2024-25 Provisional Outturn Financial Performance Report

Agreed Executive 1 paper

Cabinet agreed this item on Wednesday 23 July 2025. Below is the council's own wording, with the papers it was decided on.

Item49/25

Resolved

For the reasons set out in the report, the Executive Mayor and Cabinet AGREED : 2.1 to note the General Fund revenue budget provisional overspend of £29.2m after the one-off benefit of £3.7m transformation earmarked reserves not allocated to transformation/improvement projects. This reduces to a £0.7m underspend after the forecast utilisation of £51m capitalisation directions (including £13m not used in 2023-24), utilisation of the £5.0m risk contingency budget and utilisation of £13.0m corporate earmarked reserves and £3.9m business risk earmarked reserve. 2.2 to note that the provisional outturn is the position prior to final accounting adjustments (e.g. capital accounting/revaluation/receipts) and any impact from potential changes in prior years’ accounts which are being concluded (e.g. debt calculations). Any overspend after the use of non-recurrent mitigations (following final accounting adjustments and any changes required from the external audit) would require funding from other earmarked reserves and/or General Fund balances. Any final underspend would reduce the required use of earmarked reserves. 2.3 to note that the significant level of 2025-26 savings (£21.821m), agreed by Full Council in February 2025, include reduction in budgets that are delivering underspends in 2024-25 and will, therefore, not be recurrent underspends in 2025-26. 2.4 to note that all service directorates were asked to reduce their net expenditure through the in-year Financial Recovery Plan as set out from paragraph 4.16. 2.5 to note the unfunded Local Government cost pressures that emerged nationally, regionally and locally relating to increases in demand and market prices which need to be addressed by Government changes to policy and/or funding levels. 2.6 to note the provisional outturn Medium Term Financial Strategy (MTFS) savings achievement of £22.3m (80.6%) against the total savings target of £27.7m as set out in paragraph 4.143. 2.7 to note the provisional outturn expenditure on the Council’s Transformation Programme as set out from paragraph 4.137. 2.8 to note the Housing Revenue Account (HRA) revenue budget provisional outturn overspend of £6.3m. 2.9 to note the General Fund capital programme 2024-25 provisional outturn underspend of £16.2m against the capital budget of £137.4m. 2.10 to note the HRA capital programme 2024-25 provisional outturn underspend of £21.2m against the capital budget of £68.3m. 2.11 to note the Council’s historic borrowing and subsequent debt burden and national, regional and local service pressures continue to be critical to the non sustainability of the Council’s revenue budget as set out from para 4.164. Dialogue with MHCLG continues around options of further financial support from Government to ensure the Council can deliver sustainable Local Government services. 2.12 to note that the Council continues to operate Spend Control Panels, and tightened the criteria from July 2024, to ensure that stringent financial control and assurance oversight are maintained.
Word for word from the decision Croydon published for this meeting. Source: democracy.croydon.gov.uk

Follow this further

Built from Croydon's papers

What the report saysPro

Report to Cabinet

LONDON BOROUGH OF CROYDON REPORT: CABINET

DATE OF DECISION: 23 July 2025

REPORT TITLE: 2024-25 Provisional Outturn Financial Performance Report

CORPORATE Jane West DIRECTOR: Corporate Director of Resources (Section 151 Officer)

LEAD OFFICER: Allister Bannin, Director of Finance (Deputy S151)

LEAD MEMBER: Cllr Jason Cummings, Cabinet Member for Finance

KEY DECISION? No Reason: N/A

CONTAINS EXEMPT No Public INFORMATION? Grounds for the exemption: N/A

WARDS AFFECTED: All

1 SUMMARY OF REPORT

1.1This report provides the Council’s provisional outturn (prior to final accounting adjustments and external audit review) financial performance for 2024-25 for the General Fund, Housing Revenue Account (HRA) and the Capital Programme. The report forms part of the Council’s financial management process for publicly reporting financial performance on a monthly basis and supports the Mayor’s Business Plan 2022-2026 objective one “The council balances its books, listens to residents and delivers good sustainable services”.

Financial Performance Summary Table

Financial Performance Area 2024-25 2024-25 2024-25 2024-25 Revised Forecast Forecast Forecast Budget Variance Variance (£m) (£m) (£m) (%) Revenue Forecast (General Fund) 361.3 360.6 (0.7) (0.2%) Revenue Forecast (Housing Revenue Account) - 6.3 6.3 N/A Capital Forecast (General Fund) 137.4 121.2 (16.2) (11.8%) Capital Forecast (Housing Revenue Account) 68.3 47.1 (21.2) (31.1%) 2 RECOMMENDATIONS For the reasons set out in the report, the Executive Mayor and Cabinet are recommended:

2.1to note the General Fund revenue budget provisional overspend of £29.2m after the one-off benefit of £3.7m transformation earmarked reserves not allocated to transformation/improvement projects. This reduces to a £0.7m underspend after the forecast utilisation of £51m capitalisation directions (including £13m not used in 2023-24), utilisation of the £5.0m risk contingency budget and utilisation of £13.0m corporate earmarked reserves and £3.9m business risk earmarked reserve.

2.2to note that the provisional outturn is the position prior to final accounting adjustments (e.g. capital accounting/revaluation/receipts) and any impact from potential changes in prior years’ accounts which are being concluded (e.g. debt calculations). Any overspend after the use of non-recurrent mitigations (following final accounting adjustments and any changes required from the external audit) would require funding from other earmarked reserves and/or General Fund balances. Any final underspend would reduce the required use of earmarked reserves.

2.3to note that the significant level of 2025-26 savings (£21.821m), agreed by Full Council in February 2025, include reduction in budgets that are delivering underspends in 2024-25 and will, therefore, not be recurrent underspends in 2025-26.

2.4to note that all service directorates were asked to reduce their net expenditure through the in-year Financial Recovery Plan as set out from paragraph 4.16.

2.5to note the unfunded Local Government cost pressures that emerged nationally, regionally and locally relating to increases in demand and market prices which need to be addressed by Government changes to policy and/or funding levels.

2.6to note the provisional outturn Medium Term Financial Strategy (MTFS) savings achievement of £22.3m (80.6%) against the total savings target of £27.7m as set out in paragraph 4.143.

2.7to note the provisional outturn expenditure on the Council’s Transformation Programme as set out from paragraph 4.137.

2.8to note the Housing Revenue Account (HRA) revenue budget provisional outturn overspend of £6.3m.

2.9to note the General Fund capital programme 2024-25 provisional outturn underspend of £16.2m against the capital budget of £137.4m. 2.10 to note the HRA capital programme 2024-25 provisional outturn underspend of £21.2m against the capital budget of £68.3m.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2024-25 Provisional Outturn Financial Performance ReportReport 429 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 21 attended
MJ
Mayor Jason PerryChair, present
JB
Councillor Jeet BainsCommittee Member, present
JC
Councillor Jason CummingsCommittee Member, in attendance, virtual
MG
Councillor Maria GatlandCommittee Member, present
LH
Councillor Lynne HaleCommittee Member, present
YH
Councillor Yvette HopleyCommittee Member, present
OK
Councillor Ola KoladeCommittee Member, present
SR
Councillor Scott RocheCommittee Member, present
AS
Councillor Andy StranackCommittee Member, present
JW
Jane WestOfficer, expected
KK
Katherine KerswellOfficer, expected
PM
Peter MitchellOfficer, expected

All 21 on the meeting page

On this subject at Croydon

Search all
  1. 2024-25 Provisional Outturn Financial Performance ReportThis decision
  2. 2025-26 Provisional Outturn Financial Performance ReportAgreed
  3. 2023-24 Provisional Outturn Financial Performance ReportNoted

More from Croydon Cabinet

All decisions
MeetingDecisionOutcome
23 Sep 2026 Croydon Youth Justice Plan 2026/27For the reasons set out in the report and its appendix the Executive Mayor and Cabinet AGREED : The plan (Appendix A)... Agreed Open
23 Sep 2026 Temporary Accommodation Strategy and Action PlanFor the reasons set out in the report, the Executive Mayor and Cabinet AGREED : 3.1 Approve the Temporary Accommodati... Agreed Open
23 Sep 2026 Crisis Resilience FundFor the reasons set out in this report and its appendices the Executive Mayor and Cabinet AGREED to: 3.1 Accept the a... Agreed Open
23 Sep 2026 Review of Council Tax Support Scheme 2027-28For the reasons set out in the report and its appendices the Executive Mayor and Cabinet RESOLVED : 2.1 to agree to a... Agreed Open
23 Sep 2026 2026-27 Period 3 Financial Performance ReportFor the reasons set out in the report, the Executive Mayor and Cabinet AGREED to: 2.1 Note the General Fund revenue b... Agreed Open