The Cabinet is recommended to:
a) Note the outturn for the financial year 2023/2024 as summarised in this report.
b) Approve the addition of a Senior Project Manager within the Built Environment Team to be funded from existing and future capital projects. (para 9.9)
c) Approve the virement in the Capital Programme of £67k from Allotments to Goffs Park (para 9.8)
d) Note the carry forward requests detailed in section 6.
The Cabinet is recommended to request Full Council to:
e) Agree to the transfers of reserves and level of balances as outlined in section 10 of this report.
f) Approve the addition to the Capital Programme of £1.1m funded from the Better Care Fund. (para 9.3) g) Approve the addition to the Capital Programme of £60k for Three Bridges Station funded from S106 monies received. (para 9.6)
Reasons for the recommendations
3.1To report to Members on the outturn, subject to audit, for the year compared to the approved budget.
Background
4.1As part of the Budget Strategy, the Council has in place robust budget monitoring systems to ensure that unapproved overspends are avoided. The Council also manages and analyses underspending to identify potential savings that could help meet current and future years’ priorities.
4.2Since the budget was set in February 2023 the Council’s financial situation has deteriorated significantly as reported in the 2023/24 Budget Monitoring Report – Quarter 1 (FIN/633), 2023/24 Budget Monitoring Report – Quarter 2 (FIN/635) 2023/24 Budget Monitoring Report – Quarter 3 (FIN/643). The reasons for the projected overspend were fully explained in the reports and include pay inflation and other service cost pressures, which were largely offset by the increased return on investments. However, the biggest cost pressure is the increase in the cost of homelessness. Further information with regard to Homelessness (temporary accommodation) is contained in paragraphs 5.3 and 5.4. During the year the Council identified significant reductions in net expenditure in order to mitigate the effect of this increase but the scale and speed of the increase in net expenditure has meant a significant draw down from the Council’s General Fund Reserve for 2023/24 which is not sustainable in the medium term (para 10.1).
4.3Budget monitoring is undertaken with budget holders. There are quarterly budget monitoring reports to Cabinet with the Corporate Management Team receiving monthly update reports on key areas and any other areas of concern. The Overview and Scrutiny Commission has the opportunity to scrutinise expenditure.
4.4The purpose of this report is to allow Members to review the revenue and capital outturn figures for 2023/24 for the Council, subject to external audit.
5. Budget Monitoring Variations
5.1General Fund The table below summarises the variance for the financial year ending 31 March 2024 compared to the projection from the previous quarter: Q3 Q4 Projection Outturn Change £'000 £'000 £'000
Financial Outturn 2025-2026 (Quarter 4)RESOLVED That the Cabinet: a) notes the outturn for the financial year 2025/26 as summarised in report FIN/745 . b) a...
Treasury Management Outturn 2025 – 2026RESOLVED That the Cabinet: a) notes the Treasury Management Outturn 2025/2026 report FIN/746 . b) approves the actual...
2026-2027 Budget Monitoring - Quarter 1RESOLVED That the Cabinet notes the projected outturn for the financial year 2026/27 as summarised in report FIN/747 ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.