Resolved
The Leader of the Council delegated authority to the Cabinet to make the following decisions:
Cabinet decided this item on Monday 21 February 2022. Below is the council's own wording, with the papers it was decided on.
Resolved
The Leader of the Council delegated authority to the Cabinet to make the following decisions:
CONTRACTS & COMMISSIONING BOARD REVIEW POINT 3 (RP3) - CONTRACT AWARD REPORT Director of C&P via CCB £100k to £500k Nominated Cabinet Member via CCB >£500k to £5m Cabinet via CCB >£5m CCB AGENDA ITEM: 27.01.2022 Project name: Corporate Cleaning and Security Services Contract Dept. report author: Dean Myles (Principal Facilities Manager, Commercial Investment and Capital) Project Sponsor (Director or above): Peter Mitchell (Interim Director of Commercial Investment and Capital) Executive Director: Richard Ennis (Interim Corporate Director of Resources) David Padfield (Interim Corporate Director of Housing) Contract Manager: Dean Myles (Principal Facilities Manager, Commercial Investment and Capital) Report Version: V5 Date report to go to CCB: 27th January 2022 Next Review Date (RP4) N/A AWARD REPORT – CHECKLIST: Estimated Contract start date: 01/04/22
Estimated Contract end date - excluding any extension periods (for construction and works contracts, officers need to include the time period for the defects 31/03/26 liability period): Is there provision to extend or vary this contract within the terms and conditions? Yes
Planned extension type (e.g., 2 x 1 yr, 3 years, etc): 1+1
What is the maximum end date including all extensions? 31/03/28
Has the supplier signed up to Premier Supplier Programme (PSP)? If yes, have Y you informed legal the PSP Supplier Participation Agreement will need to be included in the contract? Y
An Equality Analysis has been undertaken, reviewed, and approved by the Y Equalities Manager, Denise McCausland Awarded supplier’s response to Equalities questions (section 8 of the Tender Response Document) has been sent to Equalities Manager, N Denise McCausland Has an electronic copy of the contract been requested? N
STAGE 1 APPROVAL: Strategic Procurement 21/01/22 Matthew Devan Manager STAGE 2 APPROVALS Departmental sign-off Who Date Circulated Date Approved
Page 1 of 17 Budget Approved by relevant 19/11/21 27/01/22 Matthew Davis dept. S151 Finance Officer Confirm relevant Cabinet 27/01/21 27/01/21 Cllr Callton Young Member is sighted on the report Confirm relevant Cabinet 21/01/22 30/01/22 Cllr Patricia Hay- Member is sighted on the Justice report Interim Corporate Director of 21/01/22 30/01/22 Richard Ennis Resources Interim Director of Commercial 21/01/22 27/01/22 Peter Mitchell Investment and Capital Interim Corporate Director of 21/01/22 27/01/22 David Padfield Housing Human Resources Jennifer Sankar 26/11/21 21/01/22 Legal Services Sonia Likhari 19/11/21 21/01/22 Equalities Manager Denise McCausland 26/11/21 21/01/22 Relevant Head of Service C&P Scott Funnell 19/11/21 20.01.22 CCB Inbox [email protected] <insert> N/A STAGE 3 APPROVALS (CCB) Approval CCB sign-off Date reference number Director of C&P Director of Law & Governance Head of Commissioning & Procurement Director of Finance & deputy Section 151 CCB1723/21-22 01.02.2022 Officer Commissioning & Procurement Governance Manager
Page 2 of 17 REPORT TO: CABINET FEBRUARY 2022
SUBJECT: Corporate Cleaning and Security Contracts
LEAD OFFICER: Richard Ennis Interim Corporate Director of Resources David Padfield Interim Corporate Director of Housing Peter Mitchell Interim Director of Commercial Investment and Capital
CABINET MEMBER: Councillor Patricia Hay-Justice, Cabinet Member for Homes Councillor Callton Young, Cabinet Member for Resources and Financial Governance
WARDS: All
CORPORATE PRIORITY Our priorities – 2021-2024 for Croydon will support the delivery of the new administration priorities as set out below:
We will focus on providing the best quality core service we can afford. First and foremost, providing social care services that keep our most vulnerable residents safe and healthy. And to keep our streets clean and safe. To ensure we get full benefit from every pound we spend, other services in these areas will only be provided where they can be shown to have a direct benefit in keeping people safe and reducing demand.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Corporate Cleaning and Security Services ContractReport | 342 KB | DownloadRead as text |
Follow Cabinet at Croydon and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Sep 2026 | Croydon Youth Justice Plan 2026/27For the reasons set out in the report and its appendix the Executive Mayor and Cabinet AGREED : The plan (Appendix A)... | Agreed | Open |
| 23 Sep 2026 | Temporary Accommodation Strategy and Action PlanFor the reasons set out in the report, the Executive Mayor and Cabinet AGREED : 3.1 Approve the Temporary Accommodati... | Agreed | Open |
| 23 Sep 2026 | Crisis Resilience FundFor the reasons set out in this report and its appendices the Executive Mayor and Cabinet AGREED to: 3.1 Accept the a... | Agreed | Open |
| 23 Sep 2026 | Review of Council Tax Support Scheme 2027-28For the reasons set out in the report and its appendices the Executive Mayor and Cabinet RESOLVED : 2.1 to agree to a... | Agreed | Open |
| 23 Sep 2026 | 2026-27 Period 3 Financial Performance ReportFor the reasons set out in the report, the Executive Mayor and Cabinet AGREED to: 2.1 Note the General Fund revenue b... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.