Resolved
RESOLVED : The Committee AGREED to note the report for Internal Audit for April to August 2019.
General Purposes & Audit Committee agreed this item on Wednesday 9 October 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED : The Committee AGREED to note the report for Internal Audit for April to August 2019.
1.1The Committee is asked to note the Internal Audit Report for April to August 2019 (Appendix 1). 2. EXECUTIVE SUMMARY 2.1 This report details the work completed by Internal Audit so far during 2019/20 and the progress made in implementing recommendations from audits completed in previous years.
3. DETAIL 3.1 The Internal Audit report (Appendix 1) includes the following: a list of all audits completed so far in 2019/20, a list of audits relating to 2018/19, but finalised after the annual report, and lists of follow up audits completed and the percentage of priority one, and other audit recommendations implemented.
3.2Internal Audit is responsible for conducting an independent appraisal of all the Council's activities, financial and otherwise. It provides a service to the whole Council, including Members and all levels of management. It is not an extension of, nor a substitute for, good management. The Internal Audit Service is responsible for giving assurance on all control arrangements to the Full Council through the General Purposes & Audit Committee and the Chief Financial Officer (also known as the Section 151 Officer), who is currently the Director of Finance, Investment & Risk. It also assists management by evaluating and reporting to them the effectiveness of the controls for which they are responsible.
3.3At this stage in the year there is insufficient evidence (3 final reports) on which to give an overall assurance level for the Council.
4. FOLLOW-UP REVIEWS 4.1 When Internal Audit identifies risks, recommendations are made and agreed with service managers to mitigate these. The Council then needs to ensure that action is taken to implement audit recommendations. The Council’s targets for audit recommendations implemented are 80% for all priority 2 and 3 recommendations and 90% for priority 1 recommendations. The performance in relation to the targets set for 2014/18 audits are shown Table 1.
Table 1: Implementation of Audit Recommendations Target 2014/15 2015/16 2016/17 2017/18 2018/19 Implementation of priority one 90% 100% 91% 100% 93% 69% recommendations at follow-up Implementation of all 80% 94% 89% 87% 87% 69% recommendations at follow-up
5. PROGRESS AGAINST THE AUDIT PLAN 5.1 By 31 August 29% (35% last year) of the 2019/20 planned audit days had been delivered and 7% (18% last year) of the draft audit reports due for the year had been issued. The contractor has given assurances that the necessary resources are available to deliver the internal audit plan in-year as usual. 6. PUBLICATION OF INTERNAL AUDIT REPORTS
6.1Following a decision at the June 2015 meeting of this committee, all finalised internal audit reports are published on the Council’s public internet site.
7.1The outcome of all audit work is discussed and agreed with the lead service managers. The final reports and audit recommendations are sent for consideration by Departmental Leadership Teams (DLT). Details are circulated and discussed with Directors on a regular basis.
8. FINANCIAL AND RISK ASSESSMENT CONSIDERATIONS
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Internal Audit Update ReportReport | 89 KB | DownloadRead as text |
PDF |
Internal Audit Update report: Appendix 1 /19Appendix | 211 KB | Download |
Follow General Purposes & Audit Committee at Croydon and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 21 Apr 2022 | Minutes of the Previous MeetingRESOLVED that the minutes of the previous meeting, held on Thursday 3 March 2022, be approved as an accurate record. | Approved | Open |
| 21 Apr 2022 | Minutes Action TrackerRESOLVED that the contents of the Action Tracker, be noted. | Noted | Open |
| 21 Apr 2022 | Assurance Mapping - Next StepsRESOLVED that the report be noted. | Noted | Open |
| 21 Apr 2022 | Anti-Fraud Update Report - 1 April 2021 to 31 March 2022RESOLVED that the report be noted. | Noted | Open |
| 21 Apr 2022 | General Purposes and Audit Committee - Annual Report 2021-2022RESOLVED that the report be noted/referred to Council Chair’s Closing Remarks In marking the final meeting of the cur... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.