Cabinet agreed to award an additional one for one receipt grant funding payment of £1,035,146 to Hightown for the development known as 66 Books, Wood Lane End for affordable housing development in the borough. This will result in a total grant funding level of £3,300,000 for this scheme.
Word for word from the decision Dacorum published for this meeting.Source: democracy.dacorum.gov.uk
Report for: Cabinet Title of report: Grant Funding Hightown Housing Scheme – 66 Books, Wood End Lane
Date: 14th February 2023 Report on behalf Councillor Margaret Griffiths, Portfolio Holder for Housing of: Part: I If Part II, reason: N/A Appendices: N/A Background Cabinet report January 2018 (CA/18/18) papers: Glossary N/A
Report Author / Responsible Officer David Barrett - Assistant Director of Strategic Housing & Delivery
Corporate Priorities A clean, safe and enjoyable environment Building strong and vibrant communities Ensuring economic growth and prosperity Providing good quality affordable homes, in particular for those most in need Wards affected Adeyfield East Ward Purpose of the report: To seek approval for the payment of one for one grant funding to Hightown to enable the delivery of 33 affordable housing units at the site known as 66 books. Recommendation (s) to the decision To award an additional one for one receipt grant funding payment of £1,035,146 to Hightown for the maker (s): development known as 66 Books, Wood Lane End for affordable housing development in the borough. This will result in a total grant funding level of £3,300,000 for this scheme. Period for post policy/project review: 2 years 1 Introduction/Background:
In January 2018, Cabinet reached a decision to award £2,264,854 funding via 141 Right to Buy receipts to Hightown for their project called 66 Books. To date £883,819 of funding has been paid to Hightown Housing Association for a 30% contribution towards the acquisition of the land.
The remaining funds were not drawn down by Hightown as the requirement to spend the funding within a 3-year period resulted in the funds being redirected to the Council’s own programme of building new homes. The Council was only ever providing grant towards the funding of 33 rented homes that were not going to be part of the s106 requirement. It was always Hightown’s intention that the remaining units would be funded by Homes England.
Hightown knew that the Council could not fund completed social housing from one for one receipts, (and considered bare land owned by a housing association to be ‘social housing’). They agreed to enter into more than one grant agreement: one for funding towards the land and one for the build, as they knew that they would not be able to buy the land, achieve planning permission and build out the scheme within the 3 year timeframe for spending one for one receipts (as it was at the time).
When Hightown finally achieved planning permission and came back to the Council for further grant, the Council’s one for one receipts had significantly reduced and the grant funding previously agreed was no longer available.
Upon the announcement from Homes England of further affordable homes grant, in September 2020, for the period 2021-2026, Hightown approached Homes England to establish if they would be able to secure any further funding for the affordable units on the scheme. There is a rule around the use of blending one for one grant with other affordable grants and this is not permitted. Hightown were unable to achieve further grant funding via this route for the construction of the affordable units.
Until now, the 33 homes that had low levels of grant, (just the ‘acquisition grant’), that Hightown could not get top up funding from Home England. The 33 units are due to complete in July 2023.
The cost increase is due to rising inflation costs causing an uplift on the cost of construction and the requirement to maximise the grant to assist in achieving the right level of affordability for tenants.
2 Key Issues/proposals
Homes England have asked the Council to consider further funding to enable completion of the 66 Books site, preventing any risk to delivery of the remaining affordable housing units and impacting negatively on provision of accommodation to Dacorum residents.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.