Opening the Books - Returning the Council to Financial Sustainability (2023/24 Budget Update, MTFS and savings proposals, Period 1 /2 and outturn report)
DecidedExecutive1 paper
Cabinet decided this item on Wednesday 6 July 2022. Below is the council's own wording, with the papers it was decided on.
RESOLVED : 1. The launch of the Executive Mayor’s initiative to ‘Open the Books’ of the Council. 2. A report on the results of the ‘Open the Books’ review would be reported to Cabinet no later than January 2023. 3. The General Fund was projecting a £18.3m service overspend at the end of Period 1 for 2022/23, but that £9.4m of in-year risk and contingency provisions were held corporately that may be used to partially offset that forecast and reduce the projected overspend to £8.9m. 4. That in-year savings would need to be identified for the General Fund to offset the projected overspend of £8.9m to deliver a balanced budget by 31 March 2023. 5. That the budget gap for 2023/24 had initially been identified as £27.4m plus a further £8.7m in the following year but that these gaps have risen to £42.9m and £15.7m respectively based on current known pressures. 6. That further work would be done over the year to identify significant savings to balance the gap in 2023/24 and reduce the gaps in the later years. 7. The timetable for both financial reporting and developing the Budget and Medium-Term Financial Strategy for 2023/24-2025/26. 8. That an allocation of up to £500k would be made from contingency for project support and external specialist advice for the Opening the Books project, in order to undertake a review of its balance sheet, review its capital financing arrangements, oversee the application of the capitalisation directions, undertake a range of reconciliations and review the financial relationships with the Council’s companies. 9. The Housing Revenue Account (HRA) was not projecting a revenue budget variance at the end of Period 1.
Word for word from the decision Croydon published for this meeting.Source: democracy.croydon.gov.uk
SUBJECT: Opening the Books – returning the Council to financial sustainability
Jane West, Corporate Director of Resources LEAD OFFICER: (Section 151) Councillor Jason Cummings Cabinet Member for Finance CABINET MEMBER:
SUMMARY OF REPORT: The Council’s financial position continues to be very challenging. Its past financial problems have not yet been overcome and it is yet to return to financial sustainability. The well documented previous mismanagement of finances has left the Council in a weak position to whether the storm of inflation and global impacts currently being experienced.
Over the last year, the Cabinet has received monthly reports on the General Fund, Housing Revenue Account and Capital Programme, providing a step change improvement in transparency in relation the Council’s finances. Projected outturns, risks and opportunities have been examined in detail each month.
This report launches the next stage in this journey which is the Executive Mayor’s initiative to ‘Open the Books’ of the Council. The Council’s finances will be scrutinised over the next six months through a review of its balance sheet, its capital financing arrangements, all reconciliations and the financial relationships with the Council’s companies. This project will provide a firm base position from which to achieve financial sustainability by 2024/25, in line with the plan reviewed by the Improvement and Assurance Panel which was established by the Department of Levelling Up, Housing and Communities to oversee Croydon’s recovery.
The ‘Opening the Books’ review will further improve the Council’s understanding of its financial risks and will develop additional plans to mitigate them. These plans will contribute to the next stage in the development of the Council’s Medium Term Financial Strategy.
Even before the outcome of the ‘Open the Books’ review, the March 2022 Cabinet report on the General Fund and Housing Revenue Account Budget and MTFS 2022/23- 2024/25 identified that the Council will need to find extensive savings over the next three years and planning is underway for this now. This report provides an update on the development of the Council’s savings strategy for 2023/24 to 2025/26 and a timetable through to the budget and council tax setting meeting in March 2023. This year represents the most challenging to date in terms of delivering the savings already identified at the same time as developing new plans for additional savings on top. Sustained focus on this agenda from the whole organisation is vital.
1 The report also forms part of the Council’s financial management process of publicly reporting financial performance against its budgets on a monthly basis. A narrative update for the Period 1 budget monitor is included.
The final outturn position will be reported once the annual closedown of accounts has been completed, prior to the annual accounts for 2021/22 being published. The latter will be delayed until the autumn 2022 due to outstanding issues in relation to the external audit of the accounts for 2019/20 and 2020/21.
FINANCIAL IMPACT The initiative to ‘Open the Books’ will largely be met from within existing base budget resources but some project support and external specialist advice will need to be sought. A budget of up to £500k is proposed to be set aside as an earmarked reserve at the end of 2021/22 this purpose.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Opening the Books: Returning the Council to Financial Sustainability (2023/24 Budget Update, MTFS and savings proposals, Period 1 /2 and outturn report)Report
37/22Opening the Books - Returning the Council to Financial Sustainability (2023/24 Budget Update, MTFS and savings proposals, Period 1 /2 and outturn report)This decision
Opening the Books - Returning the Council to Financial Sustainability (2023/24 Budget Update, MTFS and savings proposals, Period 1 /2 and outturn report)This decision
Croydon Youth Justice Plan 2026/27For the reasons set out in the report and its appendix the Executive Mayor and Cabinet AGREED : The plan (Appendix A)...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.