That the following grant funding payments for affordable housing developments in the Borough be approved: 1. £812,233 to Watford Community Housing Trust for a development known as Goldcroft garage site, Hemel Hempstead. 2. £1,417,000 to Thrive Homes for a site known as land off Two Waters Road, Hemel Hempstead. (Old Hewden Hire site) 3. £133,168 to Hastoe Housing Association for a development known as garage site adjacent to 28 & 30 West Dene, Gaddesden Row, Great Gaddesden. 4. Approve the purchase of the site known as Garages to the South of 71 – 81 Burns Drive, Hemel Hempstead for a sum of £495,000. Agree an additional expenditure of £100,000 for consultant fees to deliver the scheme on this site.
Word for word from the decision Dacorum published for this meeting.Source: democracy.dacorum.gov.uk
Use of right to buy one for one replacement funding Title of report: Margaret Griffiths, Portfolio Holder for Housing Contact: Elliott Brooks, Assistant Director for Housing
David Barrett, Group Manager for Housing Development To seek approval for the payment of “one for one” grant Purpose of report: funding to Housing Associations (Registered Providers) delivering affordable housing schemes in the Borough. To seek approval for the payment of “one for one” grant funding to Housing Associations (Registered Providers) delivering affordable housing schemes in the Borough.
In addition seek approval to purchase a site known as Garages to the South of 71 – 81 Burns Drive for the purposes of building Council homes and commit expenditure to developing the scheme to build out. Recommendations That Cabinet approves the following grant funding payments for affordable housing developments in the Borough: 1. £812,233 to Watford Community Housing Trust for a development known as Goldcroft garage site, Hemel Hempstead.
2. £1,417,000 to Thrive Homes for a site known as land off Two Waters Road, Hemel Hempstead. (Old Hewden Hire site)
3. £133,168 to Hastoe Housing Association for a development known as garage site adjacent to 28 & 30 West Dene, Gaddesden Row, Great Gaddesden.
4. Approve the purchase of the site known as Garages to the South of 71 – 81 Burns Drive, Hemel Hempstead for a sum of £495,000. Agree an additional expenditure of £100,000 for consultant fees to deliver the scheme on this site. Delivering Affordable Housing Corporate Objectives: Implications: Financial This approach to supporting other organisations developing affordable housing in the Borough will enable us to allocate the funding before the deadline to spend expires.
Value For Money Value for Money Implications “One for one” receipts paid to Housing Associations by way of a grant provides the means to increase the provision of affordable homes within the Borough at no cost to the Council and assist in avoiding the costs of homelessness by increasing supply.
If the Council is unable to spend its “one for one” receipts they Risk Implications must be returned to the Government. Should the Council retain receipts and then be unable to spend them within a three year period then interest becomes payable. The recommended model agreement passes this risk onto the receiving Housing Association. Community Impact Assessment reviewed/carried out Community Impact Assessment n/a Health And Safety Health & Safety is identified as a key risk of the Housing Implications Service and is reported to the Council’s Housing & Communities Overview & Scrutiny Committee on a quarterly basis. Deputy Monitoring Officer: Monitoring Officer/S.151 Under the scheme introduced in 2012 investment in new Officer Comments affordable housing can be made by the Council itself or through grant funding registered providers. This decision proposes funding developments by Watford Community Housing Trust, Thrive Homes and Hastoe Housing Association. Officers should ensure that each grant going forward is covered by the grant agreement (referred to in para 5 below) to ensure that the Council’s position is protected and enable it to meet audit requirements.
In relation to the purchase of the garage site, the final terms of the purchase contract must be reviewed by the Legal Team prior to completion.
Deputy S.151 Officer
The award of these grants can be met from the 1-4-1 receipts and will be reported on the pooling return to CLG which is audited on an annual basis by DBC’s appointed external auditors.
The grant agreement protects the Council from the payment of any interest penalties charged for late delivery of schemes.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.