CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
London Borough of Croydon
Cabinet, Wednesday 15 October 2025 at 6.30pm

Croydon Companies Supervision and Monitoring Panel - Update Report

Agreed Executive 2 papers

AI summaryCroydon Cabinet delegates power to dissolve dormant council companies and updates the Companies Supervision Panel's terms of reference.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedThree recommendations agreed on company oversight and dissolution powers
MoneyNo direct financial implications reported
What happens nextCELF closure by December 2025Board aims to complete solvent winding down and cancel FCA registration
Who it affectsCouncil companies and subsidiariesCompanies listed in Appendix 1 including CCMC and CELF

What was decided

Cabinet delegated to the Corporate Director of Resources and S151 Officer, in consultation with the Executive Mayor and Cabinet Member for Finance, the power to exercise shareholder functions and dissolve companies, subject to legal and financial due diligence. Report P3

Cabinet approved incorporating the authority to dissolve companies within the CCSMP Terms of Reference. Report 2.2

Cabinet noted the status of Croydon Council companies set out in Appendix 1. Report 2.3

Why

The recommendations enable efficient house-keeping of Croydon companies and avoid additional costs from maintaining legal entities that are no longer required. Report 3.2, 5.17

The CCSMP was set up in response to governance failings identified in Grant Thornton's October 2020 Report in the Public Interest, which found the Council lacked proper control and oversight of its subsidiaries. Report 1.1, 5.2

The panel's work is intended to ensure the Council's strategic objectives are met, the financial impact of companies is understood, and regulatory failings such as strike-offs are avoided. Report 1.2, 5.1, 5.3

What happens next

Croydon Enterprise Loan Fund (CELF) Board aims to complete the solvent winding down of the company by the end of December 2025, novating loans and residual assets to the Council, then cancel its Financial Conduct Authority registration. Report 5.14, 5.15

A dedicated project manager funded by Croydon Central Management Company is being recruited, and a report is being issued to nominate the Corporate Director of Housing as Director of CCMC. Report 5.12

Work continues to transfer accounting and administrative support away from the Council to the Limited Liability Partnerships themselves, and to complete share allocations in CCMC with all three building owners. Report 5.6, 5.10

Options considered

  • Rejected: Alternative options considered. None considered Report 6.1

Implications

  • Financial: No direct financial implications; dissolution of historic companies is good practice and may reduce financial risk and costs for the Council. Report P40, P41
  • Legal: The Council has power to participate as Member, Shareholder or Trustee of a company, LLP or charity under the general power of competence in the Localism Act 2011. Report P42, P43, P44
  • Equalities: CCSMP will monitor equality data and workforce implications; housing and estate management functions will be subject to equality monitoring, including accessibility for disabled residents and service charge affordability. Report P50, P51, P52, P54
  • Staffing: No immediate workforce implications; any matters will be managed in accordance with relevant HR policies and procedures. Report 8.3, P46, P47
  • Other: Governance improvements will include requirements for equality and diversity reporting, transparency, and adherence to the Council's George Floyd Race Matters Pledges, with specific attention to embedding anti-racist practice. Report P52, P53

Who and where

  • Croydon Council companies listed in Appendix 1, including Croydon Central Management Company (CCMC) and Croydon Enterprise Loan Fund (CELF) Report 5.4, 5.7, 5.14
  • Council taxpayers, whose interests the CCSMP is intended to safeguard Report 1.2, 5.3
  • Residents of the Queens Quarter estate, where the Council now provides management services to CCMC after Encore Ltd's exit in August 2024 Report 5.7, 5.11
  • Owners of Bloom House, Chorus Apartments and The Fold (London & Quadrant Housing and Legal & General), who are required to take up CCMC share allocations Report 5.10, P23, P24, P25

Timeline

  • 29 November 2017: Croydon Central Management Company incorporated to manage the Queens Quarter estate Report 5.7
  • 2022: Ownerships of Bloom House, Chorus Apartments and The Fold transferred from the Council on completion of the site Report 5.9
  • October 2020: Grant Thornton's first Report in the Public Interest issued, identifying governance failings Report 1.1, 5.2
  • 26 July 2021: Cabinet established the CCSMP in response to the Grant Thornton report Report 1.1
  • 14 February 2024: Cabinet delegated monitoring of Brick by Brick (Croydon) Limited to the Corporate Director of Resources
  • August 2024: Encore Ltd exited as manager of CCMC; the Council took on a backstop management role Report 5.11
  • 14 October 2024: Previous CCSMP update presented to Cabinet Report 3.1, 5.5
  • 18/09/2025: Legal comments approved by the Head of Commercial, Housing & Litigation Law and Deputy Monitoring Officer Report P44
  • 22/09/2025: Equalities comments reviewed by the Senior Equalities Officer Report P54
  • 26/09/2025: Finance comments approved by the Director of Finance (Deputy s151 Officer) Report P41
  • End of December 2025: CELF Board aims to complete solvent winding down and cancel FCA registration Report 5.15

Plain English for the jargon

  • CCSMP: Croydon Companies Supervision and Monitoring Panel, established by Cabinet on 26 July 2021 to oversee the Council's companies
  • CCMC: Croydon Central Management Company Ltd, incorporated 29 November 2017 to manage the Queens Quarter estate
  • CELF: Croydon Enterprise Loan Fund, currently being wound down
  • S151 Officer: The Council's statutory Chief Finance Officer, responsible under section 151 of the Local Government Act 1972
  • LLP: Limited Liability Partnership
  • FCA: Financial Conduct Authority, the UK financial services regulator
  • NIA: Net Internal Area, used to determine share allocations in CCMC
  • Brick by Brick (Croydon) Limited: A Council subsidiary, separately monitored under powers delegated on 14 February 2024, and excluded from this report
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item70/25

Resolved

For the reasons set out in the report, the Executive Mayor and Cabinet AGREED : 2.1 To delegate to the Corporate Director of Resources and S151 Officer, in consultation with the Executive Mayor and Cabinet Member for Finance, the power to exercise shareholder functions and dissolve companies subject to necessary legal and financial due diligence and consultation at Croydon Companies Supervision and Monitoring Panel. 2.2 To approve to incorporate the authority to dissolve companies within the CCSMP Terms of Reference. 2.3 To note the status of Croydon Council companies as set out in Appendix 1.
Word for word from the decision Croydon published for this meeting. Source: democracy.croydon.gov.uk

Follow this further

Built from Croydon's papers

What the report saysPro

Report to Cabinet

Executive summary

1.1This report provides an update to Cabinet from the Croydon Companies Supervision and Monitoring Panel (CCSMP), established by Cabinet on 26 July 2021, as a response to the governance failings identified in Grant Thornton’s Report in the Public Interest, issued in October 2020. The Council had created a series of complicated company structures but did not have the right control or oversight in place to ensure the effective management of them. This had led to a situation where relationships were not understood, and regulatory failings resulted in the strike-off of one of the Council’s subsidiaries.

1.2Amongst the recommendations accepted by Cabinet on 26 July 2021 was a requirement that the Council review arrangements to govern its interest in subsidiaries and ultimately ensure the Council’s and taxpayers’ interests are safeguarded. The work of the panel ensures that the Council’s strategic objectives are met, the financial impact of Council companies is understood, and regulatory failings such as strike offs are avoided. 1.3 The report provides an update on the status of Council companies that exist but excludes Brick by Brick (Croydon) Limited. This is monitored in accordance with the powers delegated by the Cabinet to the Corporate Director of Resources, in consultation with the Executive Mayor, at the meeting held on 14 February 2024.

2 RECOMMENDATIONS For the reasons set out in the report, the Executive Mayor and Cabinet is recommended: 2.1 To delegate to the Corporate Director of Resources and S151 Officer, in consultation with the Executive Mayor and Cabinet Member for Finance, the power to exercise shareholder functions and dissolve companies subject to necessary legal and financial due diligence and consultation at Croydon Companies Supervision and Monitoring Panel.

2.2To approve to incorporate the authority to dissolve companies within the CCSMP Terms of Reference.

2.3To note the status of Croydon Council companies as set out in Appendix 1.

Reasons for recommendations

3.1This report provides a further update on Croydon Council companies since the last update was presented to Cabinet on 14 October 2024.

3.2Recommendation 2.1 and 2.2 will enable the efficient house-keeping of Croydon companies, and avoid additional costs associated with maintaining legal entities that are no longer required.

4 CONTRIBUTION TO EXECUTIVE MAYOR PERRY’S BUSINESS PLAN

Outcome 1: The Outcome 2: Outcome 3: Outcome 4: Outcome 5: Council Croydon is a Children and Croydon is a People can lead balances its place of young people in cleaner, safer and healthier and books, listens to opportunity Croydon have healthier place, a independent lives residents and for business, the chance to borough we’re for longer. delivers good earning and thrive, learn and proud to call sustainable learning. fulfil their home. services. potential.

✓ 5 BACKGROUND AND DETAILS Overview of Croydon Companies

5.1The Croydon Companies Supervision and Monitoring Panel (CCSMP) was established with the purpose of ensuring that the Council’s strategic objectives are met, and to support the development of the Council group of companies in line with the Council’s regulations and strategic objectives.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Company Matrix 2 September 2025 /25Appendix 1 535 KB Download
PDF
Croydon Companies Supervision and Monitoring Panel: Update ReportReport 132 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 21 attended
MJ
Mayor Jason PerryChair, present
JB
Councillor Jeet BainsCommittee Member, present
JC
Councillor Jason CummingsCommittee Member, present
MG
Councillor Maria GatlandCommittee Member, present
LH
Councillor Lynne HaleCommittee Member, present
YH
Councillor Yvette HopleyCommittee Member, present
OK
Councillor Ola KoladeCommittee Member, present
SR
Councillor Scott RocheCommittee Member, present
AS
Councillor Andy StranackCommittee Member, present
JW
Jane WestOfficer, expected
KK
Katherine KerswellOfficer, expected
PM
Peter MitchellOfficer, expected

All 21 on the meeting page

On this subject at Croydon

Search all
  1. Croydon Companies Supervision and Monitoring Panel - Update ReportThis decision
  2. Croydon Companies Supervision and Monitoring Panel - Update ReportApproved
  3. Croydon Companies Supervision and Monitoring Panel - Update ReportNoted
  4. Croydon Council Companies (excluding Brick by Brick Croydon Ltd) Update ReportApproved
  5. Governance of Croydon Council CompaniesDecided
  6. Strategic Review of Companies and other investment arrangements - Brick by Brick Croydon Ltd ("BBB") Shareholder decision - Directors and articles of associationDecided

More from Croydon Cabinet

All decisions
MeetingDecisionOutcome
23 Sep 2026 Croydon Youth Justice Plan 2026/27For the reasons set out in the report and its appendix the Executive Mayor and Cabinet AGREED : The plan (Appendix A)... Agreed Open
23 Sep 2026 Temporary Accommodation Strategy and Action PlanFor the reasons set out in the report, the Executive Mayor and Cabinet AGREED : 3.1 Approve the Temporary Accommodati... Agreed Open
23 Sep 2026 Crisis Resilience FundFor the reasons set out in this report and its appendices the Executive Mayor and Cabinet AGREED to: 3.1 Accept the a... Agreed Open
23 Sep 2026 Review of Council Tax Support Scheme 2027-28For the reasons set out in the report and its appendices the Executive Mayor and Cabinet RESOLVED : 2.1 to agree to a... Agreed Open
23 Sep 2026 2026-27 Period 3 Financial Performance ReportFor the reasons set out in the report, the Executive Mayor and Cabinet AGREED to: 2.1 Note the General Fund revenue b... Agreed Open