The Leader of the Council delegated to the Cabinet the power to make the decisions set out below. RESOLVED to approve: The procurement strategy which will result in contract awards for the provision of services in respect of Passenger Transport for a maximum term of eight years as set out at agenda item 12a; RESOLVED to note: The list of delegated award decisions made by the Director of Commissioning and Procurement, between 09/08/2018 – 13/09/2018. RESOLVED to recommend: 1. To the Leader of the Council that the Cabinet Member for Finance and Resources in consultation with the Leader, continues to be authorised to agree the award of contracts related to the Good to Great ICT transformation programme for reasons set out in paragraph 4.3 and 4.4 of the report. These awards will be in line with the strategy approved by Cabinet on 20th November 2017 (reference: 91/17 . ICT sourcing strategy) and any awards made under this delegation will be notified in the standard contracts report at future Cabinet meeting 2. To the Leader of the Council, the Cabinet Member for Environment, Transport & Regeneration in consultation with Cabinet Member for Finance and Resources and Cabinet Member for Children, Young People & Learning be authorised to agree the awards of contracts related to the Addington Valley SEN School for the purposes set out in the Education Estates Strategy approved by Cabinet on 22nd January 2018 (decision reference A6/18) and in line with the Addington Valley SEN Free School Procurement Strategy (CCB reference CCB1400/18-19) for reasons set out in paragraph 4.5 of the report and any awards made under this delegation will be notified in the standard contracts report at future Cabinet meetings
Word for word from the decision Croydon published for this meeting.Source: democracy.croydon.gov.uk
Review Point 2 (RP2) - How we Buy Category Managers will be required to complete the How We Buy Report in consultation with the Service area & all key stakeholders, both internal & external. It should be supported by RP1 – Make or Buy report.
RP2 Reports with a value up to £5million approved via CCB, values above £5million requires Cabinet approval (Please check with the relevant C&P HoS if this is required)
Section 1
1. Project Details Project Title: Addington Valley SEN Free School
Name, role and contact of report author: Natalie Thomas (Project Manager) Directorate: District centres and regeneration Service Area: Homes and schools improvement Project Sponsor (Director or above) Hazel Simmonds (Director of District centres and regeneration) Date RP1 – Make or Buy report approved: N/A Date of Commissioning and Contracts Board: 9th August 2018
1.2What are the outcomes we are seeking to achieve?
This is in line with the ambitions for the Timebridge Community Centre Site as set out in the Council’s Croydon Local Plan 2018. The Local Plan 2018 was agreed for submission to the Secretary of State by Full Council in December 2016 (Resolution A82/16), recommended for adoption by the Cabinet Member for Homes and Regeneration, exercising delegated authority, on 8 February 2018 (decision reference 0418HRP) and formally adopted by the Council on 27 February 2018. Furthermore, the use of the site for educational purposes was set out in the Education Estates Strategy approved by Cabinet on 22 January 2018 (decision reference A6/18). On 26 February 2018, the Cabinet endorsed and recommended to Full Council the Capital Programme 2018-21 as part of the Council’s budget setting process (decision reference A14/18a). An additional report relating to Timebridge Community centre has been approved by CCB (Ref: CCB1370/18-19 dated 28th June 2018).
The Council has been awarded £80k by the Education and Skills Funding Agency (ESFA) to complete the feasibility stage of the project. There is a requirement for the Council to submit the final feasibility report to ESFA by end of September 2018, seeking funding application to support the delivery of Addington Valley new Free SEN school which is circa. £15m. The award of contract will not proceed until confirmation has been received from ESFA with regards to the approved funding allocation.
In accordance with Regulation 17 of the Council’s Tenders and Contract Regulations, the service strategy to which this report relates has already been reported and agreed by Cabinet, and it has been determined that authority to agree this procurement strategy has been delegated to the relevant Cabinet Members.
The outcome of this project will be delivery of the new Addington Valley Free SEN school for approximately 150 children from the age of 2-19 years of age.
As soon as ESFA’s agreed funding has been confirmed, this will enable the design and build of the new SEN development which will be located at the Timebridge site. The project supports a number of key outcomes for the borough:
- Ensuring provision of sufficient school places for Croydon’s children and young people - Increasing provision of in-borough special educational needs school places - Supporting the borough’s vibrant voluntary and community sector
The key deliverables for the overall project are:
- Delivery of a new SEN school - Delivery of shared community spaces -
1.3Croydon Policies and Corporate Priorities
What are the relevant Croydon policies and priorities that apply to this Project? Details of the Councils Priority Projects, Service Plans and Strategies can be found here This project supports delivery of the following key themes of the proposed corporate plan 2018-22:
- Education and Learning We want to work towards a borough that can provide every young person the best possible start and recognises the different needs and challenges that they all face.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Croydon Youth Justice Plan 2026/27For the reasons set out in the report and its appendix the Executive Mayor and Cabinet AGREED : The plan (Appendix A)...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.