Budget Monitoring and Performance Report Quarter 1

Approved Executive 1 paper

Cabinet approved this item on Tuesday 15 September 2015. Below is the council's own wording, with the papers it was decided on.

ItemCA/34/15

Resolved

Decision 1. That the budget monitoring position for each of the detailed accounts be approved; and, That Council be recommended to approve: the supplementary budgets set out below. Details for these supplementary budgets are set out in the body of the Cabinet report and have a net nil impact on the General Fund Working Balance: · Increase Revenues and Benefits Agency Budget by £70k · Increase Other Government Grants Budget by £70k · Decrease the Performance and Projects Employees Budget by £10k · Decrease use of the Technology Reserve by £10k · Increase Office Accommodation Budget by £52,500 · Increase use of The Forum Reserve by £52,500 · Decrease the LDF Consultancy budget by £50k · Decrease use of the LDF reserve by £50k Reason for Decision To provide details of the projected outturn for 2015/16 as at Quarter 1 for the: • General Fund • Housing Revenue Account • Capital Programme Implications Financial Financial and Value for Money implications are included within the body of the report. Risk Implications Risk implications are included within the body of the report Equalities Implications None identified. Health And Safety Implications None identified. Corporate Objectives Dacorum Delivers Advice The Portfolio Holder for Finance and Resources was disappointed about the performance for quarter 1. He noted that there had been an underspend in previous years. He hoped that the overspend forecast would focus managers minds and help them meet targets. The Assistant Director for Finance and Resources recognised that there were significant variances but the intention is to produce clear action plans to improve this. He highlighted that there was slippage on the capital spend for the waste fleet replacement, however there was no good reason against procuring these vehicles at present. The Portfolio Holder for Environmental, Sustainability & Regulatory Services referred to the overspend in Waste Services. She explained that this was work in progress which should improve in the near future; a garden refuse round had already been deleted due to a reorganisation. It was confirmed that the third party overspend for facilities, set out in paragraph 3.3, page 5 of the agenda did relate to the contract with Serco. The Portfolio Holder for Environmental, Sustainability & Regulatory Services asked if it was, in part, because Serco would make a repair and then the council would have to pay them the costs. She asked if any checks were made on the charges, to ensure they were reasonable. The Corporate Director for Finance and Operations confirmed the charges were checked and scrutinised. The Portfolio Holder for Environmental, Sustainability & Regulatory Services referred to paragraph 7.3 on page 10 of the agenda and asked if the council budgeted for s106 agreements for other more recent new builds.,. The Corporate Director Housing and Regeneration confirmed this was the case, but he was unsure as to why it had not been included. He added that the council would take account of predicted s106 agreements in the budget. The Portfolio Holder for Housing asked if the council had taken this planning permission over from another body. The Corporate ... view the full minutes text for item CA/34/15
Word for word from the decision Dacorum published for this meeting. Source: democracy.dacorum.gov.uk

Follow this further

Built from Dacorum's papers

What the report saysPro

Report to Cabinet

Agenda Item 8 Page 1 of 10

AGENDA ITEM: 8 SUMMARY

Report for: Cabinet

Date of meeting: 15 September 2015

PART: 1

If Part II, reason:

Title of report: Budget Monitoring Quarter 1 2015/16

Contact: Cllr Graeme Elliot, Portfolio Holder for Finance and Resources

David Skinner, Assistant Director (Finance & Resources)

Richard Baker, Group Manager (Financial Services)

Purpose of report: To provide details of the projected outturn for 2015/16 as at Quarter 1 for the:

• General Fund • Housing Revenue Account • Capital Programme

Recommendations It is recommended that Cabinet:

1. Consider the budget monitoring position for each of the above accounts; and,

2. Recommend to Council the supplementary budgets set out below. Details for these supplementary budgets are set out in the body of the report and have a net nil impact on the General Fund Working Balance:

Increase Revenues and Benefits Agency Budget by £70k

Increase Other Government Grants Budget by £70k

Decrease the Performance and Projects Employees Budget by £10k

Agenda Item 8 Page 1 of 10 Agenda Item 8 Page 2 of 10

Decrease use of the Technology Reserve by £10k

Increase Office Accommodation Budget by £52,500

Increase use of The Forum Reserve by £52,500

Decrease the LDF Consultancy budget by £50k

Decrease use of the LDF reserve by £50k

Corporate Dacorum Delivers objectives:

Implications: Financial and Value for Money implications are included within the body of the report.

Risk Implications Risk implications are included within the body of the report.

Equalities There are no equality implications. Implications

Health And Safety There are no health and safety implications. Implications

Monitoring Deputy Monitoring Officer Officer/S.151 Officer Comments No further comments to add.

Deputy S.151 Officer

This is a Section 151 Officer report.

Consultees: Budget Managers

Glossary of GF – General Fund acronyms and any HRA – Housing Revenue Account other abbreviations used in this report:

Agenda Item 8 Page 2 of 10 Agenda Item 8 Page 3 of 10

1. Introduction

1.1The purpose of this report is to outline the Council’s forecast outturn for 2015/16 as at 30 June 2015. The report covers the following budgets:

• General Fund • Housing Revenue Account (HRA) • Capital Programme

2. General Fund Revenue Account

2.1The General Fund revenue account records the income and expenditure associated with all Council functions except management of the Council’s own housing stock, which is accounted for within the Housing Revenue Account (HRA) (see Section 6).

2.2Appendix A provides an overview of the General Fund provisional outturn position, separating expenditure into controllable and non-controllable categories in order to focus scrutiny on those areas that officers are able to influence, i.e. the controllable.

2.3The majority of non-controllable costs result from year-end accounting adjustments, e.g. depreciation charges. These are required to show the true value of resources used to provide the Council’s services, but do not result in a cash charge to taxpayers.

2.4The table below provides an overview by Scrutiny area of the current forecast outturn for controllable budgets within the General Fund.

Controllable Projected Variance Budget Outturn £000 £000 £000 % Finance & Resources 10,623 11,102 479 4.5% Strategic Planning & 5,810 6,089 279 4.8% Environment Housing & Community 1,101 1,128 27 0.5% Total 17,534 18,319 785 4.5%

2.5The following sections provide an analysis of the projected outturn and major budget variances shown by Scrutiny area.

Agenda Item 8 Page 3 of 10 Agenda Item 8 Page 4 of 10

3. Finance and Resources

Controllable Projected Finance & Budget Outturn Variance Resources £000 £000 £000 % Employees 10,188 10,461 273 2.7% Premises 1,517 1,564 47 3.1% Transport 37 37 0 0.0% Supplies & Services 4,570 4,613 42 0.9% Third-Parties 1,411 1,464 54 3.8% Income (7,101) (7,037) 64 -0.9% 10,623 11,102 479 4.5%

3.1Employees - £273k over budget (2.7%)

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Budget Monitoring and Performance Report Quarter 1Report 135 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Dacorum

Search all
  1. Budget Monitoring and Performance Report Quarter 1This decision
  2. Budget Monitoring Q3 reportAgreed
  3. Budget monitoring Q2Approved
  4. Budget Monitoring Q3Approved
  5. Quarter 2 Budget Monitoring ReportApproved
  6. Q1 Budget Monitoring ReportApproved

More from Dacorum Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 MinutesCabinet Agreed the of the previous meeting. Agreed Open
22 Sep 2026 Apologies for absenceThere were no apologies for absence. Decided Open
22 Sep 2026 Declarations of InterestThere were no declarations of Interest Decided Open
22 Sep 2026 Public ParticipationThere was no public participation. Decided Open
22 Sep 2026 Referrals to CabinetThere were no referrals to Cabinet. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies