To 1. Review the corporate FPR report (appendix A) as at 31 August 2021 with regard to overall performance against the Croydon Renewal Plan. Noting areas of good performance and those of concern. 2. Note the progress made, and areas of concern, against programmes and projects in relation to milestones, deliverables and issues. 3. Note the progress made against savings and growth targets as identified in the Croydon Renewal Plan. More detail on this area can be found in Table 2a of the Financial Monitoring Report also being presented at this Cabinet meeting. 4. That Cabinet identify areas of performance within the FPR report (appendix A of the report) where they require deeper analysis and benchmarking (where applicable) to be presented in the next FPR report at the 15 November Cabinet for discussion and action.
Word for word from the decision Croydon published for this meeting.Source: democracy.croydon.gov.uk
1.1Review the corporate FPR report (appendix A) as at 31 August 2021 with regard to overall performance against the Croydon Renewal Plan. Noting areas of good performance and those of concern.
1.2Note the progress made, and areas of concern, against programmes and projects in relation to milestones, deliverables and issues. 1.3 Note the progress made against savings and growth targets as identified in the Croydon Renewal Plan. More detail on this area can be found in Table 2a of the Financial Monitoring Report also being presented at this Cabinet meeting.
1.4That Cabinet identify areas of performance within the FPR report (appendix A) where they require deeper analysis and benchmarking (where applicable) to be presented in the next FPR report at the 15 November Cabinet for discussion and action.
Executive summary
2.1The Croydon Renewal Plan, sets out how the Council will respond to the various reviews and recommendations that have highlighted substantial need for improvements. The Improvement Plan has also identified key areas of focus which are essential to changing the overall culture of the Council to one that is evidence led, manages resources well, and is open and transparent with stakeholders.
2.2The corporate FPR report detailed in appendix A of this report, reviews the areas of project and programme delivery, and the measures used to monitor delivery of the actions detailed within the CRP plan, as well as monitoring the performance of the organisation as a whole. The report reviews the period up to and including 31 August 2021. It should be noted that where measures are subject to a reporting time lag the latest available data has been included; this may not correspond with the reported time period.
Background
3.1Cabinet and Council agreed in September 2020 to the development of the Croydon Renewal and Improvement Plan (CRP) which incorporates a financial recovery plan, the submission to MHCLG to secure the necessary capitalisation direction as part of that financial recovery, a corporate Improvement Plan to deliver the required changes to ensure the financial investment and rebalancing of the budget is sustainable.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Croydon Youth Justice Plan 2026/27For the reasons set out in the report and its appendix the Executive Mayor and Cabinet AGREED : The plan (Appendix A)...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.