Resolved

The procurement of specialist technical advice to progress work on the creation of a Development Company be approved; The primary objectives of the Development Company, as detailed in paragraph 7 of the Cabinet report be approved and, The development sites identified in paragraph 12 to form the initial pipeline for the Development Company be approved, Resolved to Recommend: 4. A draw down of £100k from the Invest to Save reserve, in order to fund the procurement of advice associated with the creation of a Development Company and further associated costs.
Word for word from the decision Dacorum published for this meeting. Source: democracy.dacorum.gov.uk

Follow this further

Built from Dacorum's papers

What the report saysPro

Report to Cabinet

Report for: Cabinet

Date of meeting: 24 May 2016

Part: 1

If Part II, reason:

Proposals for a Development Company Title of report: Cllr Graeme Elliot, Portfolio Holder for Finance & Resources Contact: James Deane, Corporate Director (Finance & Operations) Purpose of report: To gain Cabinet approval for the overarching principles of a Council-owned Development Company, ahead of procuring specialist, technical advice.

Recommendations It is recommended that Cabinet approve:

1. The procurement of specialist technical advice to progress work on the creation of a Development Company;

2. The primary objectives of the Development Company, as detailed in paragraph 7 of this report; and,

3. The development sites identified in paragraph 12 to form the initial pipeline for the Development Company,

It is also recommended that Cabinet recommend to Council:

4. A draw down of £100k from the Invest to Save reserve, in order to fund the procurement of advice associated with the creation of a Development Company. This project aligns with all of the Council’s corporate Corporate objectives, as approved by Council in February 2016. Objectives: Implications: Financial

The financial implications are included within the body of the report.

‘Value For Money Implications’ Value for Money

The procurement exercise will be governed by the Council’s Procurement Standing Orders, deigned to ensure fair competition and maximise value for money.

There are limited risks associated with the recommended Risk Implications procurement at this stage of the project. The risks inherent with the actual creation of a company will be reported back to Cabinet to consider later in the year, before the next steps are taken. Health And Safety None Implications Monitoring Officer: Monitoring Officer/S.151 The Council has the power to establish a Development Officer Comments Company pursuant to provisions contained in the Local Government Act 1972, Local Government Act 2003 and the Localism Act 2011.

As highlighted in the report, detailed legal advice will be obtained in relation to the governance arrangements which will operate between the Council and the Development Company, the applicability of ‘State Aid’ rules (EU rules in place to prevent members states distorting cross boundary competition), and the Council’s requirement to achieve ‘best consideration’ for any disposal/transfer of land to the Development Company.

Comprehensive advice on all of the above issues will be provided in future reports to Cabinet in due course.

S.151 Officer

This is a Section 151 Officer report. Consultees: Chief Officer Group

Cabinet

Background None papers: Executive Summary

1. In response to the continued financial pressures faced by the public sector, a number of Local Authorities have created, or are in the process of creating, Development Companies with a view to optimising the return on council-owned assets, in particular land, housing and commercial assets.

2. Whilst the principles of a Development Company are straightforward, the legal and financial considerations are complex and must be addressed from the outset in order to ensure that the Council creates the type of company most suited to delivering its objectives. The fundamental purpose of this report is to take the first steps towards addressing these considerations.

3. Based on consultation with other Local Authorities exploring the concept of a Development Company, the recommended process to progress from concept stage through to formation, together with indicative timeframes, is shown below. (More detail on each point is provided within the body of the report.)

a. Establish the Council’s development objectives (Cabinet May 2016) b. Identify potential development land (Cabinet May 2016) c. Issue tender for specialist legal, financial and property advice (end of July) d. Provision of specialist advice (end of July – end of October) e. Seek Cabinet and Council approval (November – January 2017)

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Proposals for a Development CompanyReport 79 KB DownloadRead as text

At this meeting

Whole meeting

More from Dacorum Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 MinutesCabinet Agreed the of the previous meeting. Agreed Open
22 Sep 2026 Apologies for absenceThere were no apologies for absence. Decided Open
22 Sep 2026 Declarations of InterestThere were no declarations of Interest Decided Open
22 Sep 2026 Public ParticipationThere was no public participation. Decided Open
22 Sep 2026 Referrals to CabinetThere were no referrals to Cabinet. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies