Strategic Planning & Environment Overview & Scrutiny agreed this item on Wednesday 10 January 2024. Below is the council's own wording, with the papers it was decided on.
Agreed 3. That a Dacorum SANG Strategy be prepared to support identified future needs for Council led SANG arising from development. Agreed 4. That delegated authority be sought for the CBSAC Mitigation Strategy decisions set out in table 2. 5. That authority be delegated to the Monitoring Officer to amend the Constitution of Dacorum Borough Council to give effect to recommendation 4 above. Both 4 &5 For 7 Against 6 Abstain1 Recommendations Agreed For full minutes, please refer to the video minutes Media
Word for word from the decision Dacorum published for this meeting.Source: democracy.dacorum.gov.uk
Report to Strategic Planning & Environment Overview & Scrutiny
www.dacorum.gov.uk Strategic Planning & Environment Overview and Scrutiny Committee
Report for: Strategic Planning & Environment Overview and Scrutiny Committee Title of report: Chilterns Beechwoods Special Area of Conservation Mitigation Strategy and Suitable Alternative Natural Greenspace Update Date: 10th January 2024 Report on behalf of: Councillor Sheron Wilkie, Portfolio Holder for Place Part: I If Part II, reason: N/A Appendices: Appendix 1 Community Impact Assessment Background papers: 1. Chilterns Beechwoods Special Area of Conservation: Publication of Mitigation Strategy report to Cabinet 15 November 2022. 2. Chilterns Beechwoods Special Area of Conservation Mitigation Strategy 3. Bunkers Park Suitable Alternative Natural Greenspace Management Plan 4. Chipperfield Common Suitable Alternative Natural Greenspace Management Plan
Glossary of CBSAC: Chilterns Beechwoods Special Area of Conservation acronyms and any CIA: Community Impact Assessment other abbreviations SANG: Suitable Alternative Natural Greenspace used in this report: SAMMS: Strategic Access Management and Monitoring Strategy SSSI: Site of Special Scientific Interest
Report Author / Responsible Officer Sara Whelan, Assistant Director - Planning
Corporate Priorities A clean, safe and enjoyable environment Building strong and vibrant communities Ensuring economic growth and prosperity Climate and ecological emergency Wards affected ALL Purpose of the report: 1. To update members on the implementation of the Chilterns Beechwoods SAC Mitigation Strategy. 2. To seek SPAE views on the proposals for future SANG sites and the delegation of authority for Chilterns Beechwoods SAC Mitigation Strategy related decisions as set out in the recommendations.
Recommendation (s) to the decision maker (s): 1. That the update on CBSAC Mitigation Strategy matters presented be reported to Cabinet. 2. That Gadebridge Park, Margaret Lloyd Park, Howe Grove and an extension to Bunkers Park be considered and if appropriate taken forward as the next phase of Council SANG sites. 3. That a Dacorum SANG Strategy be prepared to support identified future needs for Council led SANG arising from development. 4. That delegated authority be sought for the CBSAC Mitigation Strategy decisions set out in table 2. 5. That authority be delegated to the Monitoring Officer to amend the Constitution of Dacorum Borough Council to give effect to recommendation 4 above.
Period for post policy/project review: 5 years
1 Introduction/Background:
1.1In March 2022, the Council published evidence demonstrating that recreational pressure on the Chilterns Beechwoods Special Area of Conservation (SAC) is impacting the integrity of one of its component parts at Ashridge Commons and Woods Site of Special Scientific Interest (SSSI) (‘Ashridge Estate’) and that there is potential for further deterioration through recreational activity arising from new development. Following advice from Natural England, the Council subsequently stopped permitting net new residential developments across the borough.
1.2In November 2022 Cabinet approved the Chilterns Beechwoods SAC Mitigation Strategy. This sets out the process that the Council applies to ensure developments will not adversely affect the integrity of the CBSAC at Ashridge Estate. Necessary mitigation is secured through contributions for Strategic Access Management and Monitoring Strategy (SAMMS) interventions delivered by the National Trust, funded through a tariff collected from development of £913.88 for each new home built. In addition to this, affected developments also need to provide sufficient Suitable Alternative Natural Greenspace (SANG). This can be delivered directly by the applicant through their own bespoke solution or alternatively they can contribute towards one of the Council’s Strategic SANGs.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Strategic Planning & Environment Overview & Scrutiny at Dacorum and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.