Appointment of a Principal Contractor for Eastwick Row Development, Hemel Hempstead

Approved Executive 1 paper

Cabinet approved this item on Tuesday 22 September 2020. Below is the council's own wording, with the papers it was decided on.

ItemCA/80/20

Resolved

That the main contract to construct 36 x social rented units at Eastwick Row, Hemel Hempstead be awarded to Jarvis Contracting Limited. 2. That delegated authority be approved to the Council’s Assistant Director (Corporate and Contracted Services) to execute and complete all legal agreements ancillary to the JCT Design & Build Contract and/or reasonably required to complete the Project, including (but not limited to): a. all professional appointments; b. collateral warranties; and c. Agreements under S.38, & S.278, of the Highways Act 1980; S.247, Part III of the Town and Country Planning Act 1990; S.104 of the Water Industry Act 1991, and S.50 of the New Roads and Street Works Act 1991.
Word for word from the decision Dacorum published for this meeting. Source: democracy.dacorum.gov.uk

Follow this further

Built from Dacorum's papers

What the report saysPro

Report to Cabinet

Report for: Cabinet

Date of meeting: 22nd September 2020

Part: I

If Part II, reason:

Title of report: Appointment of Principal Contractor for Eastwick Row, Hemel Hempstead

Contact: Cllr Margaret Griffiths, Portfolio Holder for Housing

Mark Gaynor, Corporate Director Housing and Regeneration

Fiona Williamson, Assistant Director Housing

Nigel Howcutt, Assistant Director Finance and Resources

David Barrett, Housing Development Group Manager

Purpose of report: To be read in conjunction with Part II.

1. To seek approval to award the main contract and appoint a Principal Contractor to construct 36 units at Eastwick Row, Hemel Hempstead.

2. To provide delegated authority to the Council’s Assistant Director (Corporate and Contracted Services) to execute and complete all legal agreements ancillary to the JCT Design & Build Contract and/or reasonably required to complete the Project, including (but not limited to): a. all professional appointments; b. collateral warranties; and c. Agreements under S.38, & S.278, of the Highways Act 1980; S.247, Part III of the Town and Country Planning Act 1990; S.104 of the Water Industry Act 1991, and S.50 of the New Roads and Street Works Act 1991. Recommendations: 1. That the main contract to construct 36 x social rented units at Eastwick Row, Hemel Hempstead be awarded to Jarvis Contracting Limited.

2. That delegated authority be approved to the Council’s Assistant Director (Corporate and Contracted Services) to execute and complete all legal agreements ancillary to the JCT Design & Build Contract and/or reasonably required to complete the Project, including (but not limited to): a. all professional appointments; b. collateral warranties; and c. Agreements under S.38, & S.278, of the Highways Act 1980; S.247, Part III of the Town and Country Planning Act 1990; S.104 of the Water Industry Act 1991, and S.50 of the New Roads and Street Works Act 1991.

Corporate Objectives: Delivering Affordable Housing

Implications: Financial

The overall development budget is reviewed strategically as part of the annual review of the Housing Revenue Account Business Plan. Each individual scheme following contract award is subject to close financial monitoring with any variances agreed formally through a change control process

‘Value For Money Value for Money Implications’ This has been achieved through a successful procurement programme involving an open tender process.

Risk Implications Risk assessments are completed within the new build Project Initiation Document (PID) and reviewed and updated on Project Management Office, on a monthly basis.

A risk assessment is completed for this project by the Employers Agent and reviewed monthly from the award of the contract.

Community Impact A Community Impact assessment is not required as homes are Assessment developed and allocated in line with the demand and to replicate the criteria for assessment, as set out in the Council’s Allocation Policy, which has had a full assessment. The Development includes four Wheelchair units on the ground floor.

Health And Safety Each new build scheme has in place a Principal Designer Implications and Construction Design and Management Regulations (CDM) Advisor. Contractors are required to comply with the Council’s Health and Safety (H&S) policy along with Considerate Constructors requirements. Health and Safety is identified as a key risk of the Housing Service and is reported to the Council’s Housing and Communities Overview and Scrutiny Committee on a quarterly basis. To ensure compliance monthly site checks carried out on behalf of DBC as the client to ensure adherence to H&S procedures.

Monitoring Monitoring Officer: Officer/S.151 Officer Comments The proposed contract award follows a competitive and compliant tender process which demonstrates that the Council is receiving value for money for the contract.

Deputy S.151 Officer

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appointment of a Principal Contractor for Eastwick Row Development, Hemel HempsteadReport 948 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Dacorum

Search all
  1. Appointment of a Principal Contractor for Eastwick Row Development, Hemel HempsteadThis decision
  2. Appointment of Principal Contractor for Paradise Depot, Hemel HempsteadApproved
  3. Appointment of a Principal Contractor for Coniston Road Development, Kings LangleyApproved

More from Dacorum Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 MinutesCabinet Agreed the of the previous meeting. Agreed Open
22 Sep 2026 Apologies for absenceThere were no apologies for absence. Decided Open
22 Sep 2026 Declarations of InterestThere were no declarations of Interest Decided Open
22 Sep 2026 Public ParticipationThere was no public participation. Decided Open
22 Sep 2026 Referrals to CabinetThere were no referrals to Cabinet. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies