Cabinet, Wednesday 3 December 2025 at 6.30pm

2025-26 Period 6 Financial Performance Report

Agreed Executive 1 paper

AI summaryCroydon Cabinet noted a £23.8m forecast underspend on General Fund revenue at Period 6, cutting the needed capitalisation direction from £136m to £112.2m, and approved a £3.022m budget virement from Resources to Housing.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedGeneral Fund revenue forecast to underspend by £23.8m; quarterly reporting adopted
MoneyNot stated
What happens nextService directorates to cut net spendMove to quarterly full Cabinet reports; next full report at Period 9
Who it affectsCroydon Council finances and directoratesHousing, Resources, ASCH, CYPE, ACE, SCRER; spending controls continue

What was decided

Noted the General Fund revenue outturn is forecast to underspend by £23.8m at Period 6, reducing the capitalisation direction needed from £136m to £112.2m. Report 2.1, 1.1, 4.13

Approved a £3.022m virement from Resources to Housing General Fund to align budget with where temporary accommodation management fees (non-claimable from Housing Benefit subsidy) now sit in the NEC housing IT system. Report 2.2, 4.81

Noted MTFS savings of £21.7m (86.2%) achieved against a £25.1m target, HRA revenue breakeven, and capital programme forecast underspends of £44.8m (General Fund) and £26.8m (HRA). Report 2.6, 2.7, 2.8, 2.9, 1.2

Why

The underspend contributes to the £27.3m Stabilisation Plan stretch target and reduces the use of capitalisation directions to balance the budget. Report 2.1, 2.3, 4.18, 4.19

The virement reflects a change in how temporary accommodation management fees are recorded in the NEC system and is not a change to the budget's purpose agreed by Full Council. Report 2.2, 4.81

Historic borrowing, debt servicing cost (estimated £72m in 2025-26) and unfunded demand and market pressures continue to make the revenue budget unsustainable without Government funding reform. Report 2.4, 2.10, 4.1, 4.3

What happens next

Service directorates are to reduce net expenditure below budget to help balance the year and meet the £27.3m Stabilisation Plan target. Report 2.3, 4.14

Full Financial Performance Reports will move to a quarterly cycle (Periods 3, 6, 9, Outturn); shorter summaries will be published for the other months from Period 2 to Period 10. Report 4.9, 4.10, P36

Spend Control Panels continue with tightened criteria from July 2024 to maintain financial control; the Council awaits the provisional Local Government Finance Settlement, expected after the 26 November 2025 Budget. Report 2.11, 4.8, 4.17

The money

  • £23.8m General Fund revenue forecast underspend at Period 6 (an improvement of £1.2m from Period 5) Report 2.1, 1.1, 4.13
  • £136m to £112.2m Reduction in required capitalisation direction from Government if underspend achieved Report 2.1, 4.13
  • £3.022m Inter-directorate virement from Resources to Housing General Fund for temporary accommodation management fees Report 2.2
  • £27.3m Stabilisation Plan stretch target of unused capitalisation directions Report 2.3, 4.19
  • £21.7m (86.2%) MTFS savings achieved against £25.1m target Report 2.6, 4.14
  • £44.8m (16.2%) General Fund capital programme forecast underspend against £275.9m revised budget Report 2.8, P3, 1.1
  • £26.8m (22.2%) HRA capital programme forecast underspend against £120.5m capital budget Report 2.9, P3, 1.2
  • £72m Estimated 2025-26 cost to service the Council's debt Report 4.1
  • £10.7m 2024-25 Housing Benefit subsidy gap for temporary/emergency accommodation and private tenants Report 4.80
  • £14.0m (16.1%) DSG High Needs forecast overspend against £87.0m budget Report 4.62, P115

Options considered

  • Chosen: Approve the £3.022m virement from Resources to Housing General Fund for temporary accommodation management fees. Aligns budget with where the cost now impacts in the NEC housing IT system following the 2017 change in subsidy rules; not a change to the purpose agreed by Full Council Report 2.2, 4.81
  • Chosen: Move full Financial Performance Reports to a quarterly Cabinet cycle with shorter monthly summaries. Balances transparency with reduced administration time for service and finance officers Report 4.9, 4.10, 4.11
  • Rejected: Retain monthly full Financial Performance Reports to Cabinet. Period 3 report had already planned to remove Periods 4 and 7; further review found the revised quarterly plan best balances transparency and officer time Report 4.9, 4.10, 4.12

Implications

  • Financial: A £23.8m General Fund underspend forecast would reduce the required capitalisation direction from £136m to £112.2m and contribute to the £27.3m Stabilisation Plan target; £24.4m of the £27.3m is evidenced to date. Report 2.1, 2.3, 2.8, 4.13, 4.19
  • Financial: Council Tax collection at 51.55% is 0.53% (about £1.4m) behind the 52.08% target at end of September 2025; Business Rates collection at 59.18% is 0.99% above target. Report P214, P219
  • Financial: Treasury management shows a small forecast pressure on interest payable (£0.2m) and receivable (£0.5m), being offset by miscellaneous corporate income. Report P224
  • Legal: Historic borrowing and debt servicing, plus unfunded demand and market pressures, are described as critical to the non-sustainability of the revenue budget and require Government funding or policy change. Report 2.4, 2.10, 4.1, 4.2, 4.3
  • Legal: MHCLG-appointed Commissioners continue to support the Council in meeting its Best Value Duty, funded from a £0.6m Improvement Costs budget in the Finance division. Report 4.89
  • Risk: DSG High Needs pressure of £14.0m is above the Safety Valve Team target, reflecting local and national SEND demand growth; CIPFA has been commissioned to review placement cost recording and IT options. Report 4.62, 4.63, 4.64, 4.67
  • Risk: Housing Benefit subsidy for temporary accommodation is frozen at 90% of 2011 Local Housing Allowance, creating a £10.7m cost pressure in 2024-25; nightly paid demand remains high. Report 4.80, 4.75, P170
  • Staffing: The Stabilisation Plan action to accelerate the Target Operating Model Programme is rated Red, with no evidence of delivery to date. Report P51, P54
  • Other: Opening of Precious House children's home is dependent on Ofsted registration; approval anticipated in November 2025, leaving a £0.1m cost pressure in 2025-26 from the pre-opening period. Report 4.22, 4.56

Who and where

  • Service directorates (ASCH, ACE, CYPE, Housing, Resources, SCRER) tasked with reducing net expenditure below budget Report 2.3, 4.14, P42
  • Households in temporary accommodation, including those placed out of borough Report 4.20, 4.21, P57, P67
  • Croydon Council tenants and leaseholders, via the HRA capital programme Report 2.9, 1.2
  • Children and young people with SEND and their families, given the £14.0m DSG High Needs overspend Report 4.62
  • Croydon residents, as the Stabilisation Plan affects housing, prevention and customer access services Report 2.3, 4.19, 4.20
  • MHCLG-appointed Commissioners overseeing the Council's Best Value Duty Report 4.89

Timeline

  • 11 June 2025: Government Spending Review 2026-27 to 2028-29 presented to Parliament Report 4.2
  • 20 June 2025: Fair Funding Review 2.0 consultation launched; closed 15 August 2025 Report 4.5
  • 25 June 2025: Stabilisation Plan approved by the Executive Mayor and Cabinet Report 4.18
  • September 2025: Period 6 reporting month (actuals to date at end of September 2025) Report 1.1
  • November 2025 (anticipated): Ofsted registration decision on Precious House children's home Report 4.22, 4.56
  • 26 November 2025: Government Budget announcement; provisional LGFS expected late December Report 4.8
  • 2025-26 financial year: Service directorates to reduce net spend to meet £27.3m Stabilisation Plan target and balance the budget Report 2.3, 4.14
  • From Period 2 to Period 10 (non-quarterly months): Shorter Financial Performance Summaries to be published; full reports to Cabinet at Periods 3, 6, 9 and Outturn Report 4.10, P36

Plain English for the jargon

  • Capitalisation direction: Exceptional permission from Government allowing a council to treat some revenue spending as capital, used here to balance Croydon's 2025-26 budget given its debt and demand pressures.
  • Stabilisation Plan: Croydon's plan to reduce reliance on capitalisation directions by £27.3m in 2025-26, approved on 25 June 2025.
  • MTFS: Medium Term Financial Strategy, the council's multi-year savings and budget plan; £25.1m target in 2025-26.
  • HRA: Housing Revenue Account, the ringfenced account for income and spending on council housing.
  • DSG High Needs Block: Dedicated Schools Grant funding for SEND pupils aged 0 to 25; Croydon is part of the DfE Safety Valve programme.
  • Virement: Movement of budget between directorates without changing the overall budget purpose.
  • OFLOG: Office for Local Government, which reported that Croydon's debt servicing was 16% of core spending power at end of 2021-22, double the English median.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item99/25

Resolved

For the reasons set out in the report, the Executive Mayor and Cabinet are AGREED : 2.1 to note the General Fund revenue budget outturn is forecast at Period 6 to underspend at financial year end by £23.8m, contributing to the target as required by the Stabilisation Plan. This would reduce the necessary level of capitalisation directions from £136m to £112.2m. 2.2 to approve the inter-directorate virement from Resources to Housing (General Fund) of £3.022m budget to align with where the cost of temporary accommodation management fees (non-claimable from Housing Benefit subsidy) now impacts. This aligns with these costs now being recorded in the NEC housing IT system (no longer counted as part of the rent cost for housing benefit subsidy), as set out from paragraph 5.82. This is not a change to the purpose of the budget agreed by Full Council. 2.3 to note that service directorates have been asked to reduce their net expenditure below their budgets so that the annual budget can be balanced with reduced use of capitalisation directions, including achievement of the £27.3m Stabilisation Plan target as set out from paragraph 5.19. It should not be underestimated what a challenge this will be against the background of increased demand pressures which are continuing to build across local government as well as increased market prices. 2.4 to note the unfunded local government cost pressures that exist nationally, regionally and locally relating to increases in demand and market prices which need to be addressed by Government changes to policy and/or funding levels. 2.5 to note that the presentation of full Financial Performance Reports to Cabinet is being moved to a quarterly basis, with a shortened Financial Performance Summary being published for other months from Period 2 to Period 10 on the Council’s Corporate Performance and Finance Reporting webpage. This change is to ensure regular reporting for transparency whilst also prioritising service and finance officer time on value-added activities including transformation, as set out from paragraph 5.10. 2.6 to note the progress in Medium Term Financial Strategy (MTFS) savings achievement of £21.7m (86.2%) against the total savings target of £25.1m as set out from paragraph 5.125. 2.7 to note the Housing Revenue Account (HRA) revenue budget forecast outturn is a breakeven position. 2.8 to note the General Fund capital programme 2025-26 forecast underspend of £44.8m (16.2%) against the revised budget of £275.9m. The expected decrease in capitalisation direction usage owing to the Stabilisation Plan accounts for £27.3m of the forecast underspend. £24.4m of this is evidenced to date at Period 6 with directorates continuing to reduce their net expenditure wherever possible. 2.9 to note the HRA capital programme 2025-26 forecast underspend of £26.8m (22.2%) against the capital budget of £120.5m. 2.10 to note the Council’s historic borrowing and subsequent debt burden and national, regional and local service pressures continue to be critical to the non-sustainability of the Council’s revenue budget as set out from paragraph 5.146. 2.11 to note that the Council continues to operate Spend Control Panels, ... /25
Word for word from the decision Croydon published for this meeting. Source: democracy.croydon.gov.uk

Follow this further

Built from Croydon's papers

What the report saysPro

Report to Cabinet

Executive summary

1.1The Period 6 (September 2025) financial performance for General Fund revenue shows a forecast underspend of £23.8m against the 2025-26 budget. This is an improvement of £1.2m since Period 5. The General Fund capital programme shows a forecast underspend of £44.8m.

1.2The Housing Revenue Account (HRA) shows a revenue forecast breakeven position for 2025-26. The HRA capital programme shows a forecast underspend of £26.8m. Financial Performance Summary Table

Financial Performance Area 2025-26 2025-26 2025-26 2025-26 Budget Forecast Forecast Forecast Variance Variance (£m) (£m) (£m) (%) Revenue Forecast (General Fund) 375.8 352.0 (23.8) (6.3%) Revenue Forecast (Housing Revenue Account) - - - N/A Capital Forecast (General Fund) 275.9 231.1 (44.8) (16.2%) Capital Forecast (Housing Revenue Account) 120.5 93.7 (26.8) (22.2%)

2 RECOMMENDATIONS For the reasons set out in the report, the Executive Mayor and Cabinet are recommended:

2.1to note the General Fund revenue budget outturn is forecast at Period 6 to underspend at financial year end by £23.8m, contributing to the target as required by the Stabilisation Plan. This would reduce the necessary level of capitalisation directions from £136m to £112.2m.

2.2to approve the inter-directorate virement from Resources to Housing (General Fund) of £3.022m budget to align with where the cost of temporary accommodation management fees (non-claimable from Housing Benefit subsidy) now impacts. This aligns with these costs now being recorded in the NEC housing IT system (no longer counted as part of the rent cost for housing benefit subsidy), as set out from paragraph 5.82. This is not a change to the purpose of the budget agreed by Full Council.

2.3to note that service directorates have been asked to reduce their net expenditure below their budgets so that the annual budget can be balanced with reduced use of capitalisation directions, including achievement of the £27.3m Stabilisation Plan target as set out from paragraph 5.19. It should not be underestimated what a challenge this will be against the background of increased demand pressures which are continuing to build across local government as well as increased market prices.

2.4to note the unfunded local government cost pressures that exist nationally, regionally and locally relating to increases in demand and market prices which need to be addressed by Government changes to policy and/or funding levels. 2.5 to note that the presentation of full Financial Performance Reports to Cabinet is being moved to a quarterly basis, with a shortened Financial Performance Summary being published for other months from Period 2 to Period 10 on the Council’s Corporate Performance and Finance Reporting webpage. This change is to ensure regular reporting for transparency whilst also prioritising service and finance officer time on value-added activities including transformation, as set out from paragraph 5.10.

2.6to note the progress in Medium Term Financial Strategy (MTFS) savings achievement of £21.7m (86.2%) against the total savings target of £25.1m as set out from paragraph 5.125.

2.7to note the Housing Revenue Account (HRA) revenue budget forecast outturn is a breakeven position.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2025-26 Period 6 Financial Performance ReportReport 451 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 21 attended
MJ
Mayor Jason PerryChair, present
JB
Councillor Jeet BainsCommittee Member, present
JC
Councillor Jason CummingsCommittee Member, present
MG
Councillor Maria GatlandCommittee Member, present
LH
Councillor Lynne HaleCommittee Member, present
YH
Councillor Yvette HopleyCommittee Member, present
OK
Councillor Ola KoladeCommittee Member, present
SR
Councillor Scott RocheCommittee Member, present
AS
Councillor Andy StranackCommittee Member, present
JW
Jane WestOfficer, expected
KK
Katherine KerswellOfficer, expected
PM
Peter MitchellOfficer, expected

All 21 on the meeting page

On this subject at Croydon

Search all
  1. 2025-26 Period 6 Financial Performance ReportThis decision
  2. 2026-27 Period 3 Financial Performance ReportAgreed
  3. 2025-26 Period 9 Financial PerformanceAgreed
  4. 2025-26 Period 5 Financial Performance ReportAgreed
  5. 2025-26 Period 3 Financial Performance ReportAgreed
  6. 2025-26 Period 2 Financial Performance ReportAgreed

More from Croydon Cabinet

All decisions
MeetingDecisionOutcome
23 Sep 2026 Croydon Youth Justice Plan 2026/27For the reasons set out in the report and its appendix the Executive Mayor and Cabinet AGREED : The plan (Appendix A)... Agreed Open
23 Sep 2026 Temporary Accommodation Strategy and Action PlanFor the reasons set out in the report, the Executive Mayor and Cabinet AGREED : 3.1 Approve the Temporary Accommodati... Agreed Open
23 Sep 2026 Crisis Resilience FundFor the reasons set out in this report and its appendices the Executive Mayor and Cabinet AGREED to: 3.1 Accept the a... Agreed Open
23 Sep 2026 Review of Council Tax Support Scheme 2027-28For the reasons set out in the report and its appendices the Executive Mayor and Cabinet RESOLVED : 2.1 to agree to a... Agreed Open
23 Sep 2026 2026-27 Period 3 Financial Performance ReportFor the reasons set out in the report, the Executive Mayor and Cabinet AGREED to: 2.1 Note the General Fund revenue b... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies