Cabinet, Tuesday 27 September 2022 at 7.30pm

Appointment of the Principle Contractor for the St Margarets Way Project

Agreed Executive 2 papers

Cabinet agreed this item on Tuesday 27 September 2022. Below is the council's own wording, with the papers it was decided on.

ItemCA/77/21

Resolved

Subject to a satisfactory financial assessment and agreement on contract price in accordance with recommendation 2, and the project achieving formal planning approval, awards the main contract to construct 46 social rented homes to Helix Construct Ltd. 2. Delegates authority to the Strategic Director (Place) and the Chief Finance Officer in consultation with the Portfolio Holder (Place) to carry out a further financial assessment of Helix Construct Ltd and to finalise the contract value with the approved contractor; and 3. Delegated authority to the Assistant Director (Legal & Democratic Services) to execute and complete all legal agreements ancillary to the JCT Design & Build Contract 2016 and/or reasonably required to complete the Project, including (but not limited to): a . all professional appointments; b . collateral warranties; and c. Agreements under; · S.38, & S.278, of the Highways Act 1980; · S.247, Part III of the Town and Country Planning Act 1990; · S.104 of the Water Industry Act 1991, and · S.50 of the New Roads and Street Works Act 1991
Word for word from the decision Dacorum published for this meeting. Source: democracy.dacorum.gov.uk

Follow this further

Built from Dacorum's papers

What the report saysPro

Report to Cabinet

www.dacorum.gov.uk Cabinet

Report for: Cabinet

Title of report: Appointment of Principal Contractor for the construction of 46 dwellings at St. Margaret’s Way

Date: 27th September 2022

Report on behalf Councillor Alan Anderson, Portfolio Holder for Place of: Part: Part I with Part II procurement report annexed If Part II, reason: Appendices: Background Appendix A - Consultant’s Tender Report dated July 2022 papers: Appendix B – Proposed Development Plan

Glossary of ASHPs – Air Source Heat Pumps acronyms and DMC – Development Management Committee any other GF – General Fund abbreviations HRA – Housing Revenue Account used in this ITT – Invitation to Tender report: JCT – Joint Contracts Tribunal

Report Author / Responsible Officer

David Barrett, Head of Development, Housing Development [email protected]

Reuel Thompson, Lead Officer, Housing Development [email protected]

Corporate Priorities  A clean, safe and enjoyable environment  Building strong and vibrant communities  Ensuring economic growth and prosperity  Providing good quality affordable homes, in particular, for those most in need  Ensuring efficient, effective and modern service delivery  Climate and ecological emergency  Wards affected Leverstock Green

Purpose of the report: To be read in conjunction with Part II. 1. To seek approval to award the main contract and appoint a Principal Contractor to construct houses and flats at St. Margaret’s Way, totalling 46 new homes for social rent, including new access road, parking and amenity areas. 2. To provide delegated authority to the Council’s Assistant Director (Legal & Democratic Services) to execute and complete all legal agreements ancillary to the JCT Design & Build Contract 2016 and/or reasonably required to complete the Project, including (but not limited to): a. all professional appointments; b. collateral warranties; and c. Agreements under S.38, & S.278, of the Highways Act 1980; S.247, Part III of the Town and Country Planning Act 1990; S.104 of the Water Industry Act 1991, and S.50 of the New Roads and Street Works Act 1991.

Recommendation (s) to the That Cabinet: decision maker (s): 1. Awards the main contract to construct 46 social rented homes to Helix Construction Ltd., subject to the project achieving formal planning approval. 2. Delegates authority to the Strategic Director – Place and the Chief Finance Officer to finalise the contract value with the approved contractor; and 3. Delegates authority to the Assistant Director (Legal & Democratic Services) to execute and complete all legal agreements ancillary to the JCT Design & Build Contract 2016 and/or reasonably required to complete the Project, including (but not limited to): a. all professional appointments; b. collateral warranties; and c. Agreements under S.38, & S.278, of the Highways Act 1980; S.247, Part III of the Town and Country Planning Act 1990; S.104 of the Water Industry Act 1991, and S.50 of the New Roads and Street Works Act 1991.

Period for post There will be a 12-month defect liability period after practical policy/project review: completion. A 2-year review period is therefore recommended for this project.

1 Introduction/Background:

Since 2013, the Council has delivered 356 new Council homes in the Borough, providing a good record of delivering new homes for social rent.

This report seeks approval for the appointment of the Principal Contractor for the Council’s next project at St. Margaret’s Way.

The proposals include the delivery of 46 new, two and three bed homes, which are a mix of flats and houses on land owned by the Housing Revenue Account and land to be appropriated from the general fund. The proposal will provide an ongoing revenue stream for rental income.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
St. Margarets Way: Proposed Development Plan /77/21Appendix B 2 MB Download
PDF
Appointment of the Principle Contractor for the St Margarets Way ProjectReport 459 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Dacorum

Search all
  1. Appointment of the Principle Contractor for the St Margarets Way ProjectThis decision
  2. Appointment of Principle Contractor for Aragon Close Modular Move On AccommodationAgreed

More from Dacorum Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 MinutesCabinet Agreed the of the previous meeting. Agreed Open
22 Sep 2026 Apologies for absenceThere were no apologies for absence. Decided Open
22 Sep 2026 Declarations of InterestThere were no declarations of Interest Decided Open
22 Sep 2026 Public ParticipationThere was no public participation. Decided Open
22 Sep 2026 Referrals to CabinetThere were no referrals to Cabinet. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies