Cabinet Agreed: 1. To support the Environment Agency and Affinity Water Ltd in the restoration of the river Gade and improvements to Gadebridge Park project. 2. To approve access to Gadebridge Park for the Environment Agency and its contractors to carry out restoration and improvement works during 2022. 3. To approve, subject to Council, a contribution of up to a maximum of £130,000 for Environmental Amenity works as part of the project. 4. To delegate authority to the Assistant Director Neighbourhood Delivery in consultation with the Portfolio Holder of Environmental Services to agree expenditure up to a maximum of £130,000. 5. To delegate authority to the Assistant Director Neighbourhood Delivery in consultation with the Assistant Director (Corporate and Contracted Services), Legal Governance Management to approve legal agreements and documentation between the Council and the Environment Agency and Affinity Water Ltd.
Word for word from the decision Dacorum published for this meeting.Source: democracy.dacorum.gov.uk
Title of report: River Gade Restoration & Improvement Project in Gadebridge Park Contact: Cllr Graham Barrett, Portfolio Holder for Environmental Services
Author/Responsible Officer: Bill Buckley, Interim Assistant Director (Neighbourhood Delivery) Purpose of report: 1. Cabinet to consider the restoration and diversion scheme of the river Gade channel to prevent flooding within Gadebridge Park and the improvements to environmental amenities of the park. 2. The Environment Agency is seeking a financial contribution of £100-120k from the Council to fund inclusion within the scheme of an additional footbridge, footpaths, beaches etc to enhance the scheme and improve the park. Recommendations That Cabinet
1. Agrees to support the Environment Agency and Affinity Water Ltd in the restoration of the river Gade and improvements to Gadebridge Park project. 2. Approves access to Gadebridge Park for the Environment Agency and its contractors to carry out restoration and improvement works during 2022. 3. Approves, subject to Council, a contribution of up to a maximum of £130,000 for Environmental Amenity works as part of the project. 4. Delegatea authority to the Assistant Director Neighbourhood Delivery in consultation with the Portfolio Holder of Environmental Services to agree expenditure up to a maximum of £130,000. 5. Delegatea authority to the Assistant Director Neighbourhood Delivery in consultation with the Assistant Director (Corporate and Contracted Services), Legal Governance Management to approve legal agreements and documentation between the Council and the Environment Agency and Affinity Water Ltd. Period for post The project will be an ongoing review until completion of the policy/project scheme and for a minimum of 12 months after completion and review prior to physical assets transferring to the Authority Corporate The Project supports two of the Corporate Objectives- objectives: Safe and Clean Environment with and improved recreational and environmental amenity of Gadebridge Park, and
Climate & Ecological Emergency as the realignment of the river into its natural flood plain will reduce the incidence of flooding, improve the water quality and the natural habitat of the wildlife within the river and in the park Implications: Financial
The financial implications are set out within the report below and Cabinet are invited to consider and approve a financial contribution up to a maximum of £130,000 towards the project for environmental amenities within Gadebridge Park. This funding cannot be contained within existing budgets and would have to be found from Council Funds.
‘Value for money’ Value for money implications The procurement process by the Environment Agency will ensure value for money and scrutiny will be by the Assistant Director Neighbourhood Delivery in consultation with the Portfolio Holder for Environmental Services for any financial contribution and expenditure from the Authority Risk implications The main risk is the ability of partners to deliver on the project within the timeframe. So far, we have sought to minimise this risk by gaining buy in to the process from key partners and providing influence over the project. This approach being taken should significantly minimise this risk further to Gadebrige park. Appendix III identifies potential operational risks with mitigations to the Authority.
If Members decide not to contribute, the EA could still go ahead with the diversion of the river without the environmental amenities restricting access to the park for users. Community Impact This has not been completed, as the Environment Agency is Assessment the lead key partner and will complete such an assessment as the project progresses.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.