Resolved
The Leader of the Council delegated authority to the Cabinet to make the following decisions:
Cabinet decided this item on Monday 20 January 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
The Leader of the Council delegated authority to the Cabinet to make the following decisions:
The Cabinet is recommended by the Contracts and Commissioning Board to approve the following contract variations to The McAvoy Group Ltd, in accordance with Regulation 30 of the Council’s Tenders and Contracts Regulations and for the reasons detailed within this report:
1.1The Timebridge and Community Centre Design and Construction contract variation for a new maximum contract value of £5,297,860. This new contract value includes a 5% contingency value of £302,896 and the new contract period of 18 months including 12 months defects liability period.
1.2The design and contract of the permanent modular building contract variation for a new maximum contract value of £509,387 for the Fieldway Family Centre.
2.1On 26th February 2018, the Cabinet endorsed the recommended Education Estate Capital Programme 2018-21 (ref: A14/18a), as part of the Council’s budget setting process. This includes the delivery of a new community centre to replace the existing Timebridge Community Centre at an agreed budget of £4m, to allow for the development of the new SEN school (Addington Valley SEN Free School) to be completed by September 2020.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Timebridge Community Centre and Fieldway Family Centre Contract VariationReport | 478 KB | DownloadRead as text |
Follow Cabinet at Croydon and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Sep 2026 | Croydon Youth Justice Plan 2026/27For the reasons set out in the report and its appendix the Executive Mayor and Cabinet AGREED : The plan (Appendix A)... | Agreed | Open |
| 23 Sep 2026 | Temporary Accommodation Strategy and Action PlanFor the reasons set out in the report, the Executive Mayor and Cabinet AGREED : 3.1 Approve the Temporary Accommodati... | Agreed | Open |
| 23 Sep 2026 | Crisis Resilience FundFor the reasons set out in this report and its appendices the Executive Mayor and Cabinet AGREED to: 3.1 Accept the a... | Agreed | Open |
| 23 Sep 2026 | Review of Council Tax Support Scheme 2027-28For the reasons set out in the report and its appendices the Executive Mayor and Cabinet RESOLVED : 2.1 to agree to a... | Agreed | Open |
| 23 Sep 2026 | 2026-27 Period 3 Financial Performance ReportFor the reasons set out in the report, the Executive Mayor and Cabinet AGREED to: 2.1 Note the General Fund revenue b... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.