RESOLVED : 1.1. To note the progress to date on the structural appraisal of the LPS blocks and the revised early October timescale for receipt of the Stage 1 Structural Appraisal Report. 1.2. To note that the final structural appraisal report on the LPS blocks is forecast to be issued in Summer 2024. 1.3. To note that Reinforced autoclaved aerated concrete (RAAC) has not been identified in the LPS blocks. 1.4. To note the proposal to meet the requirements of the Building Safety Act 2022 relating to LPS/High-Risk Building (HRB) Registration at the end of September and provision of Key Building Information by 28 October 2023. 1.5. To note that procurement has commenced for additional consultancy support to complete key building information requirements. 1.6. To note the Regulator will request a Safety Case Report for all 13,000 HRB’s in England over a 5-year period, often referred to as tranche 1-5. Safety Case Reports are for each individual HRB and need to be submitted within 28 days of the Regulator’s request. The purpose of the Safety Case Report is to evidence the block is safe to occupy and to obtain a Building Assessment Certificate from the Regulator to allow the block to continue to be occupied. 1.7. To note that 15 LPS and 3 other HRB’s are forecast to be requested by the Regulator in Year 1. The Regulator can start to request these from 1st April 2024. No’s 1-87 Regina Road is an LPS block due to be fully vacated in November 2023 in advance of demolition, therefore, a Safety Case Report will not be required from 1st April 2024 for this block. 1.8. To note that if the Building Safety Regulator does not assess a Safety Case Report as being satisfactory they may request a revised Safety Case Report be re-submitted within a defined period. The ultimate sanction is that the Regulator does not issue a Building Assessment Certificate and the block must be vacated.
Word for word from the decision Croydon published for this meeting.Source: democracy.croydon.gov.uk
LONDON BOROUGH OF CROYDON REPORT: Number 8. CABINET
DATE OF DECISION 25 October 2023 REPORT TITLE: UPDATE ON LARGE PANEL SYSTEM TOWER BLOCKS
CORPORATE Susmita Sen DIRECTOR / Corporate Director, Housing DIRECTOR: Niall O’Rourke Head of Building Safety & Compliance LEAD OFFICER: Niall O’Rourke Head of Building Safety & Compliance Email: niall.o’[email protected]
LEAD MEMBER: Cllr Lynne Hale Deputy Mayor and Cabinet Member for Homes
KEY DECISION No REASON: 3923EM N/A
CONTAINS EXEMPT No Public INFORMATION?
WARDS AFFECTED: All
1 SUMMARY OF REPORT
1.1The report is a progress update on the structural appraisal and the more immediate Building Safety Act 2022 requirements on the Large Panel System (LPS) tower blocks in the Housing Revenue Account (HRA) portfolio. This form of construction was used widely in urban areas in the 1960’s and 1970’s and is predominantly associated with tower blocks. Investigations following the Ronan Point disaster highlighted concerns and the need for mitigating measures.
1.2A significant level of activity is taking place to meet the requirements of the Building Safety Act against the various timescales as detailed later in the report. We will achieve Registration with the Building Safety Regulator of High-Rise Residential Buildings at the end of September (the registration deadline being 1 October 2023). Since the registration deadline of 1 October 2023, it is now an offence to allow residents to occupy an unregistered building. We are also on course to make good progress to provide Key Building Information for the end of October. The Key Building Information for a registrable building must be submitted to the Building Safety Regulator within 28 days of completing / submitting the initial registration of that particular building. The Key Building Information focuses on information relating to the building’s structure and fire safety. However, it will be a challenge to have detailed Safety Case Reports in place in time for the earliest date the Building Safety Regulator could request these (which is April 2024).
1.3The approach of The Building Safety Regulator will be to work collaboratively to resolve any potential non-compliance: however, if the matter cannot be resolved, the Building Safety Regulator can take a range of enforcement actions, including issuing compliance notices, prosecution (in some cases), and in extreme cases, the Building Safety Regulator can apply for a special measures order appointing a special measures manager to take over the building safety duties from all accountable persons for the building.
1.4The Building Safety Regulator ‘The Regulator’ stated in August 2023, for the first time, that all LPS tower blocks will be included in the first-year requests for Safety Case Reports. These reports can be requested from 1st April 2024 and need to be submitted within 28 days of The Regulators’ request. The purpose of the Safety Case Report is for the Council to evidence that the blocks are safe to occupy and for the Regulator to provide a Building Assessment Certificate to confirm they are satisfied. If the Regulator is not satisfied with the Safety Case Report, they can re-request a Safety Case Report within a specific timescale. If the Regulator deems that the building is not safe to occupy and does not issue the Building Assessment Certificate, then the block would need to be decanted as a worst case. However, as noted above, the approach stated by The Building Safety Regulator is (at least initially) to work collaboratively to resolve any potential non-compliance.
1.5As LPS blocks will be included in Year 1 Safety Case Reports we are accelerating our activity and will develop a risk register to highlight the risks and develop mitigations.
1.6The Arup stage 1 structural appraisal report for the LPS tower blocks is anticipated in early October and the final structural appraisal in Summer 2024.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Croydon Youth Justice Plan 2026/27For the reasons set out in the report and its appendix the Executive Mayor and Cabinet AGREED : The plan (Appendix A)...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.