The Executive Mayor in Cabinet Resolved : 2.1 T o make a one off draw down from H ousing R evenue A ccount reserves to fund: 1. On e off cost for interim technical specialists to deliver the planned 12 - month continuation phase of the NEC Housing project for the year 2024/25 at a cost of £1 . 459 m 2. P urchase of the NEC Risk module at a value of £ 56 k bringing the total cost of £1.515m including th e amount stated in 2.1.1. 2.2 To note that t he portion of this project met by the General Fund is £156,000 in 2024/25 for the work done on Homelessness and Allocations . 2.3 To note that a permanent team for the ongoing improvements and internal support of the system is to be recruited . 2.4 To note that any contract related decisions will be made in accordance with the Tenders and Contracts Regulations and Public Contracts Regulations 2015.
Word for word from the decision Croydon published for this meeting.Source: democracy.croydon.gov.uk
For the reasons set out in the report, the Executive Mayor in Cabinet, is requested to approve the recommendation below:
2.1To make a one off draw down from Housing Revenue Account reserves to fund:
2.1.1. One off cost for interim technical specialists to deliver the planned 12-month continuation phase of the NEC Housing project for the year 2024/25 at a cost of £1.459m
2.1.2. Purchase of the NEC Risk module at a value of £56k bringing the total one off cost of £1.515m including the amount stated in 2.1.1.
2.2To note that the portion of this project met by the General Fund is £156,000 in 2024/25 for the work done on Homelessness and Allocations.
2.3To note that a permanent team for the ongoing improvements and internal support of the system is to be recruited.
2.4To note that any contract related decisions will be made in accordance with the Tenders and Contracts Regulations and Public Contracts Regulations 2015.
Reasons for recommendations
3.1The original project to procure and implement a Housing Management system to replace the OHMS system was initiated, in June 2016 however did not proceed effectively until May 2022 when the project was reinvigorated. The project incorporated change management to influence the culture of the Housing directorate, making sure that adequate records were maintained and putting in mechanisms and policies to administer a sophisticated software system, enabling a performance culture within the directorate. 3.2 The core functionality of the NEC Housing system has gone live which has already moved the London Borough of Croydon (LBC) forward from the position of managing services on the previous, data driven, OHMS system that had been in place for over 20 years. This is only the first step towards taking full advantage of the capabilities of the new system. The initial implementation carried with it the risks of migrating to a new database and the exercise of introducing new ways of working to colleagues within the Council. The second phase does not carry the same risk as a system change but still requires embedding the new working practices within the organisation. Whilst the core system has been implemented, Phase 2 is required to realise the system benefits.
3.3Table 1 below outlines the timeline of Phase 1 of the NEC implementation project.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Croydon Youth Justice Plan 2026/27For the reasons set out in the report and its appendix the Executive Mayor and Cabinet AGREED : The plan (Appendix A)...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.