Resolved
Cabinet approved the Q3 2023-24 update on the Strategic Risk Register.
Cabinet approved this item on Tuesday 23 April 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
Cabinet approved the Q3 2023-24 update on the Strategic Risk Register.
www.dacorum.gov.uk Cabinet
Report for: Cabinet Title of report: Strategic Risk Register Q3 2023-24 Date: 23rd April 2024 Report on behalf Councillor Michela Capozzi, Portfolio Holder for Corporate and Commercial of: Services Part: I If Part II, reason: Appendices: Appendix A- Strategic Risk Register Update Q3 2023-24 Appendix B- Risk scoring methodology
Background Cabinet December 2023 Agenda item 8 Strategic Risk Register Update Q1 and papers: Q2 2023-24
Glossary of CEE- Climate and Ecological Emergency acronyms and CLT- Corporate Leadership Team any other DLUHC- Department for Levelling Up, Housing and Communities. abbreviations HRA – Housing Revenue Account. The Council’s Housing Landlord function. used in this HTIP- Housing Transformation and Improvement Programme. A review of report and operational practices within the Housing service. appendices: SLT- Strategic Leadership Team. VCS- Voluntary and Community Sector. VFM- Value for Money.
Report Author / Responsible Officer Fiona Jump, Head of Financial Services
[email protected] / 01442 228162 (ext. 2162)
Corporate Priorities Ensuring efficient, effective and modern service delivery Wards affected All Purpose of the report: To provide committee with an update against the risks identified in the Council’s Strategic Risk Register as at Q3 2023-24.
Recommendation to the decision maker: To approve the Q3 2023-24 update on the Strategic Risk Register.
Period for post policy/project review: An update on the Council’s Strategic Risk Register is provided to Audit Committee and Cabinet on a quarterly basis. 1 Background Robust risk management supports the delivery of the Council’s corporate plan objectives. The Council has a legal obligation to ensure that it has sound risk management arrangements in place. A review of the significant strategic risks impacting the delivery of the Council’s six key corporate plan priorities was undertaken during 2022-23. This review involved Members, the Strategic Leadership Team (SLT), and Corporate Leadership Team (CLT) and the Council’s internal auditors. A revised set of strategic risks were produced as follows, to be reported on from quarter 4, 2022-23:
Risk Risk Owner Failure to ensure compliance with statutory and legislative requirements. Chief Executive Failure to work with Strategic Partners to deliver Corporate priorities Chief Executive The Council is subject to a successful cyber- Strategic Director (People and attack and/ or data breach. Transformation) We are unable to deliver effective services to residents due to an inability to retain and recruit sufficient competent and skilled Strategic Director (People and resources. Transformation) We do not plan in or deliver action early enough to ensure achievement of the CEE Strategic Director (People and statement. Transformation) Inability to manage and deliver safe and good quality affordable homes Strategic Director (Housing and Property) Strategic Director (Corporate and Weakening of the Council’s Financial Commercial Services) Resilience. / Chief Finance Officer Failure to Deliver Place Shaping and Regeneration ambitions. Strategic Director (Place)
Each risk is owned by a member of the Council’s Strategic Leadership Team. Each quarter, they will provide an assessment of the current likelihood and impact/ consequence associated with each risk, together with narrative context. This is explained further below. 2 Strategic Risk Register Update Q3 2023-24
Appendix A provides a detailed update on the Council’s strategic risks as at Q3 2023-24.
Between Q2 2023-24 and Q3 2023-24, there has been movement in the current risk score for the following strategic risk:
Weakening of the Council’s Financial Resilience - the risk score at Q3 2023-24 has been reduced to 4 (previously score of 6 at Q2 2023-24). This reflects progress on mitigation activities against this risk including approval of a balanced budget for 2024-25.
Risk scores against all other strategic risks are unchanged from Q2 2023-24.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
FINAL: Appendix A Strategic Risk Register Q3 2023-24 /40/21Appendix | 673 KB | Download |
PDF |
FINAL: Appendix B Strategic Risk Register Scoring Methodology /40/21Appendix | 318 KB | Download |
PDF |
Quarterly Strategic Risk RegisterReport | 645 KB | DownloadRead as text |
Follow Cabinet at Dacorum and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Sep 2026 | MinutesCabinet Agreed the of the previous meeting. | Agreed | Open |
| 22 Sep 2026 | Apologies for absenceThere were no apologies for absence. | Decided | Open |
| 22 Sep 2026 | Declarations of InterestThere were no declarations of Interest | Decided | Open |
| 22 Sep 2026 | Public ParticipationThere was no public participation. | Decided | Open |
| 22 Sep 2026 | Referrals to CabinetThere were no referrals to Cabinet. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.