Dacorum Borough Council
Cabinet, Tuesday 15 October 2019 at 7.30pm

New Build Update - Approval of the Contract for Gaddesden Row Site

Approved Executive 1 paper

Cabinet approved this item on Tuesday 15 October 2019. Below is the council's own wording, with the papers it was decided on.

ItemCA/98/19

Resolved

That the main contract to construct 3 x social rented units at Land Adjacent 35-36 West Dene, Gaddesden Row be awarded to Modplan Building & Refurbishment Contractors Ltd. 2. That the appropriation by the Housing Revenue Account of the General Fund land, set out in Part II of the report referenced MV2, for Council house new build purposes, be approved. 3. That an increase to the grant funding payment to Thrive Homes from £1,417,000 to £1,512,883 (Increase of £95,883) for a development known as Two Waters, Westside, London Road, Hemel Hempstead be approved
Word for word from the decision Dacorum published for this meeting. Source: democracy.dacorum.gov.uk

Follow this further

Built from Dacorum's papers

What the report saysPro

Report to Cabinet

Report for: Cabinet

Date of meeting: 15th October 2019

Part: I

If Part II, reason:

Title of report: Council New Build Programme Update Contact: Cllr Margaret Griffiths, Portfolio Holder for Housing

Mark Gaynor, Corporate Director Housing and Regeneration

Fiona Williamson, Assistant Director Housing

Nigel Howcutt, Assistant Director Finance and Operations

David Barrett, Housing Development Group Manager Purpose of report: To be read in conjunction with Part II.

To seek approval to award the main contract and appoint a Principle Contractor to construct 3 units at land adjacent 35- 36 West Dene, Gaddesden Row.

To seek approval for the appropriation of land at Coniston Road/Barnes Lane, Kings Langley.

To seek approval for the payment of “one for one” grant funding to Housing Associations (Registered Providers) delivering affordable housing schemes in the Borough. Recommendations: 1. That the main contract to construct 3 x social rented units at Land Adjacent 35-36 West Dene, Gaddesden Row be awarded to Modplan Building & Refurbishment Contractors Ltd. 2. That the appropriation by the Housing Revenue Account of the General Fund land, set out in Part II of the report referenced MV2, for Council house new build purposes, be approved. 3. That an increase to the grant funding payment to Thrive Homes from £1,417,000 to £1,512,883 (Increase of £95,883) for a development known as Two Waters, Westside, London Road, Hemel Hempstead be approved Corporate Objectives: Delivering Affordable Housing Implications: Financial

Land Adjacent 35-36 West Dene, Gaddesden Row

A detailed breakdown of the tendered costs for Land Adjacent 35-36 West Dene is included in the appendix. The scheme is subject to close financial monitoring and any future variations will be agreed formally through a change control process.

Land at Coniston Road, Kings Langley

The overall development budget is reviewed strategically as part of the annual review of the Housing Revenue Account (HRA) Business Plan. Each individual scheme following contract award is subject to close financial monitoring with any variances agreed formally through a change control process. A small part of Council owned land will be appropriated by the HRA which will result in a ‘receipt’ for the General Fund.

Two Waters, London Road

This approach to supporting other organisations developing affordable housing in the Borough will enable us to allocate ‘Value For Money the funding before the deadline to spend expires. Implications’ Value for Money

Land Adjacent 35-36 West Dene, Gaddesden Row

This has been achieved through a successful procurement programme involving an open tender process.

Land at Coniston Road/Barnes Lane, Kings Langley

Land purchases are in line with Red Book Valuation to ensure value for money

Two Waters, London Road

“One for one” receipts paid to Housing Associations by way of a grant provides the means to increase the provision of affordable homes within the Borough at no cost to the Council and assist in avoiding the costs of homelessness by increasing supply. Risk Implications Risk assessments are completed within the new build Project Initiation Document (PID) and reviewed and updated on Project Management Office, on a monthly basis.

A risk assessment is completed for each site by the Employers Agent and reviewed monthly from the award of the contract.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
New Build Update: Approval of the Contract for Gaddesden Row SiteReport 318 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Dacorum

Search all
  1. New Build Update - Approval of the Contract for Gaddesden Row SiteThis decision
  2. 24/01541/FUL New build 4 bedroom house with associated landscaping. Little Farm, Rucklers Lane, Kings Langley, HertfordshireApproved
  3. 24/01915/FUL Demolition of existing agricultural buildings, construction of 4 new dwellings, associated parking and landscaping. Tuffs Farm, Tower Hill, Chipperfield, Kings Langley, Hertfordshire, WD4 9LWRefused
  4. 23/02876/MPI- Demolition of the existing school building and construction of new replacement school building with MUGA, all weather pitch, landscaping and parking - Blessed Cuthbert Mayne Roman Catholic School, Clover Way, Hemel Hempstead, HertfordshireRefused
  5. 23/00023/FUL - Demolition of existing outbuildings and construction of a new bungalow - Lower Farm End Luton Road Markyate St Albans Hertfordshire AL3 8PZApproved
  6. 23/00813/FUL Demolition of existing buildings. Construction of 7 new houses with associated parking and landscaping Convent Of St Francis De Sales Preparatory School, Aylesbury Road, Tring, Hertfordshire, HP23 4DLApproved

More from Dacorum Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 MinutesCabinet Agreed the of the previous meeting. Agreed Open
22 Sep 2026 Apologies for absenceThere were no apologies for absence. Decided Open
22 Sep 2026 Declarations of InterestThere were no declarations of Interest Decided Open
22 Sep 2026 Public ParticipationThere was no public participation. Decided Open
22 Sep 2026 Referrals to CabinetThere were no referrals to Cabinet. Decided Open