AI summaryCroydon's Audit and Governance Committee noted the November 2025 corporate risk register covering five strategic outcomes and agreed to pick risks for future deep dives.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedAppendices 1 to 5, aligned to Mayor's Business Plan
MoneyNo direct financial impactNoted in the report
What happens nextFuture committee meetingsDeep dives on selected risks
Who it affectsCouncil and residentsRisk oversight and equalities

What was decided

The committee noted the corporate risk register as of November 2025, set out in Appendices 1 to 5 and aligned to the five strategic outcomes of the Mayor's Business Plan. Report 3.1, P3

Members agreed which risks will be the subject of a risk 'deep dive' at subsequent committee meetings, rather than being limited to risks rated red at any one point. Report 3.2

Why

The committee's terms of reference require it to monitor the council's risk management arrangements and provide independent assurance on their adequacy. Report P35

A complete overview of the risk register lets members choose deep dive topics from the full picture, not just current red rated risks. Report 3.2

Recent benchmarking with 18 local authorities found Croydon's approach generally in line with others, including use of a 5x5 matrix and quarterly risk reviews. Report 4.2, 4.3, 4.4

What happens next

Risks selected by members for deep dive will be examined at future meetings of the committee. Report 3.2

Work continues to embed the structured risk appetite approach across the Future Croydon Transformation Plan, supported by Zurich Resilience Solutions, alongside ongoing data quality improvements. Report 4.8, 4.13, P25

Implications

  • Financial: No direct financial implications arise from noting the report. The council's financial reporting and medium term strategy take account of the risk management framework. Report P30, P31, P32, P34
  • Legal: Under the Accounts and Audit Regulations 2015 the council must maintain a sound system of internal control including risk management, which the committee's oversight supports. Separate legal advice will be taken on specific risks as needed. Report P35, P36, P37
  • Equalities: The Public Sector Equality Duty applies. Unmanaged risks on financial sustainability, housing, safeguarding, or workforce diversity could disproportionately affect people with protected characteristics, and the framework should also consider risks affecting Minoritised communities. Report P41, P42, P43, P44, P45, P46
  • Staffing: No immediate human resources implications, though any staffing related risks will be managed through the council's HR policies and procedures. Report 8.3, P39, P40
  • Risk: Council risk appetite across the transformation plan is rated as Open on Residents Services and Pace or Workforce, Cautious on Financial and Legal or Regulatory, and Ambitious on Reputation, using the 1 to 5 scale in the HM Treasury Orange Book. Report 4.9, 4.10, P18, P19, P20, P21, P22

Who and where

  • Croydon Council, through its corporate risk register and transformation plan Report P3, 4.7
  • Members of the Audit and Governance Committee, who will lead selected deep dives Report 3.2
  • Residents and staff, where unmanaged risks could affect service delivery or protected groups Report P43, P44

Timeline

  • July 2024: Movement in Rating summary report rolled out across the register Report P25
  • September 2025: Previous report to the committee; structured risk appetite work has continued since Report 4.8
  • October 2025 (committee meeting): Cyber risk deep dive delivered to the committee Report P25
  • November 2025: Corporate risk register presented to committee
  • Subsequent committee meetings: Risk deep dives on topics selected by members to take place
  • 06/11/25: Financial comments on the report approved by Head of Finance Report P32
  • 9/11/2025: Equalities comments on the report approved by Equality Lead Report P46
  • 11/11/2025: Legal comments on the report approved by Deputy Monitoring Officer Report P37

Plain English for the jargon

  • Corporate risk register: The council's record of significant strategic risks, scored using a 5x5 matrix and reviewed quarterly.
  • Risk deep dive: A detailed committee examination of a chosen risk, not limited to risks currently rated red.
  • Risk appetite: The amount of risk the council is willing to accept, rated 1 (risk averse) to 5 (risk ambitious) under HM Treasury Orange Book standards.
  • Future Croydon Transformation Plan: The council's change programme covering projects such as Oracle, Digital, Customer Services, Workforce, and Homelessness Prevention.
  • SRO: Senior Responsible Officer, the senior lead accountable for a major project or programme.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item76/25

Resolved

RESOLVED to: Note the contents of the corporate risk register as of November 2025 as set out in Appendices 1-5 aligned to the strategic outcomes of the Mayor’s Business Plan. Agree which risk(s) will be subject of a risk ‘deep dive’ at subsequent meetings of the committee.
Word for word from the decision Croydon published for this meeting. Source: democracy.croydon.gov.uk

Follow this further

Built from Croydon's papers

What the report saysPro

Report to Audit & Governance Committee

Reasons for recommendations

3.1This report and accompanying appendices presents a dashboard summary report of the complete risk register. These are recommended to the committee for consideration to assist the Audit & Governance Committee in its role of overseeing the risk management framework and enable it to provide assurance that significant corporate risks are identified and mitigated by the Council.

3.2A complete overview of the corporate risk register will enable Members to determine which risks to make the subject of a risk ‘deep dive’ rather than the committee being limited to risks which are recorded as red rated at any one point.

4 BACKGROUND AND DETAILS 4.1 The registers present a dashboard summary of the complete corporate risk register appendices 1-5, aligned to the five strategic outcomes of the Mayor’s Business Plan.

Benchmarking

4.2Croydon recently took part in risk management benchmarking with other Local Authorities via the JC Application Development user forum. In summary 18 authorities took part to compare their risk management frameworks and approach and secondly the contents of their corporate risk register.

4.3The results for Croydon confirmed our approach to be generally in line/standard with others. In particular, 12 out of 18 (including Croydon) use a 5x5 matrix to score their risks. 13 out of 18 have a three part risk scoring approach: Gross/Inherent/Uncontrolled, Controlled/Current/Residual and lastly Target/Future/Predicted. 14 out of 18 (including Croydon) require their risks to be formally reviewed quarterly.

4.4All of the respondents report risks to their Audit Committee.

4.5Asked to classify their top 5 corporate risks responses again generally mirrored the situation in Croydon as follows:

Top 5 Risks % Financial Sustainability 90 Demand-led & Statutory 75 Cyber & Information Governance 65 Transformation & Workforce Capacity 60 Climate & Environmental 35 Assets & Regeneration in public realm 30 and HRA Governance & Partnerships inc NHS 25 Social Cohesion & Health 15

4.6The risk categories presented above feature heavily on the Croydon risk register and suggest our approach is in line with others, particularly in relation to demand/budget gap, cyber risk and information management governance and the demands of transformation and workforce capacity to deliver change quickly.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Fixing Our Finances Risks /25Appendix 1 60 KB Download
PDF
Place of Opportunity Risks /25Appendix 2 45 KB Download
PDF
Children & Young People Risks /25Appendix 3 51 KB Download
PDF
Cleaner, Safer & Healthier Risks /25Appendix 4 54 KB Download
PDF
Healthier Independent Lives Risks /25Appendix 5 48 KB Download
PDF
One-Page-Guide- Risk Scoring /25Appendix 6 207 KB Download
PDF
Corporate Risk ManagementReport 134 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 11 attended
OO
Dr Olu OlasodeIndependent Chair, present
MG
Councillor Matt GriffithsVice-Chair, present
CB
Councillor Claire BonhamCommittee Member, present
SB
Councillor Simon BrewCommittee Member, present
AF
Councillor Alisa FlemmingCommittee Member, present
EM
Councillor Enid MollyneauxCommittee Member, present
IP
Councillor Ian ParkerCommittee Member, present
RP
Councillor Ria PatelCommittee Member, present
DC
David Clarke (Independent Member)Public, present
JW
Jane WestOfficer, expected
TA
Tariq Aniemeka-BaileySecretary, expected

On this subject at Croydon

Search all
  1. Corporate Risk ManagementThis decision
  2. Corporate Risk Management (PART A)Noted
  3. Corporate Risk RegisterNoted
  4. Part A - Corporate Risk RegisterNoted
  5. Corporate Risk RegisterNoted
  6. Corporate Risk RegisterNoted

More from Croydon Audit & Governance Committee

All decisions
MeetingDecisionOutcome
25 Jun 2026 Minutes of the Previous MeetingRESOLVED to approve the minutes of the meetings held on Thursday, 12 March 2026 as accurate records. Approved Open
25 Jun 2026 Counter Fraud Annual Report 2025-26RESOLVED to: 1. Note the contents of the Counter Fraud Annual Report and Appendix. Noted Open
25 Jun 2026 Exclusion of Press and PublicRESOLVED that members of the Press and Public be excluded from the remainder of the meeting under Section 100A(4) of ... Decided Open
12 Mar 2026 Minutes of the Previous MeetingRESOLVED to approve the minutes of the meetings on Monday, 23 February 2026 as accurate records. Approved Open
12 Mar 2026 Draft 2026-27 Committee Work Programme & Committee Assurance Mapping DocumentRESOLVED to: Consider and approve the Audit & Governance Committee’s Draft Work Programme for 2026/27, Appendix A. Id... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies