CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
London Borough of Croydon
Public Transport Liaison Panel, Wednesday 27 February 2019 at 9.30am

Buses

Agreed Committee 1 paper

Public Transport Liaison Panel agreed this item on Wednesday 27 February 2019. Below is the council's own wording, with the papers it was decided on.

Item6/19

Resolved

It was agreed that the Access Officer, the Mobility Forum representative and the TfL representative would discuss possible solutions after the meeting. 468 bus – Report back the length that the route would be monitored. The TfL informed that Panel that more data was needed before a decision could be made and that the Panel would be informed of the outcome at the June 2019 meeting. The East Surrey Transport Committee informed the Panel that the route had a frequency increase in 2017, and then a reduction soon after. There were some parts of the route with no alternative and this had affected the residents greatly. The TfL representative responded that frequency needed to match demand, and this did cause some fluctuations in the service. It was suggested that surveys would be done in areas where there was known overcrowding. Action Point: For TfL to report back the outcome ... view the full minutes text for item 6/19
Word for word from the decision Croydon published for this meeting. Source: democracy.croydon.gov.uk

Follow this further

Built from Croydon's papers

What the report saysPro

Report to Public Transport Liaison Panel

Draft 1: Reduction of buses in Wellesley Road during Construction of New Westfield Shopping Centre in the Whitgift Centre

Today there are some 23 Bus routes that transverse Wellesley road, either from Central Croydon or from East Croydon.

The following buses from Central Croydon terminate at West Croydon: 154, 166, 194, 403, 405 & 412.

The following buses terminate at West Croydon from East Croydon: X26, 194, 367, 433 & 689

The following buses pass through West Croydon from Central Croydon: 50, 60, 75, 109, 250, 264, 407, 455 &.468

The following buses pass through West Croydon from East Croydon Station: 64, 194 & 410.

One can understand the desire to reduce services during construction work. However, any reduction in or alteration to routes needs to take into consideration the needs of passengers, especially those with reduced mobility that need to cross Croydon by having to change buses once, or even twice. The also needs to be consideration the destinations that passengers from different parts of the borough need to get to that require crossing the centre of Croydon, which include: Croydon University Hospital, Fairfield Halls, Bernard Weatherill House, Surrey Street Market and West Croydon Station. It must also maintain connectivity so that passengers can easily change buses at the same locations and any change does not require changing twice when the journey can be made by one change currently.

Therefore changes should provide passengers with new and increased journey opportunities. I would suggest that by looking at the central Croydon bus network, a number of changes could be made to routes that would result in both the least disruption and offer new and improved journey opportunities.

1 I would suggest, of the routes that cross West Croydon that the following routes remain as now in Wellesley Road:

Bus Route 60 Old Coulsdon to Streatham 64 New Addington to Thornton Heath 198 Shrublands to Thornton Heath 109 Central Croydon to Brixton via London Road 250 Central Croydon to Brixton via Green Lane 264 Central Croydon to Tooting via Mitcham 75 Croydon Fairfield Halls to Lewisham to 410 Crystal Palace to Wallington 468 South Croydon to Elephant and Castle via Upper Norwood

The following three routes could be considered for changes, dependent of the carry over across Croydon:

Bus Route Suggestion Alternative 50 Central Croydon to Brixton via London This could be diverted at West Route 468 would continue to provide a cross Road Croydon, and travel via Tamworth Croydon route to Whitehorse Road and Road and Old Town, continuing to Thornton Heath. Nottingham Road via Bramley hill. This would provide a new link to large areas of Croydon that do not have access to a bus. 407 Caterham to Sutton via Central Croydon This route is clearly in tow sections, Route 410 continues to provide a cross and could be split to run from Sutton Croydon route and the 154 provides and Caterham to East Croydon*. alternative to Central Croydon 455 Wallington to Old Lodge Lane via This route could run in two sections: Route 410 continues to provide a cross Wandle Valley Wallington to West Croydon and Old Croydon link for some of route 455. In the Lodge Lane to East Croydon* south, route 404 would continue to provide a route to West Croydon from Purley and Pampisford Road.

2 The following two routes should continue to West Croydon for the South:

Bus Route 403 Warlingham to West Croydon 405 Redhill to West Croydon

If we look at where the remaining buses that terminate at West Croydon, these could be diverted to provide new links to journey opportunities. They could be diverted to East Croydon station, but fortunately the capacity and bus station is laid out in a way that is conducive to buses laying over. However, there are a couple of alternative possibilities.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
BusesReport 86 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

3 of 27 attended
MA
Councillor Muhammad AliChair, present
ND
Councillor Nina DegradsVice-Chair, present
IP
Councillor Ian ParkerCommittee Member, present
TD
Thomas DownsClerk, expected
IP
Ian PlowrightOfficer, expected
BK
Ben KennedyOfficer, expected
SA
Stephen AselfordPublic, expected
CK
Charles KingPublic, expected
DS
Danny StephenPublic, expected
MM
Muhammed MashudPublic, expected
PH
Philip HewittPublic, expected
AH
Ayse HodgkinsonPublic, expected

All 27 on the meeting page

More from Croydon Public Transport Liaison Panel

All decisions
MeetingDecisionOutcome
20 Jun 2018 Growth Zone UpdateRESOLVED that this item be presented at the next PTLP meeting (Tuesday 16 October 2018). Decided Open
27 Feb 2018 Presentation on train Station SkippingIt was agreed that Yvonne would be briefed on these minutes and her written presentation would be circulated to panel... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies