Joint Street Lighting PFI Update

Noted Committee 1 paper

AI summaryCroydon and Lewisham joint committee notes street lighting PFI performance and approves 2025/6 unitary charges of £2.978m for Croydon and £1.675m for Lewisham.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedPerformance noted and 2025/6 costs approved
Money£2.978m and £1.675m unitary chargesPlus £185,254 and £104,205 management costs
What happens nextSubmit estimates by 30 NovemberSet joint committee budget by 15 March
Who it affectsCroydon and Lewisham residentsUsers of street lighting across both boroughs

What was decided

The committee noted the service provider's performance for the street lighting PFI from September 2024 to August 2025. Report P1, 2.1

The committee approved the proposed unitary charges for 2025/6 of £2.978m for Croydon and £1.675m for Lewisham, based on a 64% to 36% split. Report P2

The committee approved the forecasted contract management and monitoring costs for 2025/6 of £185,254 for Croydon and £104,205 for Lewisham, based on a 64% to 36% split. Report P3

Why

The report advises the committee of the overall performance of the service provider during the period and presents the proposed charges for approval. Report 2.1, 5.1

The service provider continued to perform at a high standard, achieving 99% of lights in light throughout the period with no financial adjustments. Report 3.5

Both Croydon and Lewisham have completed the refinancing of the senior debt related to the joint street lighting PFI. Report 5.5

What happens next

The Joint Committee is required to submit final estimates for approval to the constituent authorities no later than 30 November and to set its budget no later than 15 March each year. Report 5.1

Both authorities are progressing LED lantern replacements, with heads of terms agreed and installation targeted to start in August 2026, subject to the high value change process.

Ongoing discussions are taking place with the SPV and service provider to agree the design and lantern specification, with best value and price being sought.

The money

  • £2.978m Proposed unitary charge for 2025/6 for Croydon (64% share) Report P2, 5.2
  • £1.675m Proposed unitary charge for 2025/6 for Lewisham (36% share) Report P2, 5.2
  • £185,254 Forecasted contract management and monitoring costs for 2025/6 for Croydon Report P3, 5.3
  • £104,205 Forecasted contract management and monitoring costs for 2025/6 for Lewisham Report P3, 5.3
  • £11.839m Anticipated total PFI cost for 2025/26 Report 5.2

Options considered

  • Chosen: Note service provider performance for September 2024 to August 2025 Report P1
  • Chosen: Approve proposed unitary charges for 2025/6 of £2.978m for Croydon and £1.675m for Lewisham. Based on the agreed 64% to 36% split Report P2
  • Chosen: Approve forecasted contract management and monitoring costs for 2025/6. Based on 64% to 36% split Report P3

Implications

  • Financial: Croydon's share of the unitary charge is £2.978m and contract management costs are £185,254 for 2025/6; Lewisham's share is £1.675m and £104,205 respectively. Report P2, P3, 5.2, 5.3
  • Financial: Sinking fund contributions for 2025/26 have been adjusted and are offset in part by contract performance deductions. Report 5.4
  • Equalities: The PFI contributes to community safety, accessibility and well-being across all wards, with variable lighting policies subject to equality impact assessments. Report P116
  • Climate: Croydon has set a target to be carbon neutral by 2030 and will need additional zero carbon electricity to achieve that target. Report 9.3, P121
  • Climate: Lewisham's street lighting equates to just over 7% of the Council's scope 1 and 2 emissions from sources owned and managed by the Council in 2022/23. Report 9.4, P123
  • Risk: During September 2024 to August 2025 there were no serious, urgent or routine service failures under working practices, the first time since the contract started. Report P77

Who and where

  • Residents of the London Borough of Croydon Report P132
  • Residents of the London Borough of Lewisham Report P132
  • Street lighting users across both boroughs Report 10.1
  • Women and girls, older residents, people with disabilities and nighttime users of public spaces Report P116

Timeline

  • 31 October 2016: Core Investment Programme completed Report 3.3, P10
  • 2025/6: Year to which the approved unitary charges and contract management costs apply Report P2, P3
  • November 30: Deadline for the Joint Committee to submit final estimates to constituent authorities Report 5.1
  • March 15: Deadline for the Joint Committee to set its budget Report 5.1
  • September 2024 - August 2025: Reporting period for service provider performance Report P1, 2.1
  • August 2026: Target start date for installation of new LED lanterns, subject to the high value change process
  • 2024/25: Croydon street lighting consumption 6,964,359 kWh and CO2 emissions 1,553 tonnes; Lewisham 4,197,246 kWh and 936 tonnes Report P121, P123

Plain English for the jargon

  • PFI: Private Finance Initiative, a way of funding public infrastructure projects with private sector finance
  • Unitary charge: The annual payment made by the councils to the service provider under the PFI contract
  • CMS: Central Management System, a system that allows streetlights to be remotely monitored, dimmed and controlled
  • CIP: Core Investment Programme, the initial five-year programme of street lighting replacement
  • Output Specification: The contract document that sets out the required outcomes, service delivery, performance requirements and measurement criteria
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item5/21

Resolved

RESOLVED to: Note the performance of Service Provider in respect of the street lighting PFI for September 2024 - August 2025 Approve the proposed unitary charges for 2025/6 of £2.978m for Croydon and £1.675m for Lewisham (based on a 64% to 36% split) Approve the forecasted contract management and monitoring costs for 2025/6 of £185,254 for Croydon and £104,205 for Lewisham (based on 64% to 36% split).
Word for word from the decision Croydon published for this meeting. Source: democracy.croydon.gov.uk

Follow this further

Built from Croydon's papers

What the report saysPro

Report to Croydon & Lewisham Street Lighting Joint Committee

Recommendations

For the reasons set out in the report the Committee is asked to: • Note the performance of Service Provider in respect of the street lighting PFI for September 2024 - August 2025

• Approve the proposed unitary charges for 2025/6 of £2.978m for Croydon and £1.675m for Lewisham (based on a 64% to 36% split)

• Approve the forecasted contract management and monitoring costs for 2025/6 of £185,254 for Croydon and £104,205 for Lewisham (based on 64% to 36% split).

Actions from last meeting: 10 December 2024

None. 2.Executive Summary

2.1This report advises the Committee of the overall performance of the service provider during September 2024 – August 2025.

3.Detail: Operational Performance Standards Overview

3.1The Output Specification for this contract defines both Councils’ requirements for the service that the service provider shall provide pursuant to this contract. The performance standards within the Output Specification specify the required outcome, service delivery, performance requirements and measurement criteria in respect of each part of the service. The performance is reviewed on a monthly basis as part of the “Monthly Monitoring/Payment Report” and this is linked directly to any financial adjustments for failing to meet the minimum requirements set out each performance standard.

3.2The service provider shall perform the service in accordance with the following performance standards:

PS1 – Core Investment Programme.

3.3The service provider designed and installed new apparatus during the five-year Core Investment Programme (CIP) across both councils to the current British Standards and contract specification. The Core Investment Programme was completed 31 October 2016. The Croydon Public Lighting Network Cable has been de-energised and abandoned by UKPN. The old stumps that were previously keeping the Public Lighting Network Cable functioning have been completely removed.

PS2 - Planned Maintenance, Inspection and Testing.

3.4This performance standard covers planned maintenance, inspection and testing of street lighting equipment. Routine scouting of all streetlights (including CMS) is undertaken, and the performance is measured over a four-month period. During the period September 2024 – August 2025 the following wards were completed as part of the Annual Programme:

Bulk Clean and Change & Electrical Testing (Columns Y1)

Croydon: Broad Green (1316), Norbury (749), South Norwood (826), Thornton Heath (836), Upper Norwood (1008), Waddon (1152), West Thornton (799),

Lewisham: Blackheath (1023), Grove Park (721), Crofton Park (682),

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Joint Street Lighting PFI UpdateReport 230 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

3 of 4 attended
SR
Councillor Scott RocheCommittee Member, present
RW
Councillor Robert WardCommittee Member, present
AD
Councillor Amanda De RykCommittee Member, apologies
LK
Councillor Louise KrupskiCommittee Member, present

On this subject at Croydon

Search all
  1. Joint Street Lighting PFI UpdateThis decision
  2. Joint Street Lighting PFI UpdateNoted
  3. Joint Street Lighting PFI UpdateNoted

More from Croydon Croydon & Lewisham Street Lighting Joint Committee

All decisions
MeetingDecisionOutcome
4 Nov 2025 Appointment of Chair and Vice-ChairTo appoint Councillor Scott Roche as the Chair of the Committee for the 2025-26 Municipal Year. The Chair, Councillor... Decided Open
4 Nov 2025 Minutes of the previous meetingThat the minutes of the meeting held on 10 December 2024 be agreed as a correct record of the meeting. Agreed Open
19 Oct 2023 Appointment of Chair and Vice-ChairThat Councillor Scott Roche be appointed as Chair of the Committee for the 2023-24 Municipal Year. The Chair, Council... Decided Open
19 Oct 2023 Minutes of the previous meetingRESOLVED that the minutes of the meeting held on 13 October 2022 be agreed as a correct record of the meeting. Agreed Open
19 Oct 2023 Joint Street Lighting PFI UpdateRESOLVED to: • Note the performance of Service Provider in respect of the street lighting PFI for September 2022 - Au... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies