CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Dacorum Borough Council
Cabinet, Tuesday 26 July 2016 at 7.30pm

Berkhamsted Multi Storey Car Park

Approved Executive 1 paper

Cabinet approved this item on Tuesday 26 July 2016. Below is the council's own wording, with the papers it was decided on.

ItemCA/78/15

Resolved

1) Delegate authority to the Assistant Director (Finance & Resources) to proceed with the project and formally tender the building contract subject to obtaining conditional approval of planning permission; 2) Subject to contract bids falling within the budget previously approved, and detailed within the Part II element of this report, delegate authority to the Corporate Director (Finance and Operations) in consultation with the Portfolio Holder for Finance and Resources to award the building contract.
Word for word from the decision Dacorum published for this meeting. Source: democracy.dacorum.gov.uk

Follow this further

Built from Dacorum's papers

What the report saysPro

Report to Cabinet

Summary

Report for: Cabinet

Date of meeting: 26 July 2016

Part: 1

If Part II, reason:

DEVELOPMENT OF MULTI-STOREY CAR PARK AT Title of report: LOWER KINGS ROAD, BERKHAMSTED Cllr Graeme Elliot, Portfolio Holder for Finance and Resources Contact: James Deane – Corporate Director (Finance & Operations) David Skinner - Assistant Director ( Finance & Resources)

Nicholas Brown -Group Manager - (Commercial Assets and Property Development) Purpose of report: To seek authorisation to proceed and agree delegated authority for tendering and awarding the building contract and other project management issues for the multi-story car park (MSCP) subject to the receipt of Planning Permission.

Recommendations Cabinet is recommended to:-

1) Delegate authority to the Assistant Director (Finance & Resources) to proceed with the project and formally tender the building contract subject to obtaining conditional approval of planning permission;

2) Subject to contract bids falling within the budget previously approved, and detailed within the Part II element of this report, delegate authority to the Corporate Director (Finance and Operations) in consultation with the Portfolio Holder for Finance and Resources to award the building contract.

Building strong and vibrant communities Corporate Objectives: Ensuring economic growth and prosperity

Delivering an efficient and modern

Agenda item Page 1 of 5 Agenda Item Page 2 of 5

council

Financial Financial Implications: Detailed specific financial costings are not available until bids are received but market assessments and soft market testing indicate that the original baseline figures supplied in the January 2014 report are still valid. The original project budget ‘Value For Money as set out in Table2 of the Part II report is still correct. The Implications’ budgetary implications of this report are detailed further in the Part II report.

Value for Money The project will produce a return on investment for the Council consistent with the parameters agreed by Cabinet in February 2014. Delivery of the scheme is subject to planning approval. The Risk Implications Council’s planning and transport consultants continue to work with Council planning officers and County Council Highways Officers in order to progress the application. Community Impact Assessment updated. Community Impact Assessment Health and Safety issues will be considered as part of the Health And Safety project risk assessment for delivering the project. Implications

Monitoring Officer Monitoring Officer/S.151 Tendering for the build contract will require a formal regulated Officer Comments procurement process and officers will need to ensure that an appropriate construction contract is agreed with the preferred contractor in due course.

S.151 Officer

This is a Section 151 Officer report. Consultees: Ben Hosier – Group Manager (Commissioning, Procurement & Compliance) Portfolio Holder Decision Sheet PH/015/13 for the Appointment Background of a consultant to progress the development of a multi-storey papers: car park in Berkhamsted. (April 2013) Cabinet Report 11 January 2014 - Report on the Feasibility of Developing a Multi Storey Car Park on Lower Kings Road Berkhamsted. MSCP – multi storey car park Glossary of acronyms and any WYG – White Young Green (DBC’s appointed consultant) other abbreviations

Agenda item Page 2 of 5 Agenda Item Page 3 of 5

used in this report: HCC – Hertfordshire County Council

DBC – Dacorum Borough Council

Background

1.1In August 2012, an initial report was produced to study the feasibility of a Multi Storey Car Park in Berkhamsted by Savell, Bird and Axon. This was followed in April 2013, by a commercial viability assessment undertaken by White Young Green.

1.2The WYG report constituted the first phase of a 3-phase delivery approach as approved by Portfolio Holder Decision in April 2013. The approved phased approach is as follows:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Berkhamsted Multi Storey Car ParkReport 93 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Dacorum

Search all
  1. Berkhamsted Multi Storey Car ParkThis decision
  2. 20/01235/MFA - ARTIFICIAL GAMES PITCH/ MULTI USE GAMES AREA WITH FENCING AND FLOODLIGHTING - Berkhamsted Hockey Club Tring Road Tring Hertfordshire HP23 5RFApproved
  3. 20/01657/FUL - INSTALLATION OF EXTERNAL LIGHTING TO THE SOUTH, EAST AND WEST FACADES OF THE MULTI-STOREY CAR PARK. INSTALLATION OF LIGHT POSTS WITHIN THE DDA PARKING AREA. Public Car Park, Lower Kings Road, BerkhamstedDecided
  4. Construction of the Multi-Storey Car Park (MSCP) Berkhamsted - Award of ContractApproved

More from Dacorum Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 MinutesCabinet Agreed the of the previous meeting. Agreed Open
22 Sep 2026 Apologies for absenceThere were no apologies for absence. Decided Open
22 Sep 2026 Declarations of InterestThere were no declarations of Interest Decided Open
22 Sep 2026 Public ParticipationThere was no public participation. Decided Open
22 Sep 2026 Referrals to CabinetThere were no referrals to Cabinet. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies