London Borough of Croydon
Planning Committee, Thursday 3 September 2026 at 6.30pm

26/00079/OUT- 1A Brighton Road, South Croydon, CR2 6EA

Decided Planning 3 papers

AI summaryCroydon Planning Committee grants outline permission for six-storey hotel at 1A Brighton Road, South Croydon, with up to 91 rooms, subject to legal agreement and conditions including air quality contribution.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedFor six-storey hotel building with basement and dining
MoneyAir quality contribution setPlus carbon offset and LETS contributions to be calculated
What happens nextLegal agreement to be completedWithin four months or permission may be refused
Who it affectsSouth Croydon ward, 1A Brighton RoadLocally listed Swan and Sugar Loaf building nearby

What was decided

Granted outline planning permission for a six-storey hotel building above ground level with a basement, providing hotel accommodation and ancillary dining facilities, with all matters reserved except scale. Report P27, 2.1

The development is capped at a maximum of 91 hotel rooms, with stays not to exceed 90 days within any 12-month period, to remain within the scope of the assessment. Report 4.4, P15

Permission is subject to a legal agreement covering transport and highway works, environmental measures, local employment and training, and monitoring fees, with delegated authority given to the Director of Planning. Report P2, P3, P4, P5, P6, 2.2

Why

The proposed hotel use is supported by policy promoting visitor accommodation in town centres with good public transport access, and the site has an excellent PTAL rating of 6a. Report 3.1, 8.3, 8.4, 8.5

The scale of the development is the same as previously approved under outline planning permission reference 24/03390/OUT and remains acceptable in visual impact, setting of the locally listed building, and neighbouring amenity. Report 3.3, P74

The scheme passes the sequential and exception tests for flooding, with mitigation including no sleeping accommodation at ground or basement level and a raised basement threshold. Report 3.4, P15

What happens next

If the legal agreement is not completed within four months of the committee meeting, the Corporate Director has delegated authority to refuse planning permission. Report 2.4, P19

Reserved matters for access, appearance, landscaping, and layout must be submitted within three years, with two years to implement from reserved matters approval. Report P10

Pre-commencement conditions require submission of documents including a Construction Logistics Plan, contamination report, Fire Strategy, Air Quality Assessment, SuDS strategy, and Energy Assessment before development can begin. Report P11, P12

The money

  • £100 per 500sq.m Air quality contribution Report P4

Options considered

  • Chosen: Grant outline permission for six-storey hotel. Policy-compliant hotel use with acceptable scale and flood mitigation; site has excellent transport access and use is supported in local centres. Report 3.1, 3.3, 3.4
  • Rejected: Refuse based on objections preferring residential use. Each application must be considered on its own merits; the hotel use complies with policy and the site is not allocated for residential use. Report 3.2, P129, P131
  • Rejected: Refuse on grounds of height, bulk, and over-densification. The building is the same height and scale above ground as previously approved under 24/03390/OUT; appearance is a reserved matter. Report 3.3, P129, P131

Implications

  • Legal: Legal agreement (Section 106) must be completed to secure planning obligations including highways, environment, employment, and training contributions before permission is issued. Report P2, P3, P4, P5, P6
  • Financial: Air quality contribution of £100 per 500sq.m is required, along with a carbon offset financial contribution and a Local Employment and Training Strategy contribution for both construction and operation phases. Report P4, P5
  • Equalities: Two objections were received from individual neighbours, and Councillor Danielle Denton objected on grounds of height, scale, and flood risk; all were considered but did not warrant refusal. Report P127, 6.3, P131, P132
  • Risk: The site is in Flood Zone 2 and 3(a) with high surface water flood risk; mitigation includes no sleeping accommodation at ground or basement level and a 600mm raised basement threshold. Report 3.4, 4.9, P15
  • Climate: Conditions require a finalised energy statement, Be Seen monitoring, and biodiversity enhancement measures with a minimum Urban Greening Factor of 0.3. Report P4, P11

Who and where

  • Residents and businesses in South Croydon ward Report 4.7, 4.8
  • The locally listed former Swan and Sugar Loaf Public House and its occupants Report 4.8, P100, P101
  • Neighbouring restaurant at 3 Brighton Road Report 4.8
  • Future hotel guests and visitors Report 4.4
  • Transport for London, given the site's excellent public transport connectivity Report 4.9, 5.2, P112

Timeline

  • 2026-09-03: Planning Committee meeting date and decision to grant
  • Within 4 months of committee meeting: Deadline for legal agreement completion, otherwise delegated authority to refuse Report 2.4, P19
  • Within 3 years: Reserved matters (access, appearance, landscaping, layout) to be submitted Report P10
  • 2 years from reserved matters approval: Deadline to implement the development Report P10

Plain English for the jargon

  • Outline planning permission: Permission that establishes the principle of a development, with detailed matters (such as access, appearance, landscaping, and layout) reserved for later approval.
  • PTAL: Public Transport Accessibility Level, a score from 0 to 6b measuring how well connected a location is to public transport; 6a is excellent.
  • Section 106 legal agreement: A legal agreement between a developer and the council used to secure planning obligations such as financial contributions or works.
  • Sequential and exception tests: Planning tests used to assess whether a development in a flood risk area is acceptable, requiring demonstration that there are no lower-risk sites and that the development will be safe.
  • SuDS: Sustainable Drainage Systems, designed to manage surface water runoff and reduce flood risk.
  • Urban Greening Factor: A score measuring the amount of green infrastructure in a development; a minimum of 0.3 is required for this site.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item95/26

Resolved

RESOLVED to GRANT the application for 26/00079/OUT 1A Brighton Road, South Croydon, CR2 6EA
Word for word from the decision Croydon published for this meeting. Source: democracy.croydon.gov.uk

Follow this further

Built from Croydon's papers

What the report saysPro

Report to Planning Committee

Recommendation

2.1That the Planning Committee resolve to GRANT planning permission subject to:

A. The prior completion of the legal agreement to secure the following planning obligations:

Transport Highway works (through S.278 highways agreement) to potentially include (but not limited to): a. Removal of redundant crossovers (dropped kerbs) and reinstatement as footway if required, b. Construction of vehicular crossover to suit new site layout if required, c. Resurfacing the footway and carriageway to the extents of the Planning Application Site, d. Remedying any damage to the carriageway resulting from construction activity. Permit free development (commercial) OFFICIAL

Environmental Finalised energy statement and secure any carbon offset financial contribution Be Seen monitoring clauses Air quality contribution (£100 per 500sq.m)

Employment and Training Local Employment and Training Strategy (LETS) LETS contribution – construction phase and operation phase (to be calculated at reserved matters stage)

Other Monitoring fees Any other planning obligation(s) considered necessary by the Director of Planning and Sustainable Regeneration or Corporate Director of Sustainable Communities, Regeneration & Economic Recovery.

2.2That the Director of Planning and Sustainable Regeneration has delegated authority to negotiate the legal agreement indicated above.

2.3That the Director of Planning and Sustainable Regeneration has delegated authority to issue the planning permission and impose conditions and informatives to secure the following matters:

Conditions

Standard 1. In accordance with the approved plans. 2. Reserved Matters to be submitted within 3 years (access, appearance, landscaping and layout). 3. 2 years to implement from reserved matters approval.

Pre-commencement 4. Submission of Construction Logistics Plan. 5. Submission of contamination exploration and mitigation. 6. Submission of Fire Strategy. 7. Submission of Air Quality Assessment. 8. Finalised SuDS strategy. 9. Foul Water Capacity 10. Surface Water Capacity 11. Details of plant/solar panels etc and noise limitations. 12. Delivery and Service Management Plan. 13. Secure landscaping proposals including replacement trees, with additional details secured via condition including detailed design. Must meet minimum Urban Greening Factor of 0.3. 14. Biodiversity enhancement measures. 15. Secure energy assessment. OFFICIAL

Pre-commencement above ground 16. Submission of Public Art. 17. Secure By Design. 18. Cycle store details and implementation. 19. Waste storage location/elevation/detail and management/collection plan. 20. Co-ordination strategy with surrounding uses/properties. 21. Basement Impact Assessment

Pre-commencement of relevant part of works 22. Piling methodology.

Prior to Occupation 23. Details of external lighting. 24. Details of privacy measures and implementation. 25. Details on dining and café facilities and other ancillary facilities and operation thereof.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
26/00079/OUT- 1A Brighton Road, South Croydon, CR2 6EAPlan 134 KB Download
PDF
Item 6.2 1A Brighton Road, South Croydon /26Report 1.2 MB DownloadRead as text
PDF
Planning Com Addendum 030926 /26Addendum 99 KB Download

At this meeting

Whole meeting

Who was there

10 of 11 attended
IP
Councillor Ian ParkerChair, present
SF
Councillor Sean FitzsimonsDeputy-Chair, apologies, sent representative
HR
Councillor Helen RedfernVice-Chair, present
RD
Councillor Rowenna DavisCommittee Member, apologies, sent representative
MD
Councillor Matthew DormerCommittee Member, present
JP
Councillor Jose Piedade FernandesCommittee Member, present
MJ
Councillor Mark JohnsonCommittee Member, present
AS
Councillor Appu SrinivasanCommittee Member, present
MF
Councillor Melanie FeltenReserve, present as substitute
SK
Councillor Stuart KingReserve, present as substitute
YB
Yasmin BasithSecretary, expected

On this subject at Croydon

Search all
  1. 26/00079/OUT- 1A Brighton Road, South Croydon, CR2 6EAThis decision
  2. 24/02551/OUT - 1A Brighton Road, South Croydon, CR2 6EADecided
  3. LICENSING ACT 2003 - Application for a review of the premises licence at 3 Brighton Road, South Croydon, CR2 6EANoted
  4. 20/02020/FUL 443A Brighton Road, South Croydon, CR2 6EUDecided

More from Croydon Planning Committee

All decisions
MeetingDecisionOutcome
3 Sep 2026 Minutes of Previous MeetingRESOLVED that the minutes of the meeting held on Thursday 20 August 2026 be signed as a correct record. Decided Open
3 Sep 2026 Weekly Planning DecisionsRESOLVED to note the weekly Planning decisions as contained within the report. Noted Open
20 Aug 2026 Minutes of Previous MeetingRESOLVED that the minutes of the meeting held on Thursday 23 July 2026 be signed as a correct record. Decided Open
20 Aug 2026 6.1- 25/04082/FUL- Selsdon Goods Yard, Selsdon Road, South Croydon, CR2 0EARESOLVED to GRANT the application for 25/04082/FUL- Selsdon Goods Yard, Selsdon Road, South Croydon, CR2 0EA, subject... Decided Open
20 Aug 2026 6.2- 26/01490/FUL- 233 Hayes Lane, Kenley, CR8 5HNRESOLVED to GRANT the application for 26/01490/FUL 233 Hayes Lane, Kenley, CR8 5HN. Decided Open