AUDIT COMMITTEE: Work Programme 2018-19
DEADLINE TO DEADLINE MEETING MONITORING TO OFFICER ITEMS: WHO RESPONSIBLE DATE MEMBER SUPPORT
25/07/18 16/07/18 DBC Annual Accounts (Sign- Grant Thornton off)
External Audit Progress Grant Thornton Report
Internal Audit Progress Internal Audit (Mazars) Report
Completed Service Reports Internal Audit (Mazars) Housing Rents GDPR Counter Fraud
Strategic Risk Register DBC - Finance
12/09/18 03/9/18 External Audit Progress Grant Thornton Report
Internal Audit Progress Internal Audit (Mazars) Report
Completed Service Reports Internal Audit (Mazars) Commercial Asset Management
Strategic Risk Register DBC - Finance
21/11/18 12/11/18 External Audit Progress Grant Thornton Report
Internal Audit Progress Internal Audit (Mazars) Report Completed Service Reports Internal Audit (Mazars) ICT Council Tax NNDR Benefits
Strategic Risk Register DBC - Finance
06/02/19 28/1/19 External Audit Progress Grant Thornton Report
Internal Audit Progress Internal Audit (Mazars) Report
Completed Service Reports Internal Audit (Mazars) Core Financials Business Continuity Procurement Benefits/Savings Realisation
Strategic Risk Register DBC - Finance
27/03/19 18/03/19 External Audit Progress Grant Thornton Report
Internal Audit Progress Internal Audit (Mazars) Report
Progress Report Internal Audit (Mazars) Budgetary Control Governance and Risk Management Planning
Strategic Risk Register DBC - Finance
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Audit Committee Work ProgrammeReport | 56 KB | DownloadRead as text |
Follow Audit at Dacorum and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Sep 2025 | 2024-25 External Auditor's Year End Report to Audit CommitteeIt was agreed that the next Audit committee meeting to be brought forward to a suitable date at the end of November t... | Agreed | Open |
| 12 Sep 2018 | Audit Committee - September 18 - Work programmeThat the work programme for 2018/19 be agreed. | Agreed | Open |
| 25 Jul 2018 | Dacorum Borough Council Annual AccountsThat the Audit Committee a) notes the final financial outturn for 2017/18; b) Approves the additional movements on ea... | Approved | Open |
| 31 May 2018 | Provisional outturnThat Audit Committee note the carry forward of unspent reserve funded budgets from 2017/18 to 2018/19 (see Appendix D... | Noted | Open |
| 31 May 2018 | Audit Committee Annual Work PlanThat the work programme for 2018/19 be agreed. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.