Cabinet, Wednesday 14 February 2024 at 6.30pm

Repairs Contracts Update

Noted Executive 1 paper

Cabinet noted this item on Wednesday 14 February 2024. Below is the council's own wording, with the papers it was decided on.

Item124/24

Resolved

1.1. To note the progress following mobilisation of the new housing repair contracts on 1 August 2023. 1.2. To agree the actions proposed as outlined in this report and to report back to Members with an update within six months.
Word for word from the decision Croydon published for this meeting. Source: democracy.croydon.gov.uk

Follow this further

Built from Croydon's papers

What the report saysPro

Report to Cabinet

Reasons for recommendations

2.1The Executive Mayor in Cabinet endorsed the recommended procurement strategy for delivery of the Housing Responsive Repair Service and Heating in June 2022 (Reference CCB1750/22-23).

2.2In accordance with the Procurement strategy, the Council carried out a procurement process compliant with the Public Contract Regulations 2015 (PCR) using the Competitive Procedure with Negotiation (CPN) in relation to Housing Responsive Repairs and Voids. Three main contracts were awarded to Wates Ltd, Mears Group and K&T Heating. These contracts commenced service delivery on 1 August 2023.

2.3The main purpose of this report is to provide an update on the progress of the aforementioned contracts since 1 August 2023 to the present.

3. BACKGROUND AND DETAILS

3.1On 6 March 2023 the Executive Mayor in Cabinet approved the contract award report to replace the Council’s former Housing Responsive Repairs Contract with Axis Europe. Axis had served notice to end the contract with the Council. To mitigate the risk of appointing a single provider, and to attract local and Small and Medium-sized enterprise (SME) contractors, the procurement strategy report (22 June 2022) recommended splitting the contract into four parts as follows:

• Contact Centre – to be insourced • Area 1 Responsive repairs and voids excluding heating • Area 2 Responsive repairs and voids excluding heating • Heating related services

3.2A subsequent Cabinet meeting was held on 24 May 2023, in which the contract award report was approved for the appointment of K&T Heating. This was due to the late withdrawal of PH Jones, who had initially been awarded the heating related services contract.

3.3The three contracts commenced on 1 August 2023, and the Contact Centre was in- sourced to the London Borough of Croydon (LBC). Each initial contract term is six years and eight months, with an option to extend to a maximum contract duration of 10 years and eight months.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Repairs Contracts UpdateReport 178 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 22 attended
MJ
Mayor Jason PerryChair, present
JB
Councillor Jeet BainsCommittee Member, present
JC
Councillor Jason CummingsCommittee Member, present
MG
Councillor Maria GatlandCommittee Member, present
LH
Councillor Lynne HaleCommittee Member, present
YH
Councillor Yvette HopleyCommittee Member, present
OK
Councillor Ola KoladeCommittee Member, present
SR
Councillor Scott RocheCommittee Member, present
AS
Councillor Andy StranackCommittee Member, present
JW
Jane WestOfficer, expected
KK
Katherine KerswellOfficer, expected
PM
Peter MitchellOfficer, expected

All 22 on the meeting page

On this subject at Croydon

Search all
  1. Repairs Contracts UpdateThis decision
  2. Pre-Decision Scrutiny: Re-Procurement of the Repairs/Voids and Heating ContractsAgreed

More from Croydon Cabinet

All decisions
MeetingDecisionOutcome
23 Sep 2026 Croydon Youth Justice Plan 2026/27For the reasons set out in the report and its appendix the Executive Mayor and Cabinet AGREED : The plan (Appendix A)... Agreed Open
23 Sep 2026 Temporary Accommodation Strategy and Action PlanFor the reasons set out in the report, the Executive Mayor and Cabinet AGREED : 3.1 Approve the Temporary Accommodati... Agreed Open
23 Sep 2026 Crisis Resilience FundFor the reasons set out in this report and its appendices the Executive Mayor and Cabinet AGREED to: 3.1 Accept the a... Agreed Open
23 Sep 2026 Review of Council Tax Support Scheme 2027-28For the reasons set out in the report and its appendices the Executive Mayor and Cabinet RESOLVED : 2.1 to agree to a... Agreed Open
23 Sep 2026 2026-27 Period 3 Financial Performance ReportFor the reasons set out in the report, the Executive Mayor and Cabinet AGREED to: 2.1 Note the General Fund revenue b... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies