Executive, Tuesday 7 April 2026 at 10.30am

2025/26 Budget Monitoring at Quarter 3 (April to December)

Approved Executive 7 papers

AI summaryCumberland Council's Executive noted the quarter 3 revenue position, approved £2.484m of in principle contributions to earmarked reserves and recommended moving £23.553m of capital underspends into 2026/27. [D] The net draft adverse variance was £6.506m against a £332.578m approved budget. [D]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedRevenue noted, contributions approved, drawdown noted, reprofiling recommended [D]
Money£6.506m adverse variance [D]2.0% of net budget against £332.578m approved budget [D]
What happens nextCouncil to consider reprofiling [D]£23.553m proposed move from 2025/26 to 2026/27 [D]
Who it affectsBudget and capital programme [D]Revenue position, reserves and capital spending [D]

What was decided

The Executive noted the revenue position and the revenue budget adjustments between Directorates and Corporate Budgets set out in Appendix B. Report P5

The Executive approved in principle requests for £2.484m of contributions to earmarked reserves, noted the in principle drawdown, and noted the reduced in year forecast for Transformation Investment financed by Exceptional Financial Support. Report P5

The Executive noted quarter 3 adjustments to the 2025/26 capital programme totalling £0.223m and recommended that Council move £23.553m of capital programme funding from 2025/26 to 2026/27. Report P7

Why

The purpose was to ensure members were fully briefed on financial performance against budget for April to December 2025 and the forecast to 31 March 2026. Report 10.1

Sound financial management is essential to successful delivery of the Council's financial plans, value for money, financial sustainability, and stewardship and safeguarding of public money. Report P8

What happens next

The Executive recommended that Council consider moving £23.553m of capital programme funding from 2025/26 to 2026/27. Report P7

The money

  • £6.506m Net draft adverse variance, 2.0% of net budget
  • £23.553m Capital budget underspends proposed for reprofiling from 2025/26 to 2026/27 Report P7
  • £2.484m Requests for contributions to earmarked reserves approved in principle Report P5
  • £0.223m Total adjustments to the 2025/26 capital programme in quarter 3 Report P7
  • £0.512m Adverse movement from the Q2 variance
  • £5.994m Adverse variance reported at Q2
  • £332.578m Approved budget
  • 2.0% Share of net budget represented by the £6.506m adverse variance

Options considered

  • Rejected: Alternative options. Not applicable to this decision Report 9.1

Implications

  • Financial: Financial issues and implications are included in the main body of the report. Report P13
  • Risk: The £23.553m reprofiling was due to delays in the 25/26 capital programme.
  • Legal: There are no legal or governance issues arising from this decision. Report P12
  • Other: Consultation and engagement were not applicable to this decision. Report P9
  • Other: There are no information governance issues arising from this decision. Report P14
  • Other: There are no Property Services issues arising from this decision. Report P15
  • Other: There are no Procurement issues arising from this decision. Report P16

Who and where

  • Cumberland Council
  • Directorates and Corporate Budgets Report P5
  • Transformation Investment Report P5
  • The 2025/26 capital programme Report P7

Timeline

  • April to December 2025: The reporting period for financial performance against budget Report 10.1
  • Q2: The earlier adverse variance was reported as £5.994m, followed by an adverse movement of £0.512m
  • quarter 3: Adjustments to the 2025/26 capital programme totalling £0.223m were noted Report P7
  • 2025/26: The source year for the proposed £23.553m capital programme reprofiling Report P7
  • 10 March 2026: The Business and Resources Overview and Scrutiny Committee scrutinised the report
  • 31 March 2026: The date for the reported forecast position Report 10.1
  • 2026/27: The proposed destination for £23.553m of reprofiled capital programme funding Report P7

Plain English for the jargon

  • Earmarked reserves: Reserves with £2.484m of in principle contribution requests and a noted drawdown in this decision. [P5]
  • Transformation Investment: The item with a reduced in year forecast financed by Exceptional Financial Support. [P5]
  • Exceptional Financial Support: The financing source for the reduced Transformation Investment forecast. [P5]
  • Reprofiling: Moving £23.553m of capital budget underspends from 2025/26 to 2026/27. [D]
  • Net draft adverse variance: £6.506m against the approved budget of £332.578m. [D]
  • Q3: Quarter 3, the April to December 2025 reporting period. [D]
  • Q2: The earlier budget monitoring stage, when an adverse variance of £5.994m was reported. [D]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemEX.105/26

Resolved

Decision) Portfolio: Financial Planning and Assets Relevant Scrutiny: Business and Resources Overview and Scrutiny Committee Subject : The Financial Planning and Assets Portfolio Holder presented the Council’s financial performance against budget for Quarter 3 (April to December 2025), along with the forecast position to 31 March 2026. The Financial Planning and Assets Portfolio Holder reported a net draft adverse variance of £6.506m (2.0% of net budget) against the approved budget of £332.578m. This was an adverse movement of £0.512m from the £5.994m adverse variance reported at Q2. The Portfolio Holder also drew attention to the reprofiling of the £23.553m capital budget underspends from 2025/26 to 2026/27 due to delays in the 25/26 capital programme. The Business and Resources Overview and Scrutiny Committee scrutinised the report on 10 March 2026, the minute excerpt had been circulated with the report. The Financial Planning and Assets Portfolio Holder moved the recommendations and the Leader seconded them. Alternative Options: None DECISION In relation to Revenue budget monitoring - The Executive • Noted the revenue position contained within the report • Noted the revenue budget adjustments, between Directorates and Corporate Budgets as set out in the report Appendix B • Approved the in-principle requests for contributions to earmarked reserves of £2.484m as set out in section 3 and Appendix D of the report • Noted the in-principle drawdown from earmarked reserves as set out in section 3 of the report • Noted the reduced in-year forecast for Transformation Investment, financed by Exceptional Financial Support. In relation to Capital monitoring at Q3 – The Executive • Noted the adjustments to the 2025-26 capital programme in quarter 3 totalling £0.223m • Recommended to Council on the proposed reprofiling of the capital programme of £23.553m from 2025-26 to 2026-27
Word for word from the decision Cumberland published for this meeting. Source: cumberland.moderngov.co.uk

Follow this further

Built from Cumberland's papers

What the report saysPro

Report to Executive, 32 pages

Report to Executive

Meeting Date – 07 April 2026 Key Decision – No Public/Private – Public

Portfolio – Financial Planning Directorate – Corporate & Transformation Services Report Author – Chief Finance Officer (Section 151)

Title – 2025/26 Budget Monitoring at Quarter 3 (April to December)

Brief Summary: This report informs Executive of the Council’s financial performance against budget for Quarter 3 (Q3), the period April to December 2025, along with the forecast position to 31 March 2026.

Recommendations: In relation to Revenue budget monitoring, Executive are asked to:

• Note the revenue position contained within this report • Note the revenue budget adjustments, between Directorates and Corporate Budgets as set out in the report Appendix B • Approve the in-principle requests for contributions to earmarked reserves of £2.484m as set out in section 3 and Appendix D • Note the in-principle drawdown from earmarked reserves as set out in section 3 • Note the reduced in-year forecast for Transformation Investment, financed by Exceptional Financial Support.

In relation to Capital monitoring at Q3, Executive are asked to:

• Note the adjustments to the 2025-26 capital programme in quarter 3 totalling £0.223m • Make recommendation to Council on the proposed reprofiling of the capital programme of £23.553m from 2025-26 to 2026-27

Tracking Executive: 7 April 2026 Scrutiny: Council: 1. Background 1.1. The Council’s Financial Regulations require the Section 151 Officer to report to Executive on a quarterly basis the latest financial position against budget.

1.2This report outlines for the Council’s revenue budget:

• actual (net) expenditure during the period April to December 2025 • the projected net expenditure (full year forecast/forecast outturn) against budget for the year to 31 March 2026 • reasons for significant variances between the full year forecast and the approved estimates (budget) for 2025-26.

1.3The report also provides an update on quarterly reporting arrangements relating the Council’s Capital programme and treasury management activities

2. Key Message Revenue Budget 2.1. The Quarter 3 (Q3) projected outturn is showing a potential adverse outturn of £6.506m. This represents a 2.0% adverse position against the Councils current £332.578m net budget requirement.

2.2If this position remains un-changed it would require an un-budgeted contribution from general fund balances of £6.506m. Following the closure of the 2024/25 Accounts, the adverse variance forecast at Q3 does not reduce the General Fund balance below the level for Adequacy of Reserves (£25m).

2.3The forecast variance represents an adverse movement of £0.512m from the Q2 position of a £5.994m adverse variance and un-budgeted contribution from the General Fund.

Capital Budget 2.4. The projected capital outturn position for 2025-26 and associated financing for 2025-26 shows:

• a projected outturn position of £184.939m • an underspend compared to budget of (£24.197m) • expected budget carry forward requests (re-profiling adjustments) of £23.553m • an overall favourable variance (net of carry forward requests) of (£0.644m) Treasury Management 2.5. Treasury management activities during the period were carried out in accordance with the Council’s treasury management and investment strategies and within the limits established by the approved Council’s Treasury Management Strategy Statement and Investment Strategy for 2025-26.

2.6No new borrowing was undertaken.

3. Revenue Outturn Position

Summary of Projected Revenue Outturn Position

3.1Table 1 shows the Council's overall projected 2025-26 revenue outturn position at the end of Q3:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2025/26 Budget Monitoring at Quarter 3 (April to December)Report 32 pages DownloadRead as text
PDF
Capital Report Q3 2025-26 /26Appendix A 133 KB Copy on its way
PDF
Capital Budget Monitoring 2025-26 Q3 /26Appendix A1 355 KB Copy on its way
PDF
Budget Amendments to Q3 /26Appendix B 72 KB Copy on its way
PDF
Treasury Management Activity Q3 2025-26 /26Appendix C 469 KB Copy on its way
PDF
Requests for Earmarked Reserves at Q3 /26Appendix D 3 pages Download
PDF
Minute Excerpt: Budget monitoring Quarter 3 2025.26 report /26Report 3 pages Download

At this meeting

Whole meeting

On this subject at Cumberland

Search all
  1. 2025/26 Budget Monitoring at Quarter 3 (April to December)This decision
  2. Revenue and Capital Budget Monitoring Report Quarter 3Decided

More from Cumberland Executive

All decisions
MeetingDecisionOutcome
7 Apr 2026 Exclusion of Press and PublicRESOLVED – It was agreed that items in Part A be dealt with in the public, there were no items in private to be dealt... Agreed Open
7 Apr 2026 Minutes of Previous MeetingRESOLVED – That the minutes of the meeting of the Executive held on 17 February 2026 be approved and signed by the Le... Approved Open
7 Apr 2026 Individual Portfolio Holder DecisionsDECISION: That the decisions taken by Individual Portfolio Holders since 17 February 2026 be noted. Reasons for decis... Noted Open
7 Apr 2026 Delegation of authority to procure mainstream and SEND home to school transport routes via the Passenger Transport Services Dynamic Purchasing System (DPS) from its establishment to its expiryDECISION That the Executive delegated authority to the Senior Manager (or equivalent post identified by the Assistant... Decided Open
7 Apr 2026 Corporate Performance Report - Quarter 3 2025/26DECISION That the Executive noted the overall performance relating to delivery of the Cumberland Council Plan priorit... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies