REPORT ON THE USE OF SPECIAL URGENCY FOR KEY DECISIONS FOR THE FOURTH QUARTER OF 2025, AND THE FIRST AND SECOND QUARTERS OF 2026 AND EXEMPTION FROM CALL-IN FOR THE PERIOD
NotedCommittee1 paper
AI summaryCroydon Council notes use of special urgency for four key decisions and one call-in exemption between December 2025 and June 2026, including a £52.25m regeneration contract award.
Written from the decision and the officer reportPDF Pro
OutcomeNotedSpecial urgency and call-in exemption uses recorded
Money£52.25m GLA grantAt risk if Regina Road decision delayed
What happens nextQuarterly reporting continuesPer amended Constitution rule 34.1
Who it affectsCouncil decision-making transparencyCovers contracts, leases, regeneration
What was decided
Council noted the use of Special Urgency for key decisions listed in section 4.4 covering Q4 2025 and Q1 and Q2 of 2026. Report P6
Council noted the use of Exemption from Call-in for key decisions listed in section 5.3 covering December 2025 to June 2026. Report P7
Why
The Constitution's Access to Information Procedure Rules require quarterly reports to Council on the use of Special Urgency for key decisions. Report 1.1, 3.1, P49
The Scrutiny and Overview Procedure Rules require an annual report on the use of Exemption from Call-in powers, agreed by the Chair of the Scrutiny & Overview Committee. Report 1.3, 3.2, P50
Paragraph 5.2 states there were two cases of Special Urgency approved by the Chair, though section 5.4 lists four decisions taken under the provision. Report 5.2, 5.4
What happens next
Future quarterly reports on Special Urgency use will continue to be presented to full Council where there are decisions to report. Report 5.6, P29
An annual report on Exemption from Call-in will continue to be presented to Council. Report 1.3, 6.1
The money
£52.25m GLA grant funding allocated to Regina Road regeneration project Report P35
£1,000,000 Constitutional threshold above which a decision is defined as a 'key decision' Report P47
Options considered
Chosen: Use Special Urgency provisions (electricity/gas contract extension). Failure to extend would have meant out-of-contract rates and significant extra cost Report P21, P22, P23
Chosen: Use Special Urgency (Red Clover Gardens capital receipt deferral). Commercial considerations still being developed; early publication could limit Council's negotiating position Report P24, P25
Chosen: Use Special Urgency (Croydon Healthy Neighbourhood Low Traffic Neighbourhood decision). High Court judgement handed down 4 March 2026 with appeal deadline 9 March 2026; 28-day notice not possible Report P26
Chosen: Use Special Urgency (Crystal Development Centre new lease to NHS Trust). NHS Trust required the lease to complete before 31 March 2026 Report P27
Chosen: Exempt from Call-in (Regina Road Design and Build contract to Lovell). Contract needed by w/c 16 March 2026 to meet GLA start-on-site deadline; delay risked £52.25m grant Report P34, P35, P36
Chosen: No alternative. Reporting is a constitutional requirement with no alternative options Report 7.1
Implications
Financial: No direct financial implications from the report itself; each underlying decision was financially reviewed separately. Report P40, P41
Legal: Report complies with Local Authorities (Executive Arrangements) (Meetings and Access to Information) (England) Regulations 2012 and the Council's Constitution Parts 4B and 4E. Report P42, P49, P50, P51
Equalities: No evidence of disproportionate adverse impact on groups with protected characteristics; each underlying decision was supported by an EQIA or equivalent analysis. Report P55, P56, P57
Other: Officers reminded that equality analysis must remain proportionate, timely and robust even when using Special Urgency or Call-in Exemption. Report P56
Who and where
Chair of the Scrutiny & Overview Committee (approves urgent decisions) Report P15, 5.2, 6.2
13 March 2026: Notice published: Regina Road Design and Build contract award (call-in exempted) Report P34
27 March 2026: Notice published: Grant of new lease at Crystal Development Centre Report P27
20 July 2026: Council meeting considers the quarterly report
Plain English for the jargon
Special Urgency: Constitutional provision allowing a key decision to be taken without the usual 28 days' prior public notice, where even the 5-day General Exception notice is impractical; requires agreement of the Chair of Scrutiny & Overview Committee.
Exemption from Call-in: Power allowing a key decision to bypass the Scrutiny referral process where delay would seriously prejudice the Council's or public's interests; requires agreement of the Chair of Scrutiny & Overview Committee.
Key decision: An executive decision likely to result in expenditure or savings over £1,000,000, or significant in its effects on two or more wards.
EQIA: Equality Impact Assessment, an analysis of how a decision may affect groups with protected characteristics under the Equality Act 2010.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item37/26
Resolved
RESOLVED to: 2.1.1. note the use of Special Urgency for the key decisions listed at section 4.4 of this report during the fourth quarter of 2025, and the first and second quarters of this year 2.1.2. note the use of Exemption from Call-in for the key decisions listed at section 5.3 of this report during the period December 2025 and June 2026.
Word for word from the decision Croydon published for this meeting.Source: democracy.croydon.gov.uk
1.1In accordance with the Access to Information Procedure Rules (Part 4B of the Constitution), the Executive Mayor is required to submit a quarterly report to Council on the use of Special Urgency for key decisions.
1.2This report details the cases where Special Urgency has been used between December 2025 and June 2026.
1.3In accordance with the Scrutiny and Overview Procedure Rules (paragraph 11.19), Part 4E of the Constitution) the Executive Mayor is also required to submit a report to Council on the use of the exemption from call-in powers agreed by the Chair/the Deputy Chair of the Scrutiny & Overview Committee at least annually.
1.4Therefore, this report also details the cases where Exemption from call-in powers have been used between December 2025 and June 2025. 2. RECOMMENDATIONS
2.1For the reasons set out in the report Council is recommended:
2.1.1. to note the use of Special Urgency for the key decisions listed at section 4.4 of this report during the fourth quarter of 2025, and the first and second quarters of this year.
2.1.2. to note the use of Exemption from Call-in for the key decisions listed at section 5.3 of this report during the period December 2025 and June 2026.
Reasons for recommendations
3.1As noted in paragraph 1.1, there is a requirement within the Access to Information Procedure Rules in the Council’s Constitution that Council will receive a quarterly report on decisions taken under Special Urgency provisions.
3.2As noted in paragraph 1.3, there is a requirement within the Scrutiny and Overview Procedure Rules in the Council’s Constitution that Council must receive a report at least annually on the use of the Exemption from call-in powers.
4. CONTRIBUTION TO EXECUTIVE MAYOR PERRY’S BUSINESS PLAN
A Cleaner, A town centre Stronger A fair deal for Better roads, Places Backing and Safer that is local high residents better people can families, Croydon. busy, confident streets and journeys be proud to young people and thriving economies call home and adults
To note, Executive Mayor’s Business Plan for 2026-2030 approved at Cabinet, pending final approval at Full Council, anticipated October 2026.
5 BACKGROUND AND DETAILS
5.1There is a requirement when making a key decision to give 28 days’ prior public notice. Where the giving of such notice is impracticable the Constitution provides both General Exception and Special Urgency provisions. The General Exception provisions require, amongst other things, a period of five clear working days’ notice to be given. Where compliance with the General Exception principle is impractical the decision can be taken under the Special Urgency provisions. In cases of Special Urgency, the decision may only be made where the decision maker has obtained agreement that the making of the decision is urgent and cannot reasonably be deferred from:
a) The Chair of the Scrutiny & Overview Committee; or
b) If there is not such person, or if the Chair of the Scrutiny & Overview Committee is unable to act, the Chair of the Council; or c) Where there is no Chair of the Scrutiny & Overview Committee or Chair of the Council, the Deputy Chair of the Council.
5.2There have been two cases of the use of Special Urgency procedures during this period which the Chair of Scrutiny & Overview Committee approved after consideration.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
REPORT ON THE USE OF SPECIAL URGENCY FOR KEY DECISIONS FOR THE FOURTH QUARTER OF 2025, AND THE FIRST AND SECOND QUARTERS OF 2026 AND EXEMPTION FROM CALL-IN FOR THE PERIODDecisions
37/26REPORT ON THE USE OF SPECIAL URGENCY FOR KEY DECISIONS FOR THE FOURTH QUARTER OF 2025, AND THE FIRST AND SECOND QUARTERS OF 2026 AND EXEMPTION FROM CALL-IN FOR THE PERIODThis decision
REPORT ON THE USE OF SPECIAL URGENCY FOR KEY DECISIONS FOR THE FOURTH QUARTER OF 2025, AND THE FIRST AND SECOND QUARTERS OF 2026 AND EXEMPTION FROM CALL-IN FOR THE PERIODThis decision
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.